JE Punch List —June 17. 2012
1. Five Palms —TOP PRIORITY
- Exterior Door Shutters — removable option
- Painting - outside to be completed after visit
- Furniture — Sofa — leather samples JE will review while on site
- Piano - needs tuner — piano on STT 6/16
- Mirrored siding — Panels on site 6/14
- Glue on site
- Tapestry Molding for Ceiling — Ion
- Transformer building — Building 5/31, 5/25 — final electrical hookup 6/8 — temporarily powered by generator
- Fire pit —gas unit needs to be returned and reordered
- Road grading
- Internet
- Cabinets — add push latches on doors
2. Grotto -
- Floor resin
- Genset wiring — scheduling to be determined
3. Berm/Top of Hill
4. Engineering/Maintenance Yard
- Steel Shed — foundation in progress
- Metal Sheets - on old building will be replaced week of 6/4
5. Triangle — landscaping direction required from JE
6. Flagpole Pool Cabana -
- Recovering of sofa/chairs
- Furniture — needs new desk — Sarah
7. Entry Tree Lights — installation complete
8. Solutions for Generators — Sound proofing solution forwarded to JE, require direction, wall built
9. Tiki — Darren is contacting the vendor regarding the shields
10 - Floating Dock -
- Jet ski Docking - review
- Table/Dock Box — Bill starting 6/4
11. Kite House — review of wooden outside furniture - Sarah
12. Chillax Room — requires furniture piece for electrical/media equipment — Sarah
13. Chillax Bathroom - requires blue rugs for bathroom & vanity area — Sarah
14. Mechanical Building
- Replacement Transformer — estimated date to be shipped from factory (Illinois) 8/21
15. Boats
- Midnight Express — purchase Yamaha 300 motors, install by Offshore Marine
- PRD — sell
- Lady G — sell
- Big N - sell
- Calypso — refurbish
16. Gym Road - road grading after Five Palms — continues
17. Timers— review installing timers on air conditioners, irrigation water systems, and lights
18. Beach lighting — per JE, replace existing transformers for the beach lighting of palms around the salt pond
and beach
19. Pergolas — construct 3 pergolas for benches at the top of the hill —continues
20. Main entrance/gravel/grade - complete
21. Wind Door — wind door on kitchen side needs openers
EFTA00583611
- wind door stops
22. Landscaping —jospehone to visit and orgaine garden
23. Solar lights brice to order 500 landscape lights
24. Roads — grade all roads — Wednesday 6/6 — Tom - please review all roads so you can pitch, drain, with Jules
25. Library — lights on bookshelves need attention
- temperature? Atlantic refrig
26. Main hill — asphalt path
27. Master Suite -
- Large master bed planting
- put self closing hinges on the master bedroom door to the outside
30. New Employee Bathrooms —
31. Gym - add new doors in yoga and ballet room closets
32. Benches -
33. Office Pavilion - east window in Sarah's office is rusted outside
34. Danny Vicars — schedule boat driving lessons
35 jermain to re do internet at hangar
EFTA00583612
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00583611.pdf |
| File Size | 94.9 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,988 characters |
| Indexed | 2026-02-11T22:50:16.104972 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.