Punch List — per JE directives as of March 5. 2012
1. Rug — due to ship Wednesday March 7
2. Flagpole bath and cabana — slipcovers for sofa and cushion week of the 27th
3. Five Palms — stucco, window, hardscape, electrical - solar estimate Mar 9th
4. Grotto - JE to redo layout of steps, determine shelter height
5. Heli garage —final punch out (painting)
6. Hangar —floor sanding in progress — 401(50' area for slab, 3 foot wall around it — containment for ISO
fuel tank — bathroom and room divider — subcontractor
7. Steel shed have estimate for building, budget to be forwarded 31 Jan
8. Triangle, commenced work
9. Entry tree lights, confirmed ground lighting
10. Library Dehumidifaction — commences week of March 12
11. Solutions for generators —drawings complete for bid package
12. Too of hill — CLEAN UP — remove rocks and hydroseed
13. Five Palms
- Floor
- Doors location and fabrication
-Lighting schedule
14. Tree order — develop list
15. Tiki
- Shields due end of the month
- Dock box pending available time
16. Sunken garden berm - continues
17. Concrete roads at flagoole - continues
18. Concrete triangle
19. Bench placements — bench on peninsula point
20. Engineering clean up - continues
21. New vehicles — two more Polaris bikes (800's) — Larry/Brice
22. Dock decking — discuss pressure treated timber and carpeting
23. Aquarium photo — ordered for small shutters
24. Mgrs Cottage Roof work remains — completion 2 weeks
25. Mooring Permit — proceeding with bids to place anchors
26. Electrical quotes - forward to JE
27. Rationalize Telephone system — Karen to make up extension list for each phone
28. Gates to hide engineering both at top and bottom of hill. Bill reviewing light weight gates —JE advises three
8 foot gates - bi-fold design running in track on the ground
29. Engineering service road reshaped - Continues
30. Dock lighting -Barn lights for structures, ordered due on sight 2nd week of March
31. Roads —from intersection to Flagpole
32. Guest house — moved to Beach 3, layout to be confirmed — scrape ground — lay rebar
33. Chillax room — furniture piece required for electrical/media equipment
34. Replacement transformer Mechanical building — have bid — reviewing shipping — Brice to finalize cost
comparisons — refurbishment VS. new
35. Photos for Chillax bath — install small ones that are on site
36. Floating Dock — fabrication of metal beam to commence 3/6
37. Remove Rusty metal dock Columns — recovered
38. Midnight Express — new trailer to be purchased
EFTA00583475
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00583475.pdf |
| File Size | 75.1 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,561 characters |
| Indexed | 2026-02-11T22:50:13.752545 |