Punch List — perJE directives as of February 5. 2012
2. Slipcovers for sofa and cushions in production
Stereo cabinets estimate due this week
— Flagpole lights?
w
3.
- Dock Box- pending available time
4. Five Palms — stucco, window, hardscape, electrical
5. Grotto — lookout built with metal roof, landings
6 .Greenheart wood — steps to Grotto - steps top and bottom
8. Heli garage. Concrete poor
9. Hangar -floor sanding in progress — 401(50' area for slab, 3 foot wall around it — containment for ISO
fuel tank — bathroom and room divider — subcontractor
10. Steel shed have estimate for building, budget to be forwarded 31 Jan - shed quote
11. Triangle, commenced work - triangle road
12. Entry tree lights, confirmed ground lighting xmas lighting
13. Pebble beach - Solar fridge, light, fan for pebble beach.
14. Library Dehumidification 2nd unit ordered, Sarah office damper needs new board, invoicing issue still need
to sorted out — Sarah's office is to be set at 79 degrees
15. Yellow flowering Alamandra up Old Mill wall and Flagpole hill Peter to train vines to wall
16. Solutions for generators —drawings complete for bid package
17. Fire system — need to review operational and maintenance schedule
18. Top of hill — CLEAN UP - place garbage in circle — build up 10 feet — new helipad
20. Library windows done - shutter in library
21. Five Palms
- Floor
- Doors location and fabrication
-Lighting schedule
22. Tree transplants — Peter redo the three new trees?
23. Guestroom -
Cabana 3 leaks, Cabana 1 leaks Main terrace — sealing of gutters in progress
24. Tiki
- Shields due end of the month
- Dock box pending available time
25. Sunken garden berm continues
26. Concrete roads at flagpole
27. Concrete triangle
28. Compass - sundial
29. Bench placements - bench on peninsula point — benches, grotto
30. Engineering clean up continues
31. New vehicles
32. Dock Decking - dark stain the dock sample
34. Lighting - adjust landscape lights at night
37. Mgrs Cottage Roof work remains
38. Master bath - leaks
39. Mooring Permit at Army Corp
42. Top of hill Clean up continues
43. Rationalize Telephone system Bill and Steve were on LSJ 27th to 29th Jan
44. Rock grinder Purchased
46. The rock crusher, the dirt sifter, and the cement plant should all be operating at full capacity — completed?
EFTA00583416
47. Gates to hide engineering both at top and bottom of hill - Bill Adams' Rates
48. Engineering service road reshaped. Continues
49. Dock lighting -Barn lights for structures, spots for dock and barge ramp on remote
50. Dock house completed except for final electrical
51. Roads — from intersection to Flagpole
52. Guest house — site layout needs to be confirmed
56. High gloss polyurethane deck finish applied to nautilus shells 30th - nautilus lights
57. Replacement transformer Mechanical building. Reviewing bids, will submit for approval 1 Feb
58. Photos for Chillax bath — installed
60. Let Jules and Peter bulldoze road now from top of hill down towards Flagpole Done
61. Floating Dock, new design to be submitted 3'd Feb
62. Remove Rusty metal dock Columns. Reviewing options
63. New Lull will forward options next week.
64. Fat Cat- inspection completed, buyers contacted
65. Big N- inspection today
66. Midnight Express repairs complete
67. Socket on terrace
69. Paint engineering plywood green
71. Brian's bonus
72. We need to re-hydro-seed, fertilizer, get lots of hydro-seed
73. Concrete the dock
75. Trash bin location
76. Hell approach lights
EFTA00583417
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00583416.pdf |
| File Size | 113.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,561 characters |
| Indexed | 2026-02-11T22:50:13.324851 |