EFTA00616757.pdf
PDF Source (No Download)
Extracted Text (OCR)
MEMORANDUM
July 17, 2015
To: Andrew Farkas, Jeffery Epstein
From: Tom Mukamal
Cc: Frank Garrison, Eric Simonton, Kenny Jones
RE: American Yacht Harbor Asset Management Strategy
Since the onset of the financial crisis, the capital investment strategy for AYH has been (A) to preserve and
extend the life of the existing infrastructure for as long as possible, immediately addressing any life safety
concerns, and to make limited strategic investments in the infrastructure that provide near term ROI or are
necessary to preserve service standards and business continuity, and (B) to preserve and build a working
capital surplus in order to (i) maintain a cash balance sufficient to mitigate a potential catastrophic windstorm
event loss (note our windstorm deductible is 5% of the total loss capped at $1MM) (ii) to secure long term re-
financing and (iii) address longer term infrastructure issues at the marina in a cost effective manner.
Preservation of Infrastructure/Life Safety & ROI
Capital infrastructure spending at the property was restricted during the recession as cash flow levels declined,
however spending has now increased steadily over the last few years. Capital spending in 2013 was $123,746,
in 2014 it was $346,420, and in 2015 it is $341,599 YTD and is projected to be approximately $400,000 at year
end. Based upon 2015 projected total revenue (including fuel net profit only) estimated to be approximately
$5.3MM, this would equate to a capital investment rate of 7.6% of revenues in 2015.
In recent years, major CAPEX projects have included (not limited to):
•
Marina bathroom refurbishment
•
Marina access control gates and fencing
•
Site signage
•
Railing replacement throughout the property
•
Cistern refurbishment
Major on-going Repairs & Maintenance projects include:
•
Parking lot striping
•
Building painting
•
Driveway repairs
•
Roofing repairs
•
Dock decking repairs and resurfacing
Although there has been much accomplished at the property in the last few years, there is still a substantial
amount of refurbishment and maintenance anticipated in the coming years. With the capital intensive
handrail project wrapping up focus will be shifted to the following projects during the remainder of 2015 and
2016:
•
Elevator cab refurbishment (at recall of onwerthip)
EFTA00616757
•
Parking garage ceiling, lighting, and painting improvements to improve appearance and uniformity (at
request of ownership)
•
Building stair repair/replacement
•
Roof Gutter and flashing replacement
•
B/C Building decking improvements to improve uniformity and aesthetics
•
Landscape refreshment to improve curb appeal
•
P Dock Refurbishment (AYH will contribute $59,500 towards the approximately $350,000 that St
Thomas Sport Fishing Center will be investing in the refurbishment of P Dock. The scope of the
project includes sleeving the existing piles, reinforcing the stringer and pile lateral load system, re-
decking and running new utilities.)
Working Capital Surplus
At December 31, 2015, we estimate that there will be a working capital surplus at AYH of $1.8MM. There are
many competing demands on these funds as outlined below.
Loan Refinance
Management has placed this project as the first priority with respect to the use of any working capital
surplus. Some or all of this working capital surplus may be required in order to facilitate an extension or
refinancing of the current property loan with Banco Popular, which matures September 1, 2017. The Banco
Popular loan is on extremely favorable terms. It has an outstanding principal balance of $12,913,200 at July
1, 2015, amortizes over a 30 year period and bears interest at LIBOR plus 2.000%. Executing a multiyear
extension of this loan is important to realizing future value at AYH and it is possible that Banco Popular will
require a principal payment in connection with an extension or a refinance. We were informed by Banco
Popular that we should receive a response to our extension request before the end of July.
Long Term Deferred Maintenance at lvianna
The marina structures are approximately 30 years old. A large scale refurbishment or redevelopment
of the marina will likely be required over the next several years. The marina has been kept functional with a
steady repairs and maintenance program. The strategy employed has been to maintain the docks and utilities
at a level that ensures business continuity and safety. On-going decking and re-surfacing repairs and servicing
of the utility systems have been the focus.
To date, there has not been sufficient market justification to undertake a wholesale redevelopment of
the marina. Market conditions (including weak slip demand, high utility costs in the USVI etc.) and the
physical limitations of the site limit the potential upside of any redevelopment scenarios. A conceptual
redevelopment study by ATM (IGY's engineering subsidiary) conducted in 2013 produced a new marina
layout that included larger slips to meet future market demand (assuming a broader market recovery), but also
requires dredging and shoreline stabilization to make better use of inner slips. The overall concept reduced
available linear footage (although increased "usable" linear footage of dockage) when compared to the current
layout, and was estimated to cost between $4MM and $5.5MM assuming dredging and permitting hurdles
could be overcome.
In 2015, ATM will be submitting on American Yacht Harbor's behalf an application to secure federal
grant funding to partially finance the market, engineering, and bathymetric studies and designs necessary as
the first step to redeveloping the marina. The cost of this work is approximately $75,000. The project would
be eligible to receive 25%-50% of the total cost of the effort under the US Fish and Wildlife Service Boating
Infrastructure Grant program ("BIG Grant"). The Wildlife & Sport Fish Restoration program grants
between $12-16MM annually nationwide. Through ATM, we are intimately familiar with the program and
EFTA00616758
have secured over $15MM in funding for its clients in recent years. The application is due in September,
2015 and if successful, funding would be granted in early 2016. The engineering work would commence
immediately upon funding approval.
Once the marina redevelopment project is fully defined, a second round of BIG Grant funding could
also be sought to offset the actual construction costs of the project. Partial funding for the construction of
the project could be applied for in 2016 and potentially received in 2017, at which time permits and
contractors could conceivably be in place. The BIG Grant funding of 25-50% of the project would have a
significant impact to the financial return analysis of the project.
Management is also waiting to see the results of the "P' Dock reconstruction project being
undertaken by St Thomas Sportfishing Center, which will likely provide useful insight into the costing and
methodology of the AYH marina redevelopment. Specifically, whether existing piles and structural members
may be reinforced at a lesser cost or whether complete demolition and replacement is required.
Assuming new financing is obtained without the requirement of a significant principal paydown, our
goal is to attempt to secure a federal grant and phase in the refurbishment over multiple years, such that the
marina redevelopment may be funded out of the current cash reserves and operating cash flow. This will be
highly dependent upon the availability of BIG Grant funding, the ultimate cost and scope of the project, the
extension and/or refinancing of the bank loan, and overall market conditions (which are improving).
EFTA00616759
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00616757.pdf |
| File Size | 201.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 7,772 characters |
| Indexed | 2026-02-11T23:05:51.337674 |