EFTA00635963.pdf
PDF Source (No Download)
Extracted Text (OCR)
From: "Gary Kerney"
To: "Jeffrey Epstein" <jeevacation@gmail.com>
Subject: RE: FW: CZM
Date: Wed, 03 Mar 2010 14:36:21 +0000
correct, I talked to Bob and he explained the plans still need to look like real plans, floor plans, with square footages, and
elevations as well as perspectives to convey images that the CZM staff can visualize. The package will require the same
amount of effort whether they are real or not.Dejongh has been our adviser on CZM submittals and knows their requirements
and knows the plans are for permit only and will be changed after intitlements.He didn't work off of percentages to calculate
his fee and based it on the time it would take to do the plans, fixed fee.
From: Jeffrey Epstein [mailto:jeevacation@gmail.com]
Sent: Wed 3/3/2010 7:28 AM
To: Gary Kerney
Subject: Re: FW: CZM
he cannot desin„ these are only throw aways for czm purposes..
On Tue, Mar 2, 2010 at 12:30 PM, Gary Kerney
Normal archectual fees for schematic design are 20% of the construction costs.
The proposed fees are below 20%
my estimates:
Dejongh
cottage — 2700 sq.ft. @ 500=$1,350,000 @ 20%=$27,000
$16,230.77
pool --1800 sq.ft. @ $1000 41,800,000 @ 20% =$36,000
$16,230.77
piano —1600sq.ft. @ $750 41,200,000 @20%424,000
$12,984.62
AN - 1050 sq.ft. © $4004420,000 @20=$8,400
$11,361.54
what little he's over on the ATV is covered by what he's under on the rest.
comments?
Sent Tue 3/2/2010 11:01 AM
To: Gary Kerney
Subject Re: CZM
Seems very high what do you think ad it merely schematics
Sent from my iPhone
On Mar 2, 2010, at 9:42 AM, "Gary Kerney"
Jeffrey
Attached is the CZM Dejongh proposal for $56,807.69 ,5 week
Ok to execute?
Gary
> wrote:
> wrote:
EFTA00635963
From:
Sent: Tue 3/2/2010 9:10 AM
To: Gary Kerney
Subject: RE: CZM
[mailto:
Gary:
I have attached the Fee Proposal for preparing the 4 Schematic Design sets for the buildings you stated below.
Please call when you have reviewed it.
Robert deJongh
From: Gary Kerney [mailto:
Sent: Monday, March 01, 2010 10:25 AM
To:
Subject: CZM
Donna
Do you have the proposal for the schematics for the 4 CZM exhibits
1.pool building
2.cottage
3.piano room
4.atv building
and a schedule
Thanks,Gary
<Fee Proposal Schematic Design CZM Submittal 1 March 2 2010.pdf>
■sssserrrrrrrrrrrrrrrrrrrrrrrrr******rrrrrrrrrrrrrrrrrrrrrr
The information contained in this communication is
EFTA00635964
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail.com, and
destroy this communication and all copies thereof,
including all attachments.
EFTA00635965
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Email Addresses
Document Details
| Filename | EFTA00635963.pdf |
| File Size | 113.1 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,954 characters |
| Indexed | 2026-02-11T23:12:27.326321 |