ESTATE PROGRESS REPORT — November 28, 2003
7151 STREET
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Schedule
Changes to Pinto's schedule: Mirrors are expected early Jan, not
early Dec.
51h Floor
1. Front Room
a. Front room to remain GM's office.
b. Metal table style & 2 arm chairs for GM office.
c. Carpets to be changed.
d. Current furniture to remain.
e. Pinto to specify paint color for trim & interior wall finish.
2. Back Room
a. Back room to eventually become children / nanny room. Pinto
has been informed.
b. Lynn & Jojo are to move into the basement as soon as
construction is complete.
c. Bathroom to stay as is for the time being.
Fax sent to Pinto Nov 24 inquiring when the MBR is to be installed
— no response yet.
Pinto - Jean
Pinto
Pinto
Pinto
6'h Floor
Round table: is in the process of being restored. Expected
completion by Nov 28 — delay due to miscalculation of time frame.
J Burdine
11/28
Ceiling Speakers
No speaker in MBR. Speaker wire in cornices.
Dining Room
1. Table-top: Brian Kelly is storing new rectangular table-top in
his shop until after construction phase.
2. Lighting: JE approved three chandeliers instead of spotlights.
3. Carpet: JE approved green-striped carpet.
Pinto - Jean
EFTA00577479
ESTATE PROGRESS REPORT — November 28, 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
4. Speakers: on dining room ceiling.
Entry Hall
1. Entry hall door: not to be moved.
2. Entry hall marble floor: to remain.
3. Original chandelier to remain but be painted white.
4. JE wants silk banners to hang in front entry hall in front of
Japanese paintings. Pinto to source.
5. JE has samples to select exact shade of pink for the entry hall
walls.
Pinto
JE
Main Stair
1. To be re-carpeted — JE saw sample in Paris & did not approve.
JE to advise if he liked new sample sent by Jean to 7151 St.
2. Sconces to ship from Paris week of Nov 10 — delayed to Dec 8.
3. JE agreed to spotlights for tapestry.
4. Alberto to make shelves to place sculptures or china pot on by
tapestry.
JE
Kitchen Service
Corridor
Kitchen & corridor painted white. Clark to provide prices on
limestone floor. Doug has samples for JE to choose from. Pinto to
send more samples.
Clark / Doug
/ Pinto
Speakers
Speakers from Zorro mended & are in basement of 71i1.
Gym
1. To be painted by painters that are at 7P1 St now not French
painters. Pinto to advise paint scheme.
2. Sample carpet expected by Nov 26.
3. Yoga Room is to remain the same.
4. Gym Bath is to remain the same.
Pinto
2
EFTA00577480
ESTATE PROGRESS REPORT — November 28, 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
MBath
1. MBath carpet: border of original carpet to be left & Jean to
provide new insert. JE chose blue & white carpet. Pinto has
selected carpet & is due to arrive in Feb 2004.
2. Ceiling: complete; scaffold to be removed week of Dec 1.
3. Bed & little table: Pinto to purchase. Pinto has been informed
to ensure that the bed is delivered prior to completion of the MBR
walls so as to make sure the bed fits.
4. Skylight bars - JE advised to dispose of bars. Skylight is being
mended.
Pinto — Jean
Pinto
MBR
1. Windows: approved to be further sound-proofed. Installation to
begin after painting & hoisting of scaffold & carpet through
windows.
2. Plaster sconces are at 71s' Street.
3. Wall paper is due end of Feb.
4. Painting & passageway to be painted to match Bedroom. Pinto
to confirm paint color.
5. Decorative painting in progress — completion in Dec.
Doug
Pinto
Pinto - Jean
Mirrors
Second floor landing: Mirrors to be delivered to house Dec 8 —
delayed to Jan 8. Awaiting response from Pinto re installation.
Pinto
Oriental Rug
Expected completion by Dec.
Costikyan
Technology
1. Security: Surveillance Cameras (3rd Floor): wiring complete.
Cameras to be installed once construction near completion. PTV
camera outside building installed. Night vision camera installed &
tested. Installation is in progress.
3
EFTA00577481
ESTATE PROGRESS REPORT — November 28, 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
2. Computer: Upgrade for Landis BMS — complete. Software has
been loaded on new computer, new graphics installed & complete.
Static IP address for offsite connection installed.
3. Computer Networking — WIFI entire house. Complete except
in areas under construction.
4. MBR A/C Upgrade: JE approved MBR fan & cooling tower
upgrade - revised total of $87,022.66 includes electrical, ABB
Drive, & engineering fees (with design plans for chiller). Awaiting
cost for adding a separate control panel for Landis to hook system
up to BMS — proposal expected by Nov 18 — delayed.
Complete
Terrace
Jean to come up with new suggestion.
Pinto - Jean
Bio Gear
2 medium, 1 large biosuits ordered. 1L at 65th St, to be sent to 71st
St. The 2M are backordered until Jan 21. Steve Joslin, who
ordered the suits, not able as of Nov 21 to source other suppliers
for earlier delivery.
Dupont
delay
Blackout Update
Since the Black Out the following Emergency Systems have been
checked or tested to assure proper operation in the event of a power
failure. The following list contains the results of these tests.
1. Emergency Generator: cooling radiator to be cleaned & flushed.
To be done on next maintenance check — not urgent.
2. Battery Lighting Inverter - battery racks & all 48 batteries are
still on order.
Cummings
Metro Power
11/7
4
EFTA00577482
ESTATE PROGRESS REPORT — November 28, 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
3. Otis: Inspection of the elevator is complete.
FYI: In an
emergency / electrical problem, the lift automatically goes to the
ground floor & the doors stay open.
A regular phone line needs to be installed in the lift — Rich to
organize.
Rich
Massage Room
Ceiling
Ceiling to be painted with clouds by the same painters being used
for the MBR woodwork. To be scheduled with painters when Jean
on site Dec 5.
Living Room
Fire Screen: Jean was told to order one.
Pinto - Jean
Nextel phones
The problem when JE was trying to ring
was that
had
forgotten her phone in the bathroom. JE to advise if any further
problems with this system exist.
JE
5
EFTA00577483
ESTATE PROGRESS REPORT — November 28, 2003
457 MADISON
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Office Dividers
Estimate & floor plan without new desks is in. Estimate & plan with
new desks expected by Nov 12 — delayed due to H Miller
accommodating changes & awaiting window tint selection. JE to
advise on window samples which were taken to LSJ on last trip.
H Miller / JE
Office Computers 1. Upgrade / change computers, new programs.
Approved: 20 computers to be re-vamped.
a. LSJ & Z computers ordered & expected by Nov 21 — not arrived
yet.
b. Other new computers: 6 to be ordered.
c. 10 computers remaining to be upgraded as needed.
JE to advise fate of replaced computers: Should they go into 301?
2. Approved Microsoft Project & hardware upgrades. Solomon
accounting system was rejected. Marc is assembling an on-line
training package to familiarize project managers with the new
system. New servers are being installed on Dec 1.
JE
Marc / Eric
Conference Room Jeff Schantz's room to be turned into a conference room.
I. 8 Lucite chairs have been ordered week — expected by Dec 12.
2. Rich to order collapsible table.
3. Cabinets to be removed from room by Dec 12.
Kartcll
Rich
12/12
Blackberry's
All key personnel,
Larry V, Larry M, Dave Rodgers should
have Blackberry's.
6
EFTA00577484
ESTATE PROGRESS REPORT — November 28, 2003
PALM BEACH
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Renovations
1. Doug, Pascal, & Marsh met in PB.
Doug to interview 4
construction company candidates on Dec 1 in PB.
Construction to commence in Feb 2004 as planned.
2. Doug has received the plans for enlarging the breakfast room
from Pascal.
3. JE is considering putting up wooden shutters with in the house.
4. JE to advise if a house is to be rented.
5. No work has been done on the Cabana. According to Pascal, he
was not aware that any work was requested to be done on it. JE to
advise next action.
Doug
JE
JE
Air Conditioning Approved - Cassidy proposal to remove pink room from main
house unit & put on a separate unit so that each guest room has
their own unit. To be done during construction phase.
Cassidy has replaced the air ventilator grills in MBR to reduce
excess noise.
Cassidy
Complete
Painting
Dock
Approved - Dock has been sanded & varnished on Nov 21, dry by
Nov 23.
Complete
JE to view
1999 Merc 5600
5600 mechanical work is complete. Currently being worked on
cosmetically (dent removal & repainting) - expected completion by
Nov 24 — delayed to Nov 26.
11/24
11/26
7
EFTA00577485
ESTATE PROGRESS REPORT — November 28, 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
1997 Merc
Stereo is malfunctioning & is being replaced Nov 25. C.D. unit is
being replaced as well since this unit is not compatible with the
new stereo.
Red Jeep
Jeep is in shop for repairs — expected completion by Dec 5.
12/5
Landscaping
Approved - Stopek has planted aromatic flowers (hedychium) by
the pink gate.
Complete
JE to view
Outside Table
Section of frosted table top is eroded — replacement panel has been
ordered from Italy & is due in PB by Dec 12.
12/12
a
EFTA00577486
ESTATE PROGRESS REPORT — November 28, 2003
PARIS
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
JE office
Horseshoe table /Ash tray is still expected in December.
Pinto - Jean
Kitchen
A/C to be fixed in conjunction with construction. Work to begin
Nov 25 & will take approx 3 weeks.
Pinto
12/16
Living Room
Separation to be added to round end of living room & new section
to be converted into MBR sitting room. Jean met with cabinet
maker & decided on custom made light Italian metal covered in
fabric. FYI: it will take 6 months to make.
Pinto — Jean
Shower Pump
Pressure
3 valves & 3 shower heads have been installed & according to
Valsdon, there is a "positive improvement."
Complete
Bath
JE agreed to new plan for Bath: more cabinets & drawers & a
decorative paint scheme on screen.
9
EFTA00577487
ESTATE PROGRESS REPORT — November 28, 2003
PARIS - NEW APARTMENT
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Construction
Demolition has commenced. Expected completion in April 2004.
Original plumber retained. Updated schedule expected by Dec 5 —
Serge said there will be delay in construction due to JE's
adjustments for the bathroom.
Pinto - Jean
Gym Room
JE discussed with Pinto on site & decided on wall sconces &
double doors.
Pinto - Jean
10
EFTA00577488
ESTATE PROGRESS REPORT — November 28, 2003
PLANES
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
727 Boeing
1. Larry M awaiting fabric selection for office chair. JE to advise. JE
2. Shower water heater & control has removed & is being repaired
To be reinstalled while stripe change is being made.
3. JE requested painted stripe on the exterior to be modified — to
be done (except for full length stripe) week of Dec 1 in PB in
conjunction with shower reassembly & other minor maintenance
tasks — approx 3 day down.
a. The top 1/4" beige to become a 1/2" red touching the top
blue stripe full length.
b. The blue stripes to be lengthened at the leading edge by 1/2".
c. The white stripes to become red.
d. Changes to fuselage stripe will be duplicated on the tail.
Bell
1. Larry V is confirmed for Bell maintenance course Dec 1-12.
Helicopter
2. Larry V needs Pilot training for helicopter no later than end of Larry
Jan. Larry to advise re: dates during his maint course training.
3. Recurrent training: Gary & Maria have completed course.
Nicholas is scheduled for Dec 8-9.
4. a. Nicholas will be off island Dec 5-9 & Dec 26 — Jan 3.
b. Maria will be available Dec 1 — 26.
EFTA00577489
ESTATE PROGRESS REPORT — November 28, 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
c. Gary will be available Dec 1— 30.
Gulfstreatn
No. 2 GEE engine has been installed. JE advised for Gulfstream
to be picked up after Thanksgiving
12
EFTA00577490
ESTATE PROGRESS REPORT — November 28, 2003
STAFF
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Rick Harrington
JE to advise if there is any further action to be taken?
JE
Personal
Requests
Nicholas would like to use the Dive Boat that is for sale from
Dec 26 — Jan 3 to take his family to Anagada for New Year's. GM
recommends no.
13
EFTA00577491
ESTATE PROGRESS REPORT — November 28, 2003
MISCELLANEOUS
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Directories
Personalized directories for the houses have been completed.
JE has revised sample metal binder. JE to confirm approval.
4 weeks to completion.
JE
NetJets / Flight
Options
As of Nov 24, Kocher & other parties are still working on this
matter.
Kocher
Suburban
2004 Suburban for NY has been ordered. Expected by Dec 1.
12/1
14
EFTA00577492
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00577479.pdf |
| File Size | 697.9 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 13,236 characters |
| Indexed | 2026-02-11T22:48:32.024304 |