From: Daphne Wallace
To: "Jeffrey E." <jeevacation@grnail.com>
Cc: ann rodriquez
>, Rich Kahn
Subject: Re: R.O. & Generator Bldg. Revisions
Date: Wed, 22 Apr 2015 20:26:10 +0000
Greetings Sir,
John's response:
The flat roof is possible. It would have to be a slightly sloping shed, subject to the building's manufacturer. We
can design it and show the steel building manufacturer what you want.
Respectfully, Daphne
On Wed, Apr 22, 2015 at 2:40 PM, jeffrey E. leevacation@gmail.com> wrote:
on builiding b can we have a flat roof?
On Wed, Apr 22, 2015 at 3:14 PM, Daphne Wallace <
wrote:
Greetings Sic
Revisions from John for your review and comments.
Respectfully, Daphne
Forwarded message
From: John P. Woods, AIA
Date: Wed, Apr 22, 2015 at 2:03 PM
Subject: R.O. & Generator Bld . Revisions
To: Daphne Wallace
, Cecile de Jongh <
rodriquez
Daphne,
, ann
Attached are the revised drawings for the R.O. & Generator Building Roofing project. These changes are
based upon comments from Mr. Epstein at a recent site visit on Friday, April 17, 2015. In summary, the
changes requested are as follows:
1. The longer building (R.O. Bldg.) will be expanded to a width of 60 feet. There will be roll up doors on
both of the short ends. The two long sides will have no openings. The exterior sheathing shall be a typical
metal siding provided by the steel building manufacturer. The eave height of the building shall be reduced to
12 feet to minimize the height of the structure. This will also result in the roll up door height being reduced
to 10 feet.
EFTA00644897
2. The shorter building (Generator Bldg.) will have exterior sheathing that is the typical metal siding
provided by the steel building manufacturer. The height will be increased to 20 feet to accommodate a roll
up door 16 feet in height. This is the minimum height established by the LSJ maintenance staff to
accommodate the roll on roll off activities of the dumpsters.
I would like to add some observations regarding the change in heights of the two buildings. For one, it
doesn't make sense to minimize the height of one building while the other must be a full 8 feet higher. The
Generator building now looks out of proportion with that extra height. What may be more appropriate in my
opinion is to consider not roofing where the dumpsters will be located and extend the parapet wall up
another 3 — 4 feet to be almost 9 feet above the roof slab. This will do a lot to visually screen the dumpsters.
You should also consider replacing the dumpsters with enclosed units that have compactors incorporated
into them. Some of these type of dumpsters are presently being used in very visible sites on St. Thomas,
particularly at WICO. Finally, I have also included the revised floor plan for the Maintenance & Workshop
Building, eliminating the Break Room.
JPW
This email is free from viruses and malware because avast! Antivirus protection is active.
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail.com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA00644898
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Email Addresses
Document Details
| Filename | EFTA00644897.pdf |
| File Size | 124.4 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,582 characters |
| Indexed | 2026-02-11T23:16:13.659735 |