Punch List — perJE directives as of February 6. 2012
1. Slipcovers for sofa and cushions - in production
2. Stereo cabinets - estimate due this week
3. Flagpole lights
4. Dock Box — pending available time
5. Five Palms — stucco, window, hardscape, electrical
6. Grotto — lookout built with metal roof, landings
7. Greenheart wood — steps to Grotto - steps top and bottom
8. Heli garage - Concrete pour
9. Hangar —floor sanding in progress — 401(50' area for slab, 3 foot wall around it — containment for ISO
fuel tank — bathroom and room divider — subcontractor
10. Steel shed have estimate for building, budget to be forwarded 31 Jan - shed quote
11. Triangle, commenced work - triangle road
12. Entry tree lights, confirmed ground lighting Christmas lighting
13. Pebble beach - Solar fridge, light, fan for pebble beach.
14. Library Dehumidification 2nd unit ordered, Sarah office damper needs new board, invoicing issue still need
to sorted out — Sarah's office is to be set at 79 degrees
15. Yellow flowering Alamandra up Old Mill wall and Flagpole hill Peter to train vines to wall
16. Solutions for generators —drawings complete for bid package
17. Fire system — need to review operational and maintenance schedule
18. Top of hill — CLEAN UP - place garbage in circle — build up 10 feet— new helipad
19. Library windows done - shutter in Library
20. Five Palms
- Floor
- Doors location and fabrication
-Lighting schedule
21. Tree transplants — Peter redo the three new trees?
22. Guestroom -
Cabana 3 leaks, Cabana 1 leaks Main terrace — sealing of gutters in progress
23. Tiki
- Shields due end of the month
- Dock box pending available time
24. Sunken garden berm continues
25. Concrete roads at flagpole
26. Concrete triangle
27. Compass - sundial
28. Bench placements — bench on peninsula point — benches, grotto
29. Engineering clean up continues
30. New vehicles
31. Dock Decking - dark stain the dock sample
32. Lighting - adjust landscape lights at night
33. Mgrs Cottage Roof work remains
34. Master bath - leaks
35. Mooring Permit - at Army Corp
36. Too of hill - Clean up continues
37. Rationalize Telephone system Bill and Steve were on 1.5127th to 29th Jan
38. Rock grinder - Purchased
39. The rock crusher, the dirt sifter, and the cement plant should all be operating at full capacity — completed?
40. Gates to hide engineering both at top and bottom of hill - Bill Adams' gates
41. Engineering service road reshaped - Continues
EFTA00584656
42. Dock lighting - Barn lights for structures, spots for dock and barge ramp on remote
43. Dock house completed except for final electrical
44. Roads — from intersection to Flagpole
45. Guest house — site layout needs to be confirmed
46. High gloss polyurethane deck finish applied to nautilus shells 30th - nautilus lights
47. Replacement transformer Mechanical building. Reviewing bids, will submit for approval 1 Feb
48. Photos for Chillax bath — installed
49. Let Jules and Peter bulldoze road now from top of hill down towards Flagpole Done
50. Floating Dock, new design to be submitted 3rd Feb
51. Remove Rusty metal dock Columns - Reviewing options
52. New Lull - will forward options next week
53. Fat Cat- inspection completed, buyers contacted
54. Big N- inspection today
55. Midnight Exoress repairs complete
56. Socket on terrace
57. Paint Engineering plywood green
58. Brian's bonus
59. We need to re-hydro-seed, fertilizer, get lots of hydro-seed
60. Concrete the dock
61. Trash bin location
62. Heli approach lights
EFTA00584657
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00584656.pdf |
| File Size | 108.7 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,579 characters |
| Indexed | 2026-02-11T22:50:28.255775 |