JE Punch List — November 13, 2012
1. Clean Up - make as many barge runs as necessary
2. Equipment and Vehicles
- Sell equipment
- No machinery off the island unless approved
- Lull — replacement parts — on site. Sub Boom Assembly ETA LSJ 11/16
3. Five Palms
- Picture frame — on site, 86 x 70 — Sarah forwarded 3 proofs for JE to review 11/8, will frame locally
- Wooden Bases — for sculptures — David — in production ETC 11/21
- Mirrored siding — continue to reglue as sections fall off, 2 sections off, area needs to dry before installation can be
completed
- Piano/Stool —to be relocated to hanger after visit
4. Grotto
- Mattress cover — completion delayed due to owner travelling to northeast — completion expected 11/14
5. Berm/Top of Hill
— Brice investigating a wood/paper combination material for hydro-seeding. Distributor found, sourcing material
- Pergola construction for high road benches — David — require design details/number from JE
6. Triangle
- Palms - relocated once Lull is repaired
- Gorilla — to be relocated to top of triangle once Lull is repaired
- Installation of lights — final light installation will be completed once Gorilla is relocated
7. Flagpole Pool Cabana
- Furniture — Desk - ETA STT 12/10
- Area Rug — JE requested 11/7 either soft white with black design or plain white extra soft rug - Sarah
- Pace clock — ordered 2 units due on site 11/8 delay due to Sandy ETA 11/14
8. LSJ Dock
- Dock box top & seat — Installed. Require more coats for UV Protection, which will be completed after visit
- Dock Carpet — David will install early Dec
9. Dock Boxes
- David will attempt to refurbish & replace all rotten lids & bases on existing boxes
10. Chillax Room
— Requires furniture piece for electrical/media equipment - Sarah forwarded another suggestion 11/13
11. Chillax Bathroom
- Walls in vanity area to be painted —JE to select color/style.
- Install Robe Hook on bathroom door —require location/height. Sarah has ordered correct hook 11/11
12. Boats
- Lady G — sell — will remain at Nanny Cay until sold. LV investigating selling in NJ
- Big N — rams/boxes installation & painting — complete. Hydraulic hoses installation & final electrical completion
expected 11/14
- Midnight Express —sell - LV investigating selling in NJ. Advertising locally
— Purchase New Dingy — sourcing locally
13. AC - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees
14. Transient Surge Protection, Blue Storage Bins & Safety Glasses —
Tropical shipped to Nassau in error, customer who received goods is refusing to return items. Awaiting claim forms
from Tropical. Per JE direction reordered 11/09
15. Old Floating Dock —
Break down and Dispose - begin 11/12
16. Landscaping — Peter's List
- Line all Roads with Rocks & Rocks for Waterfall — Top Priority
- Beach 3 — cleaned & graded - work to begin 11/14
EFTA00522066
- Rubbish Dump - regrade, bern placement along side road
- Transformer area on back high road — plant out
- Cutting Flowers/Vegs — Brice has purchased wide variety of seeds - planted 11/11
- Master Planter — JE to speak with Peter when he is back on duty
- Pop's Garden — electric fence — ETA STT 11/14
- David to make planter boxes — in production, 1 complete.
- Black Heli Under Pads — install at top of bike path at MC— Installation to begin 1/10
- Sea Grape — contacted PR sourcing prices expected 11/14
- 20 x 15ft Coconut Palms — for engineering area — ordered 11/9 ETA LSJ 12/1
17. Roads
- General re-grading of roads — ongoing — Peter
- JE requested investigating surfaces that can handle the weight of the heavy equipment
18. Library
- AC quote forwarded to Rich Barnett, who had design concerns. Plans forwarded to Atlanta 10/30, engineer will
answer concerns & develop control designs, EDA 11/16
19. New Employee Bathrooms
- research "outhouse "option
20. Gym
- Old Punching Bag to be reinstalled — complete 11/13
- Glass front fridge on site 11/15 to be installed — David to trim out location
- Ballet Room Windows — chipped. Opener needs gluing — will complete after visit
21. Beach Office
- complete electrical overall required
- waterproofing/sealing/replace rotten wood —Complete
- painting in progress ETC — 11/16
22. LSJ Mooring — Darren spoke with Army Corp 10/17 — still working on environmental report, will forward ASAP
23. Hangar
- Fuel Containment Pad —
24. Steel shed — ETA Tropical shipping 12/3, sailing 12/5 ETA STT 12/8 Container will be emptied on LSJ & stored until
installation crew on site, Construction crew ETA 1/11
- JE requested extra metal sections & roller door to old engineering area — need to approve layout will forward 11/14
- Installation of new bolts — David. Due on site 11/14
25. Equipment/Household Purchase and Delivery
- (3) Terex RL-4000 6kW Light Tower systems — 2 on site, 1 remaining to be picked up 11/16
- (1) 2012 John Deere 5101E tractor with 553 loader and 8' blade — ETA LSJ 11/16
- (1) 2003 Genie Z60/34 Boom lift — EDA Tropical by 11/8 ETA Sailing 11/26
- (1) 2012 JCB 8035Z Mini Excavator purchased - $39,455 — awaiting buckets from UK, one received by vendor, 2 nd due
to vendor 11/16 ETA Tropical 11/19 ETA STT 11/25
- Yellow Black Assort Life Jackets — ordered 11/13
- Floating Pool Mats — for ocean & pool — ordered 11/7 awaiting shipping details
- 20ft Floating Trampoline — ordered 11/7 ETA Tropical 12/29
- Italian Deck Chairs — awaiting shipping/delivery details
- Extra Restoration Hardware Cushions ordered 11/10 awaiting delivery date
- LSJ Mats — for all locations Logo approved 10/16 - in production — EDA STT 11/23
26. Containers — 3 off site. RO & Generators in remaining container, will be removed once Lull repaired
27. Stone Walls
— Repair work to replace missing loose stones — Gerry & TJ working as time permits
- Complete Heli Pad Wall — sub contractor forwarded bid 11/12 scope of work & more details required, awaiting
revised bid
28. Part Time Employees — interview scheduled for 11/16
29. Heli Pad - wind sock for Heli pad on site. New wind sock assembly ETA STT 11/13
EFTA00522067
30. Cisterns — need to be cleaned /sealed. Bid approved 11/8 Work to start after 1/10 expected completion by 11/18
then back to complete the Great Room cistern early Feb
31. Solar — Solar lights to be placed everywhere
- New Solar Vendor on site 11/8 will forward a proposal within 14 days
32. Movie Screen — investigating purchase Stewart Screen & new Blue Ray DVD Player — will review with Larry while on
site 11/141
33: Pebble Beach House — fan ordered 11/8 - ETA NYC 11/23 to be brought down on plane
EFTA00522068
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00522066.pdf |
| File Size | 187.0 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 6,694 characters |
| Indexed | 2026-02-11T22:21:52.316065 |