1. Clean Up - make as many barge runs as necessary
2. Equipment and Vehicles
- Sell equipment
- No machinery off the island unless approved
- Red Polaris Bike - Power Steering Module Installation - COMPLETE
- Lull — replacement parts — due at Tropical 11/1, unable to sail until 11/7 due to value over $2,500
3. Five Palms
- Picture frame — on site, 86 x 70 -
to forward selected picture, will frame locally
- Mirrored siding — will continue to reglue as sections fall off - 17 new sections/glue — ETA on LSJ 11/2
4. Grotto
- Mattress cover — completion delayed due to owner travelling to northeast — family issues, will update ASAP
5. Berm/Too of Hill
- Hydroseed all top of hill/berm — COMPLETE — Brice investigating a different material
6. Triangle
- Must design triangle - awaiting JE direction
- Palms will be relocated once Lull is repaired
7. Flagpole Pool Cabana
- Furniture — desk left Paris, awaiting ETA to STT
- Pace clock — ordered 2 new units -1 for backup — due on site 11/8
- Auto closer on toilet door — David (carpenter) - COMPLETE
- Add some lights near steps — COMPLETE — JE to review when on site
8. Floating Dock
- Jet ski bumpers — COMPLETE — this installation has not resolved the issues of protecting the jet skis
- Sea-Do Jet Ski — will need to review how this unit will be secured at dock
- Dock box top & seat — one final attempt to refinish — David (carpenter) — COMPLETE will reinstall 11/2
- Dock boxes — struts to be replaced — David (carpenter) — box lids keep breaking down/rotten wood when struts
installed — will review when JE on site
- Dock & Floating Jet Ski Dock Carpet - due to leave Tropical 11/31 — David (carpenter) will install
9. Chillax Room
— Requires furniture piece for electrical/media equipment -
forwarded a selection 9/28, 10/1 & 10/30 —awaiting
direction
10. Chillax Bathroom
- walls in vanity area to be painted — JE to select color
11. Mechanical Building Transformer — changed out - COMPLETE
12. Boats
- Lady G — sell — will remain at Nanny Cay until sold
- Big N — repair at AYH dock in progress —hydraulic hoses due Tropical 10/31, boxes to be installed 10/30, painting to
be begin 10/29, electrical refurbishment 80% complete. Cylinders to be installed on LSJ — will discuss timing when JE
13. AC - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees
14. Transient Surge Protection —Tropical shipped to Nassau in error - EDA on STT by 11/6
15. Landscaping — Peter's List
- High road waterfall — rocks to be installed
- Line all roads with stones
- Pop's Garden — require deer protection —Electric Fencing due at Tropical 11/31
- Shade cloth — reviewing propagation of seeds which were planted 10/16. Suggest raised planter beds, using tables
from nursery
- Peter to clean the sides of the road — work in progress
- Black Heli Under Pads — install at top of bike path at MC — ETA on LSJ 11/2
- Review growth of sea grape - engineering area — transplanting has not worked — review purchasing small plants
EFTA00584498
- Take down the ropes at the end of the month on the trees — COMPLETE
16. Roads
- General re-grading of roads — ongoing — Peter
- Betteroads quotes from triangle to crest of road above gym — Asphalt - $71,5000, Concrete - $103,600. Researching
porous concrete option, water drains thru surface, used on St John & St Thomas
17. Library
- AC quote forwarded to Rich Barnett, who had design concerns. Plans forwarded to Atlanta 10/30, engineer will
answer concerns & develop control designs, ETA 11/16
18. New Employee Bathrooms
19. Gym
- New punching bag — installation of the speed bag - David (carpenter) — old unit removed awaiting direction from JE
- New front & back doors installation — David (carpenter) — COMPLETE
20. Beach Office
- complete electrical overall required
- waterproofing/sealing/painting/replace rotten wood — David (carpenter) — will begin 10/28
21. LSJ Mooring — Darren spoke with Army Corp 10/17 — still working on environmental report, will forward ASAP
22. Hangar
- Fuel Containment Pad — via Cecile 10/25 — there is an issue with the site possibly being in a flood zone. Reviewing
with Jaredian Design Group (John Woods).
23. Steel shed — Buck Steel drawings on site. Shed ordered.
Removal of existing bolts patterns & installation of new - David (carpenter)
24. Equipment Purchased
- (3) Terex RL-4000 6kW Light Tower systems — due to arrive at Tropical 10/31
- (1) Skid steer forks — due to arrive at Tropical 10/31
- (1) 2012 John Deere 5101E tractor with 553 loader and 8' blade — delivered to Tropical 10/25 — will sail as soon as
space is available
- (1) 2003 Genie Z60/34 Boom lift — ETA Tropical 11/9
- (2) 2013 S4-Express electric golf cars — ETA on LSJ 11/2
- (1) 2012 JCB 8035Z Mini Excavator purchased - $39,455 — at Tropical. Awaiting bucket from UK, expected ETA STT
11/10
25. LSJ Mats — for all locations — ordered 9/22 — Logo approved 10/16 — in production — ETA STT 11/12
26. Containers — 3 off site. RO & Generators in remaining container, will be removed once Lull repaired
27. Stone Walls — Repair work to replace missing loose stones — Gerry & TJ working as time permits
28. Part Time Employees — focus on finding housekeepers — have a potential candidate, working the next week.
Employment Company Anna found was unable to provide anyone. Advertising
29. Heli Pad - wind sock for Heli pad on site. New wind sock assembly ordered by Larry awaiting ETA
30. Cisterns — need to be cleaned /sealed. Vendor on site 10/20 to review scope of work — quoted expected 11/1
31. Solar - installation COMPLETE - JE does not like the white light", prefers soft white light — JE to review when on site
- Revised proposal from Pure Logic submitted to JE via email 10/22
32. Master Bedroom — door sliders require waxing and alignment — David (carpenter) - COMPLETE
EFTA00584499
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00584498.pdf |
| File Size | 157.1 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 5,970 characters |
| Indexed | 2026-02-11T22:50:26.662959 |