ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
DOCK
Floating Platform and
Dock
Additional 2 steps per JE design have been added.
Complete
GYM
Cement outside
Tile to be installed outside gym to increase cement. JE to
supply drawing of area in order to start project. Per JE, on hold.
On Hold
Dip and Chin
Machine
Approved - Standing Body Masters. Ordered & expected in
Miami by Dec 8 — then to ship to LSJ.
Stereo
System installed. JE approved set-up / location / stereo while
on site. Speaker cables to be hidden by Dec 12.
Miles
12/12
MAIN CURRENT HOUSE
Spot Lights
Installed additional lights to illuminate terrace courtyard below
Great Room.
Complete
Lanterns
Lanterns in France for LSJ have been damaged in shipment —
Pinto advised that re-storing will be too expensive & lengthy in
time. They have been re-ordered — no delivery date yet.
Pinto
Lights
Lights that shine up & down to replace glass hurricane lamps
located outside of the house. JE chose 6" diameter ones. Miles
hung. Please see attached photos. *A-1
Complete
Courtyard Lights
Removed sample and reverted to original spot light.
Complete
EFTA00577493
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Courtyard
Paint high gloss blue stripes 2" wide with 9" white squares in
between stripes. Paint small section first for JE to see &
approve. Photo to follow. If approved, completion by Dec 3.
Great Room
1. Screen installed. Projector faulty — has been mended in NY.
Sound Experience has installed.
2. Ceiling fans extension poles reduced.
3.1 amp to be installed.
4. Black out curtains for windows — black cloth to be draped
behind movie screen to create total darkness.
Complete
Complete
Christmas lights
Christmas lights to be installed in large trees for the season. JE
advised to use Japanese lanterns in addition to Xmas lights.
1. Lanterns have been ordered & are expected in NY by Nov 29.
2. Xmas lights have been purchased & have been taken to LSJ
on Nov 21.
3. Lanterns from David Tang have arrived & will go to LSJ on
next trip.
12/16
11/29
Kitchen & Office
Doors
Change double doors to single doors. Doors too heavy to act as
single door. The good-looking hinges are not sturdy enough.
Per JE, make up sample of double door for JE to view.
Woodshop
12/11
Kitchen Salamander
Attempt by technician to install was unsuccessful — shelve
above stove to be reconfigured. Correct mounting brackets
received Nov 19 — installation by Dec 5.
Bruce White
11/14
12x'5
2
EFTA00577494
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Trellis Screen on
Terrace
External trellis around Great Room to enclose complete arches
has been completed.
Complete
Bed Mattress
Per JE, mattresses in Bedrooms 1 & 3 have been replaced.
Complete
Picture Frame
Per JE, additional picture frame for bedroom 1 to be made up
locally. Framer is working off sample frame.
Framer
11/26
Flag Pole Generator
Burnt out due to rain. Replacement part is $2000.00 including
shipping. JE to approve.
JE
GUEST ROOMS
Bath Rooms
All faucets to be changed to same as MBath — 5 sets ordered —
awaiting delivery dates.
MASTER BEDROOM
MBR Stairs Down to
Beach
Top half of stairs completed.
Complete
Shoe Rack
6 & 7 foot chrome shoe rack / metal shelving - more options
being sourced.
GM / Pinto
Steam Room
Doug is currently preparing a drawing to send to Miles. Miles
advises that there are no local shower door companies on STT.
JE to advise how Miles should proceed.
Doug
JE
Master Bedroom
Bathroom
Bathroom fixtures:
1 — Waterworks sink faucets: have been installed.
2 — Grohe shower fixtures: 1 of 9 pieces has been taken to LSJ
Bruce White
Complete
3
EFTA00577495
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
on Nov 21. The remaining 8 shipped by manufacturer to LSJ on
Nov 24.
3 — Czech & Speake bath fixtures were special-ordered & are
expected at 65th St by Dec 3.
Bathroom Door
Self-closing hinge installed on MBR toilet door.
Complete
Floating Dock
Miles spoke to Larry V & they suggest that since it has been
difficult to find a manufacturer that supplies docks that can
withstand saltwater conditions, the best alternative is to have
one built in the same fashion as the jet ski dock, a floating
modular system. JE to advise if to proceed once the jet ski dock
has been received & assembled & JE has viewed it. Alternative
source of floating dock sent to JE.
JE on site
Hot Water
Replaced elements and thermostats.
Complete
Dressing Room
Lights
2 floor lights to be moved from bedroom into dressing room. JE
to source & buy 2 new lights for bedroom.
JE
LANDSCAPING / IRRIGATION
Gym planting area
Coconut and flamboyant trees have been planted in areas
marked by JE. Per JE, marked areas replanted.
Complete
Wall — Old Heli Pad
Construction of the wall to hide old helicopter pad & Coconut
tree planting on the inside of wall are complete.
Complete
Coconut Trees
Approved - 50 trees have been planted.
Complete
4
EFTA00577496
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
New Entrance Road
Coconut trees planted on hill to hide sea and engineering view.
Per JE, statue has been moved & marked areas replanted.
Please see attached photo. *A-2
Complete
Complete
Big Trees
Approved - 100 trees. 32 planted. JE advises that the balance
must be purchased and planted in same area to create one area
of color. (Miles sd that he was not sure now whether he should
buy the trees as apparently JE sd that the whole area needs to be
designed by Madison Cox to achieve a structured terrace look).
The area is also possible site for orchard. Per JE, on hold.
Matt
Mahaffey
On hold
Fniit Tree Orchard
Madison has forwarded to Matt all information re: selected fruit
trees, planting site, orchard layout & future maintenance. Matt
felt that the list was not varied enough — he wants to add
pineapples, cinnamon trees, & more. JE approved list. Matt to
liaison with MC to purchase. Per JE, on hold.
Madison /
Matt
Mahaffey
On hold
Gabion Baskets
Approved - Gabion Baskets - 20 each of each of two sizes have
been ordered.
Main Beach Entrance Main beach entrance has been reworked per F Goffinette's plan.
Per JE, marked areas have been replanted.
Complete
Great Room St. John
View
Per JE, coconut trees to be relocated — completion by Dec 5.
12/5
Iguana Intersection
Rock wall to be extended 20 feet on both sides & lowered —
expected completion by Dec 5.
12/5
5
EFTA00577497
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Helipad
1. All bush & grass to be pruned / cut &
2. Oleander plants to be repositioned.
3. "Dog cemetery-like plants" to be removed.
11/26
11/26
11/26
POOL
Rock at Swimming
Pool
1. Madison drawing sent in Oct 3 report.
2. Rock top has been lowered.
3. Rock wall has been leveled with flat stones.
4. Plexi-glass screen erected — upper wooden bracket removed.
Please see attached photo. *A-3
5. Stone threshold to be built between pillars by Dec 5.
12/5
Complete
Complete
Complete
Pool Terrace Pergola
Madison submitted shading options:
1. JE has declined Madison's estimates of sample shading
devices.
2. Madison shipped Bamboo sample panels to LSJ but were
rejected by JE as JE does not think bamboo is suitable.
JE to advise next action.
.1 L
Pool steps
Rubber strips to be put on pool steps. Miles contacted pool
supplier in STT to source & provide information by Dec 5
12/5
Windscreen
1. Windscreen was moved behind plants.
2. Matt to replant area with colorful plants by Dec 5.
Matt
12/5
Complete
Seat in Rock
1. Bimini to be built with chrome or polished aluminum poles to
cover seating area. Miles does not understand what JE wants so
requests drawing to give to someone to make. JE to advise.
JE
6
EFTA00577498
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
2. Rock seating needs to be re-covered & fabric needs to be
purchased — can be made on LSJ. GM to purchase.
GM
BEACH
Tiki House Thatch
Replacement thatch on LSJ — to be installed by Dec 19.
Woodshop
12/19
Security Lights
Large temporary diesel-powered lighting system - 2 light towers
ordered & expected in STT by Dec 5. Cost of each is $6,825.
12/5
NANNA
4 Stroke Engines
JE advised to wait until Jan.
On hold
Upgrade and Repairs
Nanna is in the water.
Requires minor electrical upgrade to repair the wires to the
radar & horns. In progress.
Cabin area broken/fiberglass cracked for no apparent reason. JE
advises repair as soon as possible as Boscoe reports damage is
serious. Nanna hauled out at LSJ. Fiberglass repaired.
Aluminum panel cut and sent to be powder-coated red, per JE.
Re-carpeting will commence once boat operational.
Boscoe
In progress
12/19
Hi-Fi Speakers
Replace speakers as necessary.
Boscoe
11/17
Cover
Approved - $3500 for full storage cover for Nanna - to be used
for protection between visits. FYI: the cover has a 2 month
delivery time — expected completion in late Jan.
Boscoe
1/31
7
EFTA00577499
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
SEAMORE
Listing
Seamore for sale at $250,000.00. Seamore has been listed in St.
Thomas Yacht Sales books. No interest shown in boat to date.
Boscoe
Complete
CALYPSO
Calypso Boat
JE advised to re-cover seats in red & redo bottom paint.
Approved - $2475 to re-cover seats. Deposit delivered to
builder Nov 19. All wood backing material sent to supplier to
be upholstered.
Bottom paint to be redone once Nanna back in water.
Boscoe
JET SKI
Jet Ski Clips
JE to view current 3 inch jet ski clips that hold jet skis in place
on next visit & advise if he prefers larger ones.
JE on site
Jet Ski
JE approved one jet ski - $10,250 — jet ski on LSJ. Cover
delivered. Trailer on LSJ. Floating dock for jet ski is complete.
Complete
CART PATHS
Slip Road to Gym
1. New road to the gym has been cut, stone work around
triangle completed & cactus garden planted. Coconut trees
planted in triangle.
2. Stone walls in that area reworked to make them similar to the
new walls.
Complete
Complete
Approach Road to
Gym
1. Width of road near the gym entrance reduced. Combined
with slip road to gym/helipad. Rebuilt road to helipad.
Complete
8
EFTA00577500
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
2. Per JE, stonework to continue to link up with the intersection.
In progress.
3. Statue has been moved & area replanted. Please see attached
photo. *A-2
Miles
In progress
11/28
12/5
Complete
NEW BUILDING SITES
Cactus Clearing
Approved - 3 guys hired to do cactus removal until the job is
done. Estimate 2 to 3 months to complete initial phase of
project.
Matt
Ongoing
Red Shed
1. Create path and move Red Shed to new position as marked by
JE has been completed.
2. Approved - $392.90 for solar powered extractor fan. Ordered
& expected in PB by Nov. 24.
Complete
Cleared Area Seeding Cleared area has been seeded.
Complete
Deer
JE advised Miles to dart deer & move them to Great St. James.
Guns and darts on LSJ, no tranquilizer. Matt has contacted
local vet to provide tranquilizer. Vet to be on site to supervise -
project to be completed by Dec 12.
Matt
12/12
Surveyor
Moseley on island Oct 30 & surveyed points marked by JE and
Khan. Results have been emailed to architect and JE.
JE requested additional contour lines to be surveyed as marked
on plans — expected completion by Dec 5.
Mosely
12/5
Marking Poles
JE requested 100 4-ft rebar poles & 30 x 10 ft white pvc poles
with spray paint & tape.
Bruce
11/26
9
EFTA00577501
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
TECHNOLOGY/
MISC
Digital Phone System Marc spoke to Steve Scully & Scully says there are still some
extensions that are analog (only on the voice side, data is all
digital). As of Nov 18, Vitel Co claims there is a problem in
converting channel banks to all digital. Scully looking into
taking Vitel Co to the Public Works Commission to force them
to convert to all digital. Update to follow.
Scully
Generators
1. Approved - new generator on LSJ. Installation to be linked to
upgrade of electrical panel.
2. Upgrading exiting panel from 300 amps to 600 amps — JE
approved M Glidden quote. Installation date to be determined
once Glidden informs Rich of time frame for receiving panel &
installing so as not to interfere with JE's Christmas plans.
Boscoe /
Miles / M.
Glidden
M Glidden /
Rich
12/31
Curtains — Beach
Office
New white gauze fabric delivered to Fabric Mill on St. John to
make up curtains - will not be completed until after Christmas.
12/26
Chaise Lounge /
Furniture — MH
Chaise Lounge - Pinto to decide on furniture.
Plastic Pots
Approved -10 pots from Conran shop purchased. Conran shop
made a mistake and thought the pots were in the US when they
were ordered - they are still in Italy — expected by Dec 12.
12/12
Redecoration
Wicker furniture options — Pinto.
Pinto
10
EFTA00577502
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Radio on LSJ for St.
John Rescue
Approved - installation of St. John Rescue radio in a building on
LSJ.
Hoffman & Darren have reviewed the SJR agreement for
liability issues & forwarded to St. John Rescue for signature.
Per P Hoffman Nov 18, signed agreement sent to Darren.
P Hoffinan /
St. John
Rescue
Island Grill
Viking Grill: Doug has specs so that he can draw it up — and
give it to Miles to have a price quote for building it
Doug
Light House
Architect is in the process of drawing up blueprints. He was
told that the light house would be erected on solid rock & does
not require soil borings anymore. Please see attached proposal
& estimate. JE to advise.
JE
Bunk Beds
JE to advise which bunk beds to purchase. On hold until after
New Year.
On Hold
Underwater Lights
Per JE, Miles to source alternative lights.
Miles
Miscellaneous
According to the VI Environmental Protection Agency, LSJ has
no Discharge Permit & the present Intake Permit is incomplete.
EPA has requested that LSJ reapply for both permits ASAP.
The application forms were hand-delivered to P Hoffinan's
office. P Hoffman (Oct 29) sd he will teleconference with
P Gandy & Amy Dempsey week of Nov 10 re: the applications.
Per P. Hoffman Nov 18 - no update.
11
EFTA00577503
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Think Cars
Larry is researching if any are available in Europe.
Larry
Pool Cushions /
Lawn Furniture
Pool cushions & lawn furniture are on LSJ.
Complete
Dobermans
Per JE, training to be conducted on LSJ. Initial training
completed. Trainer requests up to two more sessions to
complete - to occur between JE visits.
GM /
GM
TO PROGRESS
1. Buy more incense.
Please advise how GM and
should progress...
1. Master bedroom shower and bath light.
2. Master bedroom carpet/bathmats.
3. Outdoor lights for bedrooms/buildings
4. Master bedroom wall sconces.
ARCHITECT
Shade House
Bill Karr to look at shade house.
Karr
Giant terrace
Bill Karr to look at giant terrace.
Karr
12
EFTA00577504
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
ITEMS KRAUS-MANNING WAS RESPOSIBLE FOR
JE to advise how he wishes the following items previously
handled by K-M to be handled from this point forward. Last
accessible report from K-M from Aug 29 sent in Oct 3 report.
JE
1. Solar Power/ Wind Power for huts
2. Fat Cat stairs
3. Media House location
4. Swim deck
5. Underwater lights
6. Dock house
7. Great room terracing
8. Renovation of VIP guest quarters
9. Security lights
10. Grotto
11. Pirelli-Jacobs contract
12. WAPA agreements
13. Redesign woodshop & vehicle storage shed
14. New Power plant / fuel storage facility
15. RO & WWTP
16. Corp of engineers
17. Permitting plan
18. Design management: civil, structural, and mechanical,
electrical & plumbing engineers.
13
EFTA00577505
ESTATE PROGRESS REPORT — November 28, 2003
LSJ
FOR GM EYES ONLY
LSJ
MISCELLANEOUS
Tiki House
Two arm chairs and foot stools - awaiting quotes to recover.
Fabric? JEE attached quote.
GM /
Yellow House
Headboard in St. John for covering. Completed and returned to
LSJ.
Complete
Beach Office
Fabric for curtains being made up in St. John. Price $440.00.
12/26
14
EFTA00577506
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00577493.pdf |
| File Size | 859.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 17,060 characters |
| Indexed | 2026-02-11T22:48:32.075890 |