JE Punch List —October 12, 2012
1. Clean Up - make as many barge runs as necessary
2. Equipment and Vehicles
- Sell equipment
- No machinery off the island unless approved
- New seats for gators, progators, beach cleaner — installed on equipment - COMPLETE
- Red Polaris Bike - Power Steering Module for ordered due NM — incorrect part arrived — LV sourcing in FL
- Beach cleaner —de-rust it, clean it — 95% complete
- Lull — non-operational — mechanic removed broken part, examined for what parts are needed — Brice to advise
whether to replace the broken part or purchase a complete new boom
3. Computers/Phones
- Beach office —Internet, phone, Time Clock operational
4. Five Palms
- Furniture — outside furniture in place — Karen to tied down cushions to resolved wind issues - COMPLETE
- Picture frame — measurements forwarded to Sarah - 86 x 70
- Mirrored siding — will continue to reglue — possible mural work
- Fiber work/Phone — COMPLETE — "fiber secure box" inside 5 Palms - COMPLETE
- Piano re-tuning — Patrick Baron 10/20
5. Grotto
- Mattress cover —JE approved buying fabric — fabric on site
6. Berm/Top of Hill
- Hydroseed outside — in progress
- Reseed all of the top of hill, little seems to be growing — Peter — in progress
7. Triangle
- Must design triangle - awaiting JE direction
- Need to review new palm installation — heli approach with Larry
8. Flagpole Pool Cabana
- Furniture — desk from Paris — JE to select a fabric for seats on site — Sue
- Clock — unit rusted — have ordered 2 new units -1 for backup
- Yellow exercise pole — COMPLETE
- Auto-closer on toilet door — carpenter on site 10/15
- Hanging of paintings from PB — COMPLETE
- Add some lights to the parking area near steps — still dark — COMPLETE
9. Floating Dock
- Jet ski bumpers — complete — reviewing whether this type resolves the issues with the jet skis
- Table/Dock Box - Dock box top investigate possible "rubber material" other possible solution
- Dock boxes — struts should all be replaced —they are all backward —will add to carpentry list
- "Walk the plank" option — review material on this & floating dock — "rubberized material"
10. Chillax Room
— Requires furniture piece for electrical/media equipment, reviewing pieces that are stored in PBI, which do not work,
Sarah to review other options
11. Chillax Bathroom
- require blue rugs for bathroom & vanity area — Sarah
12. Mechanical Building Transformer — on site —Danny to receive bid for removal and installation 10/15
13. Boats
- Lady G — sell — in hurricane storage — offer $60K via JE, Rich to negotiate pricing
- Lady K — sold 10/12 - Road Town Ferries (Tortola) $105K
- Big N — repair — at AYH dock — Bob Kassner submitted invoice 10/12 for deposit to start — will start mobilizing 10/15
- Inside cleaning — COMPLETE
EFTA00522075
- Doors/windows — COMPLETE
- cylinders/boxes — on LSJ 10/12
14. AC - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees
15. Transient Surge Protection — EDA on STT 10/13
16. Landscaping — Peter's List
- High road trees
- High road waterfall — details required
- Line all roads with stones
- Pop's Garden — need deer protection — per JE, fence or electric fence - Danny
- Shade cloth — on Lal — Peter installed one for JE review — per JE "too high" — Peter making adjustments for JE review
- Clean mess, cut grass; trim all vines, acacia — owner's drive, blue beach, gym — work in progress
- Peter to clean the sides of the road — work in progress
- Black Heli Under Pads — install at top of bike path at MC —1,206 sq. ft - sourced at American Export
- Review growth of sea grape - engineering area
- Hydroseed all pull box areas & engineering
- PR Coconut Palms — planted at main entrance, blue beach (5), berm, Five Palms, MBR — COMPLETE
- Take down the ropes at the end of the month on the trees
17. Roads
- General re-grading of roads — ongoing — Peter
- Betteroads quotes from triangle to crest of road above gym — Asphalt - $71,5000, Concrete - $103,600. Brice to
review details with Better Roads — week of 10/1
18. Library
- AC quote forwarded to Rich Barnett, who had design concerns, awaiting reply from vendor
19. New Employee Bathrooms
20. Gym
- New punching bag — installation of the speed bag on hold 9/22 - per JE until visit
- New front & back doors installation — carpenter on site 10/15
- Replace battery in thermostat in gym - COMPLETE
21. Beach Office
- complete electrical overall required
- waterproofing/sealing/painting/replace rotten wood required
22. LSJ Mooring — Darren forwarded to Army Corp for final approval — awaiting response
23. Hangar
- Fuel Containment Pad — draft approved, drainage incorporated —architect returned plans for review,
questions/comments 10/11 - has a few notes and construction details yet to add - will be adding a manual valve-
controlled drain pipe from the sump trench to outfall down the slope from the pad — architect will send updated plans
once the pipe is added — to submit to DPNR for permitting
24. Steel shed — Buck Steel sent out drawings to STT via UPS on 10/12
25. Equipment to be Purchased
- (1) Light generator, (2) arms with lights to be hard wired - quote received from American Export - $19,516.74
- (1) Skid steer on site — require forks, ordered 10/2 — American Export — awaiting delivery to Tropical
- (1) John Deere box and blade — Brice has recommended JD 5101E AWD — loader, scraper, digger, 100hp, enclosed cab
- (1) man-lift
- (2) Golf cars — 2 seater — Golf Car Depot — wire sent 10/12 — delivery to Tropical estimated by 10/17
- (1) dump truck — 2012 Ford F450 - EDA on STT 10/16
- (1) mini excavator — quote received from American Export - $38,900
- (1) Jet Ski trailer — purchased — Island Marine Outfitters — on LSJ 10/12
26. LSJ Mats — for all locations — ordered 9/22
27. Engineering — start emptying/relocating items in remaining 20 foot containers — 2 emptied and leaving LSJ on
10/18
28. Stone Walls — Repair work to replace missing loose stones — Gerry & TJ — Danny to schedule them
EFTA00522076
29. Part Time Employees —focus on finding maids — Karen met with the two applicants on 10/2 — one (Mercedes) Anna
to follow up in obtaining the completed application. Anna has 4 additional potential applicants - will contact them this
weekend and schedule meetings to fill out applications — will forward applicants to Karen to schedule interviews
30. Heli Pad - reinstall windsock to north side of helipad - wind sock for Heli pad on LSJ is ordered and will arrive next
week in Palm Beach
31. Cisterns — need to be cleaned and sealed work to begin 11/1
32. Solar - lights installation COMPLETE - JE does not like the "white light", likes a "soft white" light —JE to review when
on site
- Solar quote reviewed with Rich, submitted to JE 9/17 — now researching line loss on cable, awaiting update
33. Master Bedroom —door sliders require waxing and alignment — carpenter on site 10/15
EFTA00522077
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00522075.pdf |
| File Size | 186.5 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 7,045 characters |
| Indexed | 2026-02-11T22:21:52.382287 |