EFTA00584590.pdf
PDF Source (No Download)
Extracted Text (OCR)
9 East 7151 Street daily report 6/19/13
•
Emergency hot water heater ordered three new contactor parts from A.O Smith conformation
#SG21143, expected delivery tomorrow 6/20/13.
•
Kitchen 1" floor had meeting with a contractor to repair or replace melted corian panel behind
the kitchen stove I asked contractor if he can turn the melted corian panel upside down and see
if the panel below can repair the damaged area that shows from behind the stove. If that don't
cover the damaged area than give a price to replace the panel.
•
Entrance Picture light installation had meeting with carpenter contractor to give a proposal to
scaffold stair case ,remove silk screens for electrical installation, fabricate new black picture to
mount on the wall to hide the picture light electrical installation and re hang frame and silk
screens . He will send proposal for the above scope work.
•
Con Edison Electric & Steam bill review Electric charges for May 14 to junel3th ,energy supply
charge 67,680kwh $4,096.13, Demand supply 158.4kw ,$2,013.26 total supply charges$6,369.65
energy delivery $2,238.67 ,Demand delivery 158.4kw ,$3,127.36 total delivery charge$6,186.66
total electric charge tax &fees $13,670.68 Steam costs for April 29th to May 30th for 147mlb $
$2,345.30 customer charge $4,397.96 Total with fees and taxes $7,765.97 .
•
Replaced one of two steam trap for the upper floor riser that feed the 6th floor.
EFTA00584590
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00584590.pdf |
| File Size | 42.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 1,447 characters |
| Indexed | 2026-02-11T22:50:27.569988 |