EFTA00583141.pdf
PDF Source (No Download)
Extracted Text (OCR)
IN THE SUPERIOR COURT OF THE VIRGIN ISLANDS
DISTRICT OF ST. THOMAS & ST. JOHN
**********************************
GREAT ST. JIM, LLC,
)
)
Plaintiff,
)
)
v.
)
)
DEPARTMENT OF PLANNING AND
)
NATURAL RESOURCES and DAWN HENRY )
In Her Official Capacity as Commissioner of the )
Department of Planning and Natural Resources, )
)
Defendants.
)
)
CIVIL NO.
12017
COMPLAINT
COMES NOW Plaintiff Great St. Jim, LLC, by and through its undersigned counsel,
ICELLERHALS FERGUSON KROBLIN PLLC, and for its Complaint against the Department of
Planning and Natural Resources and Commissioner Dawn Henry, states and alleges as follows:
PARTIES & JURISDICTION
1. Plaintiff Great St. Jim, LLC ("GSJ") is a limited liability company organized under
the laws of the U.S. Virgin Islands.
2. Upon information and belief, Defendant the Department of Planning and Natural
Resources ("DPNR") is an instrumentality of the Government of the U.S. Virgin
Islands.
3. Defendant Dawn Henry is the Commissioner of Defendant DPNR.
4. This is a civil action for breach of contract, breach of the implied covenant of good
faith and fair dealing, declaratory judgment, and equitable relief over which this
Court has jurisdiction pursuant to 4 V.I.C. § 76.
EFTA00583141
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 2
5. Venue is proper in this Court pursuant to 4 V.I.C. § 78, as the District of St. Thomas
& St. John is the judicial division where the cause of action arose and where
Defendants may be served.
FACTS
The Settlement Agreement
6. GSJ is the owner of the island known as Great St. James, located within the U.S.
Virgin Islands, which is the site of activity in issue.
7. In April of 2016, DPNR issued Notice of Violation identified as NOVA-04-16-STT
("Notice of Violation") to GSJ seeking an exorbitant, unprecedented, and unjustified
assessment of Two Hundred Eighty Thousand Dollars ($280,000.00) for what DPNR
alleged were violations of the Coastal Zone Management Act on the island of Great
St. James. [EXHIBIT A]
8. GSJ vehemently contested both the alleged violations and the outrageous assessment
as unjustified and well outside the scope of DPNR's authority, and negotiations
between the parties ensued.
9. On August 4, 2016, in an attempt to expeditiously resolve the Notice of Violation and
move on with its plans for Great St. James, GSJ entered into a Settlement Agreement
with DPNR regarding the challenged violations and assessment asserted in the Notice
of Violation (the "Settlement Agreement"). [EXHIBIT B]
10. As part of the Settlement Agreement, GSJ agreed to refrain from further CZM
violations, to pay DPNR a fee in mitigation for the disputed violations claimed by
DPNR and to pay DPNR the balance of the initial Two Hundred Eighty Thousand
Dollar ($280,000.00) assessment, after deduction of the mitigation fee, in the event of
future CZM violations by GSJ.
EFTA00583142
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 3
II. Additionally, because DPNR made inaccurate factual and legal determinations and
exceeded the scope of its assessment authority in connection with the Notice of
Violation, and GSJ was therefore determined to protect itself from DPNR's
unreasonable practices going forward, GSJ would not enter into the Settlement
Agreement without certain essential protections.
12. Accordingly, the Settlement Agreement provides that in the event DPNR were to seek
to claim any violations against GSJ in the future, GSJ could not be assessed for such
violations with the balance of the original assessment unless GSJ was first given prior
notice and an opportunity to cure any and all such claimed violations. See EXHIBIT
B at Item 3(d).
13. The notice and the opportunity to cure provision was and is a material component of
GSJ's bargained for consideration in the Settlement Agreement.
14. So important was this provision to GSJ that GSJ was willing to agree to and did pay a
mitigation fee of Seventy Thousand Dollars ($70,000.00) under the Settlement
Agreement in order to ensure that GSJ would be entitled to these necessary
protections from future overreaching by DPNR. In GSJ's estimation, this mitigation
fee was much higher than that which ought reasonably be, or in fact was ever,
imposed previously under similar circumstances, but was well worth the price if it
protected GSJ from further DPNR overreaching in the future.
15. As is explained below, GSJ's concerns regarding the need for protection from DPNR
overreaching were well founded.
The Unauthorized and Unlawful Entry
16. On October 28, 2016, three (3) DPNR representatives, including an armed
enforcement officer, Officer Mercer, Jean-Pierre Oriol, Director of Coastal Zone
EFTA00583143
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 4
Management, and Attorney Michele Baker, DPNR Legal Counsel, entered upon
Great St. James without prior notice to or approval from GSJ, and outside of project
working hours and demanded access to the entire island.
17. DPNR's representatives were met at the only dock on Great St. James, which
effectively serves as the owner's front door, by GSJ personnel, who specifically
advised the DPNR representatives that the owner was not on the island and that the
GSJ personnel present had no authority to grant access to the island, and directed
DPNR to GSJ's office in Red Hook.
18. Nevertheless, over the protests of GSJ personnel, and lacking any legal authority
whatsoever, DPNR entered onto the premises of Great St. James and traversed the
entire island without restriction, allegedly to conduct a "site inspection" of Great St.
James, and verbally instructed workers to cease and desist from further activity on
Great St. James.
19. This unauthorized entry and search was particularly egregious in this case because it
was conducted with the approval and participation of DPNR's legal counsel.
DPNR's Counsel is ethically prohibited from communicating with another party or its
representatives without the prior permission of that party's attorney when, as here,
DPNR's Counsel knows that party to be represented by legal counsel. Counsel for
DPNR made no attempt whatsoever to contact the undersigned legal counsel for prior
approval or to notify GSJ before the unauthorized entry on Great St. James, the
communication with GSJ personnel without permission, and the unlawful search.
20. As a result of the unauthorized entry and unlawful search of Great St. James, DPNR
caused a written cease and desist order, M02-16-STT, dated October 28, 2016, to
EFTA00583144
GS!, LLC v. DPNR et aL
Civil No.
/ 2017
Complaint
Page 5
be served on counsel for GSJ via email and delivered to GSJ's Red Hook office on
October 31, 2016 (the "Cease and Desist Order"). [EXHIBIT CI
Erroneous Notice to Cure & the Arbitrary and Unreasonable Cure Period
21. On Friday, November 4, 2016, based on inaccurate observations, unfounded
assumptions, and erroneous conclusions of fact and law made during DPNR's
unauthorized entry and unlawful search of Great St. James on October 28, 2016,
Defendants issued a Notice to Cure Breach of Settlement Agreement (the "Notice to
Cure") [EXHIBIT DI.
22. In response to GSJ's request for an opportunity to review the numerous deficiencies
in the Notice to Cure with DPNR, Counsel for DPNR proposed by email that GSJ and
DPNR conduct an informal meeting with respect to the Notice to Cure to be held on
November 16, 2016, which proposal was agreed to by GSJ.
23. The Notice to Cure was and is deficient because, among other deficiencies, it
improperly attributed violations to Plaintiff where none had occurred and as to
matters for which it was readily apparent that GSJ bore absolutely no responsibility,
failed to adequately specify the basis and nature of the violations claimed or to
provide any reasonable description of allowable cures that DPNR required, and
provided an arbitrary and unreasonably short cure period, all in clear violation of
DPNR's obligations and GSJ's rights under the Settlement Agreement.
24. Emblematic, though not an exhaustive list, of alleged violations DPNR improperly
asserted against GSJ in the Notice to Cure were the following:
a. Alleged violations against GSJ with respect to four (4) moorings in waters off
the shores of Great St. James which for decades or more prior to GSJ's
acquisition have served as a popular public recreation spot for boaters. These
EFTA00583145
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 6
moorings were affixed to submerged land which is not part of Great St. James,
and were neither installed nor maintained by GSJ, and as such, GSJ can in no
way be held responsible for them.
b. Alleged violations with respect to what DPNR claimed was the excavation of
approximately three thousand five hundred (3500) square feet to four
thousand (4000) square feet of land, which DPNR inaccurately asserted was
being prepared for future development.
As is well known by DPNR
representatives who had visited Great St. James previously, the area in
question was an old garbage dump site created by the prior owner as to which
GSJ had previously advised DPNR it required heavy machinery to clean. The
site in question appeared to be clear because by the time of DPNR's
unauthorized entry and unlawful search of Great St. James, GSJ made
substantial progress in removing the debris from the garage dump. This site
presented no violation and GSJ was obviously perplexed as to what cure could
possibly be required in respect of this site.
c. Alleged violations against GSJ with respect to a non-permanent, movable Tiki
Bar of which DPNR representatives had been made aware during a prior visit
to Great St. James, in fact, using it as a resting place, and had correctly not
found it to constitute any violation. Under the circumstances, GSJ had no idea
what violation the Tiki Bar could possibly present and no idea as to what cure
DPNR expected with respect to the Tiki Bar.
25. The Notice to Cure unreasonably and arbitrarily demanded that Plaintiff cure the mix
of non-existent, inadequately described, and improperly assessed violations alleged in
the Notice to Cure within ten (10) calendars days of its receipt, which included five
EFTA00583146
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 7
(5) days of weekends and holidays that fell during that ten (10) day cure period, and
unilaterally imposed a cure deadline of November 14, 2016 with which it was
impossible for GSJ to comply.
26. On Monday, November 7, 2016, Plaintiff notified Defendants in writing of the
deficiencies in the Notice to Cure, including the arbitrarily and unreasonably short ten
(10) day cure period, which writing was followed by an email communication on
November 11, 2016 [EXHIBITS E & Fl.
27. Despite the extremely short cure period imposed by DPNR, no response to GSJ's
communications was received from DPNR until Friday, November 11, 2016, a
federal and Virgin Islands holiday on which businesses in the Virgin Islands were
closed for the weekend.
28. By email on that date, DPNR, acting outside of the scope of its obligations under the
Settlement Agreement, unreasonably refused to grant any extension of time, leaving
GSJ without an opportunity to review with DPNR the erroneous claims and determine
jointly with DPNR a proper course and reasonable timeline in which to proceed.
[EXHIBIT GI
29. Although it was a local and federal holiday, counsel for GSJ responded on that same
date with additional valid reasons to support an extension. [EXHIBIT HI
30. After the holiday weekend had passed and the cure deadline was upon them, DPNR
grudgingly extended its unilateral cure period by a mere four (4) days to November
18, 2016, only two (2) days after the scheduled informal meeting with DPNR on
November 16, 2016. [EXHIBIT II
31. Even with the slight extension, the cure period spanned only fourteen (14) days, from
November 5, 2016 to November 18, 2016, leaving only nine (9) working days for
EFTA00583147
GS!, LLC v. DPNR et aL
Civil No.
/ 2017
Complaint
Page 8
GSJ to complete the vague cures DPNR ultimately demanded, and giving GSJ only
two (2) days after the scheduled November 16, 2016 meeting with DPNR, during
which GSJ hoped to receive from DPNR the clarification regarding the Notice to
Cure it so desperately needed in order to properly comply.
32. On November 15, 2016, DPNR denied GSJ the opportunity for that clarification
needed to effectuate any cure during even that impossibly short two (2) day cure
window when it advised GSJ that the informal meeting scheduled for November 16th
would have to be rescheduled to November 22nd or 23rd, well past the cure deadline.
GSJ's Cures and Efforts to Mollify DPNR's Unreasonable Demands
33. In correspondence dated November 17, 2016, counsel for GSJ advised DPNR of the
steps that had been taken with respect to curing the more readily decipherable
violations claimed, albeit without any clarification from DPNR. [EXHIBIT .11
34. GSJ further advised DPNR that the other claimed violations could not and should not
be addressed without clarification or input from DPNR, which up to this point DPNR
had been unwilling to provide.
35. During the November 22nd meeting, so as to avoid further discord with DPNR, cause
DPNR to lift its cease and desist order and continue to review GSJ's permits and the
requests of GSJ for additional work on Great St. James, which DPNR refused to do
while the Notice to Cure remained outstanding, GSJ:
a. Advised DPNR of the significant remedial steps taken by GSJ prior to the
meeting with regard to claimed violations, even though disputed;
b. Resolved with DPNR inaccurately asserted violations and DPNR's improperly
demanded cures; and
EFTA00583148
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 9
c. Developed a plan and a reasonable timeframe within which to timely address
areas of continuing concern to DPNR, whether or not GSJ agreed that such
matters were within the scope of DNPR's authority.
36. During that meeting, as part of the plan of action jointly developed by GSJ and
DPNR, the parties also specifically agreed on a deadline by which GSJ was to address
the only two remaining items of concern to DPNR: (1) the transport of a non-
permanent, movable Tiki Bar away from its then current location on Great St. James
to a remote staging area on Great St. James; and (2) the removal of a stretch of hand-
laid stone from a pre-existing driveway on Great St. James.
37. Both the Tiki Bar and the hand-laid stone were removed by the agreed upon deadline
of December I, 2016, which date was less than thirty (30) days after GSJ's receipt of
the original Notice to Cure and undoubtedly constituted a reasonable cure period.
38. Despite GSJ's cures on such short notice and its substantial and successful efforts to
satisfy DPNR's vague, unjustified, and unreasonable demands, on December 15,
2016, DPNR caused a Notice of Failure to Cure Breach of Settlement Agreement &
Enforcement (the "Notice of Failure to Cure") to be served on GSJ. [EXHIBIT KI
39. None of the items asserted in the original Notice to Cure were included in the Notice
of Failure to Cure with the exception of the Tiki Bar and the hand-laid stone in the
pre-existing driveway, both of which were fully addressed before the Notice of
Failure to Cure was issued.
40. These two (2) items, which were timely cured, in the manner and within the
timeframe jointly established by GSJ and DPNR at their November 22, 2016 meeting,
provided the sole basis for DPNR's Notice of Failure to Cure.
EFTA00583149
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 10
41. Although Defendants blatantly violated DPNR's obligations and GSJ's rights under
the Settlement Agreement by providing a wholly deficient Notice to Cure, unilaterally
and arbitrarily imposing unreasonable cure deadlines, refusing to meet with GSJ or to
even discuss the rampant deficiencies in the Notice to Cure with GSJ prior to the
expiration of the unreasonable cure deadlines, and, in the end asserting as failures to
cure items which in fact had been timely cured, as a justification for the outrageous,
unjustified and unprecedented assessment of Two Hundred Ten Thousand Dollars
($210,000.00) provided in the Notice of Failure to Cure, Defendants improperly
invoked the remedy provisions of the very Settlement Agreement Defendants so
clearly violated in issuing the Notice to Cure and the Notice of Failure to Cure and by
their conduct in connection therewith.'
COUNT I: BREACH OF CONTRACT
42. Plaintiff repeats and re-alleges the foregoing paragraphs of the Complaint as if fully
set forth herein.
43. The parties negotiated and entered into the Settlement Agreement, a binding and valid
contract, wherein Defendants agreed to provide written notice and a cure period in the
event Defendants believed Plaintiff was not complying with the terms of the
Settlement Agreement.
44. As the Settlement Agreement does not specify the content of the contractually
required notice or a duration for the contractually required cure period, the Settlement
Agreement must be reasonably interpreted to require a cure period of a reasonable
duration after proper and adequate notice of any alleged violation to be cured.
I On January 17, 2017, GSJ appealed the Notice of Failure to the Board of Land Use Appeals. This action, however,
raises entirely separate causes of action derived from the Settlement Agreement provisions.
EFTA00583150
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 11
45. Defendants breached the Settlement Agreement by failing to provide both proper and
adequate notice of alleged violations and appropriate cures and a reasonable cure
period, as required by the Settlement Agreement.
46. Despite Defendants' breach of contract, and Plaintiff's timely cure, under the
Settlement Agreement, Defendants have improperly imposed a Two Hundred Ten
Thousand Dollar ($210,000.00) penalty against the Plaintiff.
47. Defendants' breach harmed Plaintiff because it caused, among other things, a penalty
of Two Hundred Ten Thousand Dollars ($210,000.00) to be improperly and
wrongfully assessed against Plaintiff.
48. Plaintiff has been harmed by the improper assessment of the Two Hundred Ten
Thousand Dollar ($210,000.00) penalty and has suffered other harmful consequences
as a result of Defendants' violations of the Settlement Agreement, including DPNR's
refusal to process or even consider any applications for permits submitted by GSJ, in
a total amount to be proven at trial.
COUNT II: VIOLATION OF GOOD FAITH AND FAIR DEALING COVENANT
49. Plaintiff repeats and re-alleges the foregoing paragraphs of the Complaint as if fully
set forth herein.
50. Every contract imposes upon each party a duty of good faith and fair dealing in its
performance and its enforcement.
51. Defendants breached DPNR's duty of good faith and fair dealing by providing a
wholly deficient Notice to Cure, unilaterally imposing an arbitrary and unreasonably
short cure period on GSJ, refusing to review, discuss and clarify with GSJ the
deficiencies in the Notice to Cure before the expiration of that improper cure period,
including by cancelling a meeting with GSJ scheduled to take place prior to the
EFTA00583151
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 12
expiration of that cure period, imposing a Two Hundred Ten Thousand Dollar
($210,000.00) penalty on GSJ for alleged violations that had been already cured or
were committed by parties other than GSJ, and refusing to process or even consider
applications for permits submitted by GSJ.
52. Plaintiff has been harmed by Defendants' breach of DPNR's duty of good faith and
fair dealing in an amount to be shown at trial.
COUNT III: ACTION FOR DECLARATORY JUDGMENT
53. Plaintiff repeats and re-alleges the foregoing paragraphs of the Complaint as if fully
set forth herein.
54. The parties negotiated and entered into the Settlement Agreement, a binding and valid
contract, wherein Defendants agreed to provide written notice and a cure period in the
event Defendants believed Plaintiff was not complying with the terms of the
Settlement Agreement.
55. As the Settlement Agreement does not specify the content of the contractually
required notice or a duration for the contractually required cure period, the Settlement
Agreement must be interpreted to require a cure period of a reasonable duration after
proper and adequate notice of any alleged violation to be cured.
56. Defendants breached the Settlement Agreement by failing to provide both proper and
adequate notice of alleged violations and appropriate cures and a reasonable cure
period, as required by the Settlement Agreement.
57. Plaintiff timely cured all violations alleged in the Notice of Failure to Cure within the
reasonable cure period permitted under the Settlement Agreement.
EFTA00583152
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 13
58. Despite Defendants' breach of contract, and Plaintiff's timely cure, under the
Settlement Agreement, Defendants have improperly imposed a Two Hundred Ten
Thousand Dollar ($210,000.00) penalty against Plaintiff.
59. Furthermore, DPNR's refusal to process or even consider any applications of permits
submitted by GSJ is causing GSJ further damages by indefinitely delaying the
progress of construction and improvements on Great St. James.
60. Accordingly, pursuant to V.I. CODE ANN. tit. 5, §§ 1261-1272, Plaintiff seeks a
judgment declaring that Plaintiff is entitled under the Settlement Agreement to
adequate notice of any violations of the Settlement Agreement asserted by DPNR and
a reasonable opportunity to cure the same after receiving such notice, that Defendants
provided neither adequate notice of asserted violations of the Settlement Agreement
nor a reasonable opportunity to cure the asserted violations and that, as a result of the
same, Defendants violated the Settlement Agreement.
61. Additionally, Plaintiff further seeks a judgment declaring that the Notice of Failure to
Cure, being based upon and itself constituting a breach of the Settlement Agreement
by Defendants, is outside the scope of and an unlawful exercise of Defendants'
authority, as is the demand thereunder for GSJ to make payment of the Two Hundred
Ten Thousand Dollar ($210,000.00) penalty improperly imposed therein.
62. Additionally, Plaintiff further seeks a judgment declaring that DPNR's refusal to
process or even consider any applications for permits submitted by GSJ, asserted by
Defendants as being justified based on the unresolved Notice of Failure to Cure and
non-payment of the Two Hundred Ten Thousand Dollar ($210,000.00) assessment
imposed therein, is also outside the scope of and an unlawful exercise of Defendants'
EFTA00583153
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 14
authority, and directing DPNR to consider and process GSJ's applications for
permits.
WHEREFORE, Plaintiff seeks all damages to which it is entitled, including contractual,
compensatory, punitive and equitable damages, and declaratory relief, as well as an award of its
costs and reasonable attorneys' fees, and any pre and post judgment interest to which it is
entitled.
Respectfully,
Dated: March 8, 2017
ERIKA A. KELLERHALS, ESQ.
CHRISTOPHER ALLEN KROBLIN, ESQ.
MARJORIE WHALEN, ESQ.
V.I. Bar Nos. 849, 966 & R2019
KELLERHALS FERGUSON KROBLIN PLLC
Royal Palms Professional Building
9053 Estate Thomas, Suite 101
St. Thomas, V.I. 00802
Telephone: (340) 779-2564
Facsimile: (888) 316-9269
Email:
EFTA00583154
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Phone Numbers
Document Details
| Filename | EFTA00583141.pdf |
| File Size | 836.2 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 23,872 characters |
| Indexed | 2026-02-11T22:50:11.329555 |