Memorandum
To: Jeffrey Epstein
From: Emad Hanna
Date: 07-18-05
Re: LSJ Project # 27 Landscape Lights
Paul Gandy mentioned the original survey called for a little over 1 mile of
pathway lighting only would be around $ 100,000, which he admitted that he
made a mistake on and it is his fault. He stated in an e-mail dated 7-14 (see
attached copy) that his estimate is about $ 200,000 higher than originally
anticipated.
Upon receiving the new site plan based on the specs given to Miles, which
included the following:
1) Increase the total pathway length to nearly 4 miles
2) Utility conduits and duct banks for future facilities
3) Irrigation water
4) Communication lines
It was determined to have all utilities in a common trench.
Gandy estimates the lighting project only to take about 4 months at a cost of
$ 430,000 and the lighting and duct bank to take about 9 months at a cost of
$ 1,000,000.
Thank you,
Emad
EFTA00586313
Document Preview
Document Details
| Filename | EFTA00586313.pdf |
| File Size | 46.7 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 949 characters |
| Indexed | 2026-02-11T22:50:41.417129 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.