JE Punch List —June 11.2012
1. Five Palms — TOP PRIORITY
- Exterior Door Shutters — removable option
- Painting - outside to be completed after visit
- Furniture — Sofa — leather samples JE will review while on site
- Piano - needs tuner
- Lights - add two more lights to front of Five Palms in trees
- Mirrored siding — Panels sailed 6/8, EDA on STT 6/12
- Glue on site
- Tapestry Molding for Ceiling — Ion
- Transformer building — Building 5/31, 5/25 — final electrical hookup 6/8 — temporarily powered by generator
- Flooring
- Fire pit —gas unit needs to be returned and reordered
- Books —books on site will relocate over the week of 6/4
- Benches — one bench to west north of fire pit
- Road grading
- Piano — at Tropical FL 6/8 — scheduled to sail 6/13, EDA on STT 6/16
2. Grotto -
- Floor resin
- Genset wiring — scheduling to be determined
3. Berm/Top of Hill
- dirt and rock needs on top of hill needs to go ASAP
- hydroseed top of hill
— 4 large planter boxes with small planter inside require construction — size to be determined by JE
- cleanup and excavate — continues
- remove rock screener — completed
- run power to berm center from pull box
4. Engineering/Maintenance Yard
- Steel Shed — foundation in progress
- Metal Sheets - on old building will be replaced week of 6/4
5. Triangle— landscaping direction required from JE
6. Flagpole Pool Cabana -
- Recovering of sofa/chairs
- Furniture — needs new desk — Sarah
7. Entry Tree Lights — installation complete
8. Solutions for Generators — Sound proofing solution forwarded to JE, require direction, wall built
9. Tiki — Darren is contacting the vendor regarding the shields
10. Dock —
- Decking — replace all damaged boards and carpet - complete
- Floating Dock -
- Jet ski Docking - review
- Table/Dock Box — Bill starting 6/4
11. Kite House — review of wooden outside furniture - Sarah
12. Chillax Room — requires furniture piece for electrical/media equipment — Sarah
13. Chillax Bathroom - requires blue rugs for bathroom & vanity area — Sarah
14. Mechanical Building
- Replacement Transformer — approved to purchase — ordered
EFTA00584561
15. Boats
- Midnight Express — purchase Yamaha 300 motors, install by Offshore Marine
- PRO— sell
- Lady G — sell
- Big N - sell
- Calypso — refurbish
16. Gym Road - road grading after Five Palms — continues
17. Timers— review installing timers on air conditioners, irrigation water systems, and lights
18. Beach lighting — per JE, replace existing transformers for the beach lighting of palms around the salt pond
and beach
19. Pergola— construct 3 pergolas for benches at the top of the hill —continues
20. Main entrance/gravel/grade - complete
21. Wind Door— wind door on kitchen side needs adjusting
- wind door stops
22. Landscaping— gardenias
23. Solar lights
24. Roads— grade all roads — Wednesday 6/6 — Tom please review all roads so you can pitch, drain, with Jules
25. Library — lights on bookshelves need attention
- temperature?
26. Main hill — asphalt path
27. Master Suite —
- Large master bed planting
- Door in dressing area — the heavy mirrored door between the bed and bath is beginning to drag on the floor
- Add door handles to shutters on master bedroom door to be able to close from inside
28. Phones —
- Library terrace — phone does not work
- Flagpole— phone in cabana has all the wrong numbers as compared to the list on speed dial
29. Media —sign up for Blockbuster, VUDU, HULU
EFTA00584562
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00584561.pdf |
| File Size | 107.3 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,504 characters |
| Indexed | 2026-02-11T22:50:27.306542 |