ESTATE PROGRESS REPORT - SEPTEMBER 26, 2003
ZORRO
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Boulder Lights
1. RMC (installation co) quotes: $12, 827.62 for wiring or
$22,822.28 for wiring & lights. JE approved these lights
however, waiting to see if Cox's lights are better.
2. Lights recommended by Madison on site. Unable to wire-up
due to their large size & energy requirements (need electrician to
wire-up).
Brice to speak to Madison week of Sept 29 to come up with better
ideas / solution.
Brice /
Madison
Chess Set Lights
Lights recommended by Madison are on site. Unable to wire up
due to their large size & energy requirements (need electrician to
wire-up).
Brice to speak to Madison week of Sept 29 to come up with better
ideas / solution.
Brice /
Madison
Caboose
Gandydancer is only co in NM that is willing to do this project.
Their engineers advise for a concrete pad to be laid down due to
the ground instability of the new site.
New Colorado co. to be scheduled to make site visit for second
opinion / proposal.
Fountain in
Estancia
1. Daniel R to design & forward to Pinto for approval.
2. Madison Cox submitted drawings. Plans sent in Sept 19 report.
Daniel R
I
EFTA00577545
ESTATE PROGRESS REPORT - SEPTEMBER 26.2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
3. More tile selections for fountain — samples / book FedEx'd to
7P. JE to advise if likes any.
JE requested possible removal of Pinion Tree / adding more trees.
JE
Front Entrance
1. Madison submitted drawings. Plans sent in Sept 19 report.
2. JE requested additional Ponderosa Pines to produce a mirror
image. Estimate per tree sent in Sept 19 report. JE to approve.
If this project is approved will require estimates for cutting
concert and additional irrigation.
JE
Estancia
Fountain -
Mushroom
Nozzle
Extension added & water pressure increased, still maintaining
mushroom-shaped water flow.
Complete
JE to view
Horse Fountain
No Decision
On hole
Landscaping
Main House
1. Replacement of 20 Pinion trees to be completed by Oct 8.
2. Replacement trees for the Pool Area - JE said no to trees,
maybe fountain. JE to advise further action.
3. Does JE wish to have existing planting beds tiled in? Please
see attached photos for reference. *A-2
S. de Cristo
JE
JE
10!8
Ranch Vehicles
NY Suburban to be sent to Zorro & 2004 Suburban to be
purchased for NY.
2
EFTA00577546
ESTATE PROGRESS REPORT - SEPTEMBER 26.2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Water Issues —
Dakota Well
1. MBI on site Sept 26 to attempt one last repair on 10,000.00
gallon tank. Results known after tank fills with water by Sept 27.
2. Fencing around Evaporation Pond began Sept 22. Expected
completion by Oct 5.
MBI
Zorro Ranch
9/27
10/5
Container
Shipped from
NYC
1. Two urns to be placed outside at MH by Oct 3.
2. "Lion eating ram sculpture" to be placed on table outside LR
by Oct 3.
3. JE to advise location of rugs on next visit.
Karen
Karen
JE
10;'3
10;'3
Main House
Water Treatment
Proposals on site. 66-page proposal submitted. Proposal sent to
Darren for his review. G — Darren wasn't in today.
Pool -
Pool Heater
New Pool Heater on site, removal/installation to began Sept 15.
Expected completion by Sept 29.
Hermersons
9/29
Spa Leaking
1. Hermersons scheduled to look at first week of Oct.
2. Unit has been emptied & power washed. Will assess
re-grouting in conjunction with leak repair.
Hermersons
10/3
Dunlavy Speakers 1. Speakers are at 7P' St.
2. Repair on tweeters to be completed in NYC. Rich awaiting call
from repair person to coordinate.
3
EFTA00577547
ESTATE PROGRESS REPORT - SEPTEMBER 26 2003
LOCATION
COMMENT
NEXT
ACTION BY
DATE
BY
REVISED
DATE
Wiring of New
Speakers in
Library
Rewire & hide all cabling within wall lines, rather than under area
& furniture. FYI: Some furniture & baseboards will have to be
pulled from room. The existing speaker wire is too small for the
new speakers. JE to confirm this is what he wants done.
Please see attached photos for reference. *A-3
JE
Clay Target
Throwers
JE to advise if to purchase a proper clay target thrower. Please
see attached options. *A-4
JE
Painting MH
MH Picture Window has been repainted. Please see attached
photos. *A-5
Complete
JE to view
4
EFTA00577548
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00577545.pdf |
| File Size | 228.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 4,397 characters |
| Indexed | 2026-02-11T22:48:32.385235 |