From: Daphne Wallace
To: Jeffrey Epstein <jeevacation@gmail.com>
Cc: John C
, Rich Kahn
ann rodriquez
Subject: LSJ Paving Project - July 8, 2014
Date: Tue, 08 Jul 2014 15:33:02 +0000
Greetings Sir,
Cherie Boynes-Jackson of Boyson Transportation and Eason Jeffers of Better Roads spoke this morning
regarding the transportation needs for the paving project.
Boyson says they can do the job. Better Roads outlined their need for 5-6 truckloads of asphalt per day, plus
operating equipment.
Due to the shallow draft (8 feet possibly at high tide) and the immense weight of 5-6 truckloads at a time
(50,000-60,000 pounds), they will have to work out a schedule of 2-3 truckloads per run.
Better Roads says they are planning on the beginning of August for the start of the project, once you have
reviewed and approved the schedule, contract, etc.
I have asked Better Roads to come up with a schedule and timeline that they can present to Boyson on Monday,
July 14. Once Boyson reviews and aligns their schedule with Better Roads, we will submit the proposed
schedule to you for your review and approval.
Respectfully,
Daphne
EFTA00655778
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00655778.pdf |
| File Size | 44.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 1,153 characters |
| Indexed | 2026-02-11T23:20:13.183926 |