IN THE SUPERIOR COURT OF THE VIRGIN ISLANDS
DISTRICT OF ST. THOMAS & ST. JOHN
**********************************
GREAT ST. JIM, LLC,
)
)
Plaintiff,
)
)
v.
)
)
DEPARTMENT OF PLANNING AND
)
NATURAL RESOURCES and DAWN HENRY )
In Her Official Capacity as Commissioner of the )
Department of Planning and Natural Resources, )
)
Defendants.
)
)
CIVIL NO.
12017
COMPLAINT
COMES NOW Plaintiff Great St. Jim, LLC, by and through its undersigned counsel,
ICELLERHALS FERGUSON KROBLIN PLLC, and for its Complaint against the Department of
Planning and Natural Resources and Commissioner Dawn Henry, states and alleges as follows:
PARTIES & JURISDICTION
1. Plaintiff Great St. Jim, LLC ("GSJ") is a limited liability company organized under
the laws of the U.S. Virgin Islands.
2. Upon information and belief, Defendant the Department of Planning and Natural
Resources ("DPNR") is an instrumentality of the Government of the U.S. Virgin
Islands.
3. Defendant Dawn Henry is the Commissioner of Defendant DPNR.
4. This is a civil action for breach of contract, breach of the implied covenant of good
faith and fair dealing, declaratory judgment, and equitable relief over which this
Court has jurisdiction pursuant to 4 V.I.C. § 76.
EFTA00583185
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 2
5. Venue is proper in this Court pursuant to 4 V.I.C. § 78, as the District of St. Thomas
& St. John is the judicial division where the cause of action arose and where
Defendants may be served.
FACTS
The Settlement Agreement
6. GSJ is the owner of the island known as Great St. James, located within the U.S.
Virgin Islands, which is the site of activity in issue.
7. In April of 2016, DPNR issued Notice of Violation identified as NOVA-04-16-STT
("Notice of Violation") to GSJ seeking an assessment of Two Hundred Eighty
Thousand Dollars ($280,000.00) for what DPNR alleged were violations of the
Coastal Zone Management Act ("CZM Violations") on the residential property of
Great St. James. [EXHIBIT A]
8. GSJ contested the alleged violations as unjustified and the assessment as an
unprecedented penalty on wholly residential property, both well outside the scope of
DPNR's authority, and negotiations between the parties ensued.
9. On August 4, 2016, in an attempt to resolve the Notice of Violation, so that GSJ
could proceed with its plans for Great St. James, GSJ entered into a Settlement
Agreement with DPNR regarding the challenged violations and assessment asserted
in the Notice of Violation (the "Settlement Agreement"). [EXHIBIT B]
10. As part of the Settlement Agreement, GSJ agreed to refrain from further CZM
violations, to pay DPNR a fee in mitigation for the disputed violations claimed by
DPNR and to pay DPNR the balance of the initial Two Hundred Eighty Thousand
Dollar ($280,000.00) assessment, after deduction of the mitigation fee, in the event of
EFTA00583186
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 3
future CZM Violations which GSJ fails to cure after DPNR provides notice of the
same.
II. In order to address the prospect of additional legally and factually deficient
determinations by DPNR and further excesses in the exercise of DPNR's assessment
authority, GSJ insisted that the Settlement Agreement include notice and opportunity
to cure provisions with respect to all CZM Violations that might be asserted by
DPNR in the future.
12. Accordingly, the Settlement Agreement provides that in the event DPNR were to seek
to claim any violations against GSJ in the future, GSJ could not be assessed for such
violations with the balance of the original assessment unless GSJ was first given prior
notice and an opportunity to cure any and all such claimed violations. See EXHIBIT
B at Item 3(d).
13. In exchange for these necessary protections from future overreaching by DPNR, GSJ
agreed in the Settlement Agreement to pay and did pay a mitigation fee of Seventy
Thousand Dollars ($70,000.00), a fee much higher than that which previously ever
was ever paid for alleged CZM Violations of a similar nature on wholly residential
property.
14. The notice and the opportunity to cure provisions therefore were and are a material
component of the Settlement Agreement expressly bargained and paid for by GSJ.
15. As is explained below, GSJ's concerns regarding the need for protection from DPNR
overreaching were well founded.
The Unauthorized and Unlawful Entry
16. On October 28, 2016, three (3) DPNR representatives, including an armed
enforcement officer, Officer Mercer, Jean-Pierre Oriol, Director of Coastal Zone
EFTA00583187
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 4
Management, and Attorney Michele Baker, DPNR Legal Counsel, entered upon
Great St. James without prior notice to or approval from GSJ, or any legal authority
to do so.
17. DPNR previously issued a minor Coastal Zone Management permit to GSJ in
connection with development relating to a certain cistern project (the "Cistern
Project") situated at a discrete location on Great St. James. The express conditions of
that permit (the "Cistern Permit") limit the times during which DPNR may request
access to Great St. James, as well as the scope and location of such access. Section
V, paragraph 8 of the Cistern Permit provides:
The Commissioner or his authorized agents or representatives shall have the power to
enter at reasonable time during projects work hours upon any lands or waters for
which a Coastal Zone Permit has been issued. The Permittee shall permit such entry
for the purpose of inspection and ascertaining compliance with the terms and
conditions of said Coastal Zone Management permit.
See EXHIBIT C at Section V, paragraph 8 on page 2.
18. Thus, by the express terms of the Cistern Permit, DPNR was authorized to seek
access only at a reasonable time and only during the working hours of the Cistern
Project. Moreover, DPNR could request access only for the limited purpose of
inspecting the specific site of the Cistern Project and only in order to ascertain
compliance at that site with the terms of the Cistern Permit. By the express terms of
the Cistern Permit, GSJ is only required to permit such access during those limited
times, at that limited site and for that limited purpose. DPNR's recourse in the event
access is denied is to issue a cease and desist order or to commence proceedings to
revoke the Cistern Permit in the event it can show that the Permittee violated the
conditions of the Cistern Permit (which had not occurred in this case). DPNR is not
authorized to disregard the terms of the Cistern Permit or the directives of GSJ's
EFTA00583188
GV, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 5
representatives and trespass on private property and is statutorily limited by the
provisions of Title 12, section 913. 4E-Filwr ea.i3-44n.m4de-stattitet,g;aeli-up
here?}
19. DPNR sought access to Great St. James on October 28, 2016 at a time when there
was no work taking place at the Cistern Project and which was therefore outside of
the project's working hours. Furthermore, the time of the access was unreasonable in
that it was sought without prior notice when neither the owner nor anyone with
knowledge of Cistern Permit was then available to accompany DPNR to the site of
the Cistern Project, it disrupted the schedules of GSJ personnel, and it interfered with
the conduct of their assigned duties.
20. DPNR's representatives were met at the only dock on Great St. James, which
effectively serves as the owner's front door, by GSJ personnel, who, having been
forced to disrupt their schedules and disregard their assigned duties to receive the
DPNR representatives, specifically advised the DPNR representatives that the owner
was not on the island and that the GSJ personnel present had no authority to grant
access to the island, and directed DPNR to GSJ's office in Red Hook.
21. Nevertheless, over the protests of GSJ personnel, and lacking any legal authority
whatsoever, DPNR entered onto the premises of Great St. James. Moreover, despite
that fact that the express terms of the Cistern Permit limited the location and scope of
any permissible access on Great St James exclusively to the site of the Cistern Project
for the narrow purpose of ascertaining compliance with the Cistern Permit at that
specific site, DPNR traversed the entire island without restriction, claiming to be
authorized to conduct an "inspection" of the entirety of Great St. James.
EFTA00583189
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 6
22. This unauthorized entry and unlawful search was particularly egregious in this case
because it was conducted with the approval and participation of DPNR's legal
counsel. DPNR's Counsel is ethically prohibited from communicating with another
party or its representatives without the prior permission of that party's attorney when,
as here, DPNR's Counsel knows that party to be represented by legal counsel.
Counsel for DPNR made no attempt whatsoever to contact the undersigned legal
counsel for prior approval or to notify GSJ before the unauthorized entry on Great St.
James, the communication with GSJ personnel without permission, and the unlawful
search.
23. By refusing to comply with the conditions of the permit and conducting an
unauthorized search throughout the entirety of Great St. James without prior notice to
GSJ or its legal counsel at an unreasonable time when neither the owner nor
knowledgeable GSJ representatives could be present, DPNR, eliminated any
opportunity for clarification or discussion at the site giving rise to a series factual and
legal errors (more fully described below) by DPNR underlying the instant action.
24. During its unauthorized entry and unlawful search on October 28, 2016, DPNR
verbally instructed workers to cease and desist from further activity anywhere on
Great St. James. That verbal instruction was confirmed by a written cease and desist
order, IM-02-16-STT, dated October 28, 2016, that was to be served on counsel for
GSJ via email and was delivered to GSJ's Red Hook office on October 31, 2016 (the
"Cease and Desist Order"). [EXHIBIT DI
Erroneous Notice to Cure & the Arbitrary and Unreasonable Cure Period
EFTA00583190
GS!, LLC v. DPNR et aL
Civil No.
12017
Complaint
Page 7
25. On Friday, November 4, 2016, based on inaccurate observations, unfounded
assumptions, and erroneous conclusions of fact and law made during DPNR's
unauthorized entry and unlawful search of Great St. James on October 28, 2016,
Defendants issued a Notice to Cure Breach of Settlement Agreement (the "Notice to
Cure") [EXHIBIT E].
26. In response to GSJ's request for an opportunity to review the numerous deficiencies
in the Notice to Cure with DPNR, Counsel for DPNR proposed by email that GSJ and
DPNR conduct an informal meeting with respect to the Notice to Cure to be held on
November 16, 2016, which proposal was agreed to by GSJ.
27. The Notice to Cure was and is deficient because, among other deficiencies, it
improperly attributed violations to Plaintiff where none had occurred and as to
matters for which it was readily apparent that GSJ bore absolutely no responsibility,
failed to adequately specify the basis and nature of the violations claimed or to
provide any reasonable description of allowable cures that DPNR required, and
provided an arbitrary and unreasonably short cure period, all in clear violation of
DPNR's obligations and GSJ's rights under the Settlement Agreement.
28. Emblematic, though not an exhaustive list, of alleged violations DPNR improperly
asserted against GSJ in the Notice to Cure were the following:
a. An alleged violation against GSJ with respect to four (4) moorings in waters
off the shores of Great St. James which for decades or more prior to GSJ's
acquisition have served as a popular public recreation spot for boaters. These
moorings were affixed to submerged land which is not part of Great St. James,
and were neither installed nor maintained by GSJ, and as such, GSJ could in
no way be held responsible for them.
This indisputable fact was
EFTA00583191
GS!, LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 8
acknowledged by DPNR at a November 22, 2016 meeting, but only after GSJ
was forced to expend resources and remove the moorings prior to the
expiration of DPNR's unreasonable cure deadline.
b. An alleged violation with respect to what DPNR claimed was the excavation
of approximately three thousand five hundred (3500) square feet to four
thousand (4000) square feet of land, which DPNR inaccurately asserted was
being prepared for future development.
In fact, that site had not been
excavated. As is well known by DPNR representatives who had visited Great
St. James previously, the area in question was an existing garbage dump site
created by the prior owner. As subsequently acknowledged by DPNR's
representatives at the November 22, 2016 meeting, this site presented no
violations to be cured by GSJ.
c. An alleged violation against GSJ with respect to a non-permanent, movable
covered picnic table of which DPNR representatives specifically had been
made aware during a prior visit to Great St. James, and had correctly not
found it to constitute any violation. Under the circumstances, GSJ was unable
to determine what violation this non-permanent, readily moveable structure
could possibly present or what cure DPNR expected of GSJ with respect to it.
29. The Notice to Cure unreasonably and arbitrarily demanded that Plaintiff cure the mix
of non-existent, inadequately described, and improperly assessed violations alleged in
the Notice to Cure within ten (10) calendars days of its receipt, which included five
(5) days of weekends and holidays that fell during that ten (10) day cure period, and
unilaterally imposed a cure deadline of November 14, 2016 with which it was
impossible for GSJ to comply.
EFTA00583192
GS!, LLC v. DPNR et aL
Civil No.
12017
Complaint
Page 9
30. On Monday, November 7, 2016, Plaintiff notified Defendants in writing of the
deficiencies in the Notice to Cure, including the arbitrary and unreasonably short ten
(10) day cure period, which writing was followed by an email communication on
November 11, 2016 [EXHIBITS F & G].
31. Despite the extremely short cure period imposed by DPNR, no response to GSJ's
communications was received from DPNR until Friday, November 11, 2016, a
federal and Virgin Islands holiday on which businesses in the Virgin Islands were
closed for the weekend.
32. By email on that date, DPNR, acting outside of the scope of its obligations under the
Settlement Agreement, unreasonably refused to grant any extension of time, leaving
GSJ without an opportunity to review with DPNR the erroneous claims and determine
jointly with DPNR a proper course and reasonable timeline in which to proceed.
[EXHIBIT HI
33. Although it was a local and federal holiday, counsel for GSJ responded on that same
date with additional valid reasons to support an extension. [EXHIBIT I]
34. After the holiday weekend had passed and the cure deadline was upon them, DPNR
grudgingly extended its unilateral cure period by a mere four (4) days to November
18, 2016, only two (2) days after the scheduled informal meeting with DPNR on
November 16, 2016. [EXHIBIT J]
35. Even with the slight extension, the cure period spanned only fourteen (14) days, from
November 5, 2016 to November 18, 2016, leaving only nine (9) working days for
GSJ to complete the vague cures DPNR ultimately demanded, and giving GSJ only
two (2) days after the scheduled November 16, 2016 meeting with DPNR, during
EFTA00583193
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 10
which GSJ hoped to receive from DPNR the clarification regarding the Notice to
Cure GSJ reasonably required in order to properly comply.
36. On November 15, 2016, DPNR denied GSJ the opportunity for the clarification
needed to effectuate any cure during even that short two (2) day cure window, when
DPNR advised GSJ that the informal meeting scheduled for November 16, 2016
would have to be rescheduled to November 22 or 23, 2016, well past the cure
deadline.
GSJ's Cures and Efforts to Mollify DPNR's Unreasonable Demands
37. In correspondence dated November 17, 2016, counsel for GSJ advised DPNR of the
steps that had been taken to timely cure those of the claimed violations that were less
confusingly described in the Notice to Cure, albeit without any clarification from
DPNR. [EXHIBIT KI
38. GSJ further advised DPNR that the other claimed violations could not and should not
be addressed without clarification or input from DPNR, which up to this point DPNR
had been unwilling to provide.
39. During the November 22, 2016 meeting, so as to avoid further discord with DPNR,
and to cause DPNR to lift its cease and desist order and continue to review GSJ's
permits and the requests of GSJ for additional work on Great St. James, which DPNR
refused to do while the Notice to Cure remained outstanding, GSJ:
a. Advised DPNR of the significant remedial steps taken by GSJ prior to the
meeting with regard to claimed violations, even though disputed;
b. Resolved with DPNR inaccurately asserted violations and DPNR's improperly
demanded cures; and
EFTA00583194
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 11
c. Developed a plan and a reasonable timeframe within which to timely address
areas of continuing concern to DPNR, whether or not GSJ agreed that such
matters were within the scope of DNPR's authority.
40. During that meeting, as part of the plan of action jointly developed by GSJ and
DPNR, the parties also specifically agreed on a deadline by which GSJ was to address
the only two remaining items of concern to DPNR: (1) the transport of a non-
permanent, movable covered picnic table away from its then current location on Great
St. James to a remote staging area on Great St. James; and (2) the removal of a stretch
of hand-laid stone from a pre-existing driveway on Great St. James.
41. Both the moveable covered picnic table and the hand-laid stone were removed by the
agreed upon deadline of December 1, 2016, which date was less than thirty (30) days
after GSJ's receipt of the original Notice to Cure.
GSJ's cure by that date
undoubtedly was accomplished within a reasonable cure period.
42. Despite GSJ's cures on such short notice and its substantial and successful efforts to
satisfy DPNR's vague, unjustified, and unreasonable demands, on December 15,
2016, DPNR caused a Notice of Failure to Cure Breach of Settlement Agreement &
Enforcement (the "Notice of Failure to Cure") to be served on GSJ. [EXHIBIT LI
43. None of the items asserted in the original Notice to Cure were included in the Notice
of Failure to Cure with the exception of the non-permanent, moveable covered picnic
table and the hand-laid stone in the pre-existing driveway, both of which were fully
addressed before the Notice of Failure to Cure was issued.
44. These two (2) items, which were timely cured, in the manner and within the
timeframe jointly established by GSJ and DPNR at their November 22, 2016 meeting,
provided the sole basis for DPNR's Notice of Failure to Cure.
EFTA00583195
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 12
45. Although Defendants violated DPNR's obligations and GSJ's rights under the
Settlement Agreement by providing a factually and legally deficient Notice to Cure,
unilaterally and arbitrarily imposing unreasonable cure deadlines, refusing to meet
with GSJ or to even discuss the deficiencies in the Notice to Cure with GSJ prior to
the expiration of the unreasonable cure deadlines, and, in the end asserting as failures
to cure items which in fact had been timely cured, as a justification for the
unprecedented assessment of Two Hundred Ten Thousand Dollars ($210,000.00)
provided in the Notice of Failure to Cure, Defendants improperly invoked the remedy
provisions of the very Settlement Agreement Defendants clearly violated in issuing
the Notice to Cure and the Notice of Failure to Cure and by their conduct in
connection therewith.l
COUNT I: BREACH OF CONTRACT
46. Plaintiff repeats and re-alleges the foregoing paragraphs of the Complaint as if fully
set forth herein.
47. The parties negotiated and entered into the Settlement Agreement, a binding and valid
contract, wherein Defendants agreed to provide written notice and a cure period in the
event Defendants believed Plaintiff was not complying with the terms of the
Settlement Agreement.
48. As the Settlement Agreement does not specify the content of the contractually
required notice or a duration for the contractually required cure period, the Settlement
Agreement must be reasonably interpreted to require a cure period of a reasonable
duration after proper and adequate notice of any alleged violation to be cured.
I On January 17, 2017, GSJ appealed the Notice of Failure to the Board of Land Use Appeals. This action, however,
raises entirely separate causes of action derived from the Settlement Agreement provisions.
EFTA00583196
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 13
49. Defendants breached the Settlement Agreement by failing to provide both proper and
adequate notice of alleged violations and appropriate cures and a reasonable cure
period, as required by the Settlement Agreement.
50. Despite Defendants' breach of contract, and Plaintiff's timely cure, under the
Settlement Agreement, Defendants have improperly imposed a Two Hundred Ten
Thousand Dollar ($210,000.00) penalty against the Plaintiff.
51. Plaintiff has been harmed by Defendants' breach of contract in that it caused the
improper and wrongful assessment of a Two Hundred Ten Thousand Dollar
($210,000.00) penalty against Plaintiff, as well as other harmful consequences,
including DPNR's refusal to process or even consider any applications for permits
submitted by GSJ, in a total amount to be proven at trial.
COUNT II: VIOLATION OF GOOD FAITH AND FAIR DEALING COVENANT
52. Plaintiff repeats and re-alleges the foregoing paragraphs of the Complaint as if fully
set forth herein.
53. Every contract imposes upon each party a duty of good faith and fair dealing in its
performance and its enforcement.
54. Defendants breached DPNR's duty of good faith and fair dealing by providing a
legally and factually deficient Notice to Cure, unilaterally imposing an arbitrary and
unreasonably short cure period on GSJ, refusing to review, discuss and clarify with
GSJ the deficiencies in the Notice to Cure before the expiration of that improper cure
period, including by cancelling a meeting with GSJ scheduled to take place prior to
the expiration of that cure period, imposing an unjustified and unprecedented Two
EFTA00583197
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 14
Hundred Ten Thousand Dollar ($210,000.00) penalty on GSJ for alleged violations
that already had been cured timely, and refusing to process or even consider
applications for permits submitted by GSJ.
55. Plaintiff has been harmed by Defendants' breach of DPNR's duty of good faith and
fair dealing in an amount to be shown at trial.
COUNT III: ACTION FOR DECLARATORY JUDGMENT
56. Plaintiff repeats and re-alleges the foregoing paragraphs of the Complaint as if fully
set forth herein.
57. The parties negotiated and entered into the Settlement Agreement, a binding and valid
contract, wherein Defendants agreed to provide written notice and a cure period in the
event Defendants believed Plaintiff was not complying with the terms of the
Settlement Agreement.
58. As the Settlement Agreement does not specify the content of the contractually
required notice or a duration for the contractually required cure period, the Settlement
Agreement must be interpreted to require a cure period of a reasonable duration after
proper and adequate notice of any alleged violation to be cured.
59. Defendants breached the Settlement Agreement by failing to provide both proper and
adequate notice of alleged violations and appropriate cures and a reasonable cure
period, as required by the Settlement Agreement.
60. Plaintiff timely cured all violations alleged in the Notice of Failure to Cure within the
reasonable cure period permitted under the Settlement Agreement.
EFTA00583198
GS!, LLC v. DPNR et al.
Civil No.
/ 2017
Complaint
Page 15
61. Despite Defendants' breach of contract, and Plaintiff's timely cure, under the
Settlement Agreement, Defendants have improperly imposed a Two Hundred Ten
Thousand Dollar ($210,000.00) penalty against Plaintiff.
62. Furthermore, DPNR's refusal to process or even consider any applications for permits
submitted by GSJ is causing GSJ further damages by indefinitely delaying the
progress of construction and improvements on Great St. James.
63. Accordingly, pursuant to V.I. CODE ANN. tit. 5, §§ 1261-1272, Plaintiff seeks a
judgment declaring that Plaintiff is entitled under the Settlement Agreement to
adequate notice of any violations of the Settlement Agreement asserted by DPNR and
a reasonable period of time within which to cure the same after receiving such notice,
that Defendants provided neither adequate notice of asserted violations of the
Settlement Agreement nor a reasonable period of time within which to cure the
asserted violations, and that, as a result of the same, Defendants violated the
Settlement Agreement.
64. Additionally, Plaintiff further seeks a judgment declaring that the Notice of Failure to
Cure, being based upon and itself constituting a breach of the Settlement Agreement
by Defendants, is outside the scope of and an unlawful exercise of Defendants'
authority, as is the demand thereunder for GSJ to make payment of the Two Hundred
Ten Thousand Dollar ($210,000.00) penalty improperly imposed therein.
65. Additionally, Plaintiff further seeks a judgment declaring that DPNR's refusal to
process or even consider any applications for permits submitted by GSJ, asserted by
Defendants as being justified based on the unresolved Notice of Failure to Cure and
non-payment of the Two Hundred Ten Thousand Dollar ($210,000.00) assessment
imposed therein, is also outside the scope of and an unlawful exercise of Defendants'
EFTA00583199
GSI LLC v. DPNR et al.
Civil No.
12017
Complaint
Page 16
authority, and directing DPNR to consider and process GSJ's applications for
permits.
WHEREFORE, Plaintiff seeks all damages to which it is entitled, including contractual,
compensatory, punitive and equitable damages, and declaratory relief, as well as an award of its
costs and reasonable attorneys' fees, and any pre and post judgment interest to which it is
entitled.
Respectfully,
Dated: March 412, 2017
ERIKA A. KELLERHALS, ESQ.
CHRISTOPHER ALLEN KROBLIN, ESQ.
MARJORIE WHALEN, ESQ.
V.I. Bar Nos. 849, 966 & R2019
KELLERHALS FERGUSON KROBLIN PLLC
Royal Palms Professional Building
9053 Estate Thomas, Suite 101
St. Thomas, V.I. 00802
Telephone: (340) 779-2564
Facsimile: (888) 316-9269
Email:
EFTA00583200
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Phone Numbers
Document Details
| Filename | EFTA00583185.pdf |
| File Size | 955.3 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 27,363 characters |
| Indexed | 2026-02-11T22:50:11.568561 |