Punch List —April 9th 2012
1. Rug Pads — for JE bath & 3 guest rooms on site 4/10
2. Flagpole Pool Cabana —
- Concrete Roads —road transition needs to be reconfigured/flatten out
- Landscaping - remove Bougainvillea & Hydroseed area
- order GeoMat for track from Beach to Flagpole
- Landscape Lighting —require switches/controls for Palm Tree lights
- Fabric - on site, orange piping & pillow for sofa/chairs
via JE's direction to be completed in May
rug on site 4/10
review possibly another piece of furniture - Sarah
3. Five Palms - interior wall requires finishing
- Electrical — genset location determined, need to review Generator
- Floor- material selected, investigating availability
- Door Fabrication — manufacturer on site 4/, expect proposal 4/13
- Lighting Schedule — complete
- Coral Stone Bull Nosing - modeled after MC, ongoing
- Fire Pit —on hold
- Ramp & Road Transition — work continues
- Placement of Parrots— expected completion 4/13
- Moloyanux Painting — to glued to ceiling, cut out light areas, boarded with cornice molding (approx 6 to 8
inches wide) & painted white
- Furniture — review
X 2 cannonball lamps, bronze lamp
- more dirt required
4. Grotto -
- Concrete Steps - ongoing
- Slab & Columns — expected completion 4/13
5. Heli Road — ongoiong
6. Hangar— fill in expansion joints
kitchen wall — installed by 4/13
- Concrete Floor - grinding ongoing
- Painting —interior painting requires
hanger door to be painted white
painting floor
- Purchase Sm Utility Vehicle, for towing Heli
7. Steel Shed - have estimate, Brice to investigate faster ordering approach
8. Triangle
9. Entry Tree Lights — lights on site
10. Solutions for Generators —Brice to investigate other options
construction of wall to start 4/10
11. Top of hill — CLEAN UP — remove rocks & hydroseed
12. Palms - on site, being placed via JE's direction
13. Tiki - Shields — ETA mid May
14. Sunken Garden Berm - continues
15: Main Compound — order GeoMat for track from MC down big hill
16. Bench Placements/Construction — Placement via JE direction. Tom to make 5 benches
17. Engineering —
- Clean Up - continues
- Service Road Reshaping —continues
EFTA00522039
- Landscaping — planting Seagrape
18. New vehicles — two more Polaris bikes (800's) — Larry/Brice
19. Dock-
- Decking - discuss pressure treated timber/carpeting
- Extension - design required
- Floating Dock — design required
- Jetski Docking -
- Table — order? Require direction
20. Mgrs Cottage Roof — continues
21. Mooring Permit — proceeding with bids to place anchors
22. Electrical Quotes — on site, generator to be determined
23. Telephone system — remove/add speed dial — will be completed after visit
24. Gates - to hide engineering both at top and bottom of hill — require location
- Columns — engineered by Tom
- Construction — Brian & John
25. Guest House at Beach 3 — sited, needs to roughed out
26. Kite House — review of wooden outside furnitue
27. Chillax Room — requires furniture piece for electrical/media equipment — Sarah
28. Chilax Bathroom - requires blue rugs for bathroom & vanity area - Sarah
29. Mechanical Building
- Replacement Transformer — approved to purchase
30. Boats
- Midnight Express — 4/2 approved to purchase Yamaha 300 motors
- ship existing motors to FL, LV to sell
- PRD — sell
- Lady G — sell
- Big N - sell
- Calypso — refurbish
31. Sundial — grooves to be cut
32. Hydro seeding — as much as possible especially when it rains
EFTA00522040
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00522039.pdf |
| File Size | 113.2 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,519 characters |
| Indexed | 2026-02-11T22:21:51.976588 |