From: Mark Tollison <
To: Jeffrey Epstein <jeevacation@gmail.com>
Subject: FW: 71st update
Date: Mon, 14 Oct 2013 16:25:01 +0000
Importance: Normal
Sir,
Update below via RB provided to RK last week in my absence.
Please note we are all pushing vendors to provide their services, or to review their selective areas and to
provide quotes.
I have selected vendors for other quotes for front door, for waxing, and for sheers, which should be coming next
week.
(I am staying on RB to keep pressure on vendors in my absence. He is working very well with me. He will be
using forms I attached for your review with ZR budget to meet RK's requirements on all expenses and vendor
quotes.)
I am reviewing candidates for 9 E server and LSJ island individual/team as well.
Best regards,
Mark
Mark Tollison
The information contained in this e-mail is confidential and is intended solely for the use of the addressee(s) named above. if you ore not the intended recipient or the
person responsible for delivering this confidential information to the intended recipient, you have received this information in error, and any review, use, dissemination,
forwarding, printing, copying, or other distribution of this e-mail message and any attached files is strictly prohibited. The sender reserves the right to monitor any
communication that is created, received, or sent on its network. !/you have received this confidential communication in error, please notify the sender immediately by
reply e-mail message and permanently delete the original communication.
EFTA00663256
From:
To:
Subject: RE: 71st update
Date: Wed, 9 Oct 2013 20:08:17 +0000
Rich here is an update 1) Fire Alarm project delayed due to equipment problems, John from Gunzer Electric
came to start project last week and smoke detectors that were ordered were the wrong type. John from Gunzer
is working on a new scope of work and different equipment list that should drive the price of the project down.
Stanley Security need to come back in next week to re do the project proposal and equipment list. When new
scope of work is approved and equipment arrives Gunzer Electric will call to schedule installation.. 2) Landover
Cooling Tower at 71st Street to install new cooling tower motors today, the work is in progress various
equipment issues working to resolve installation issues. 3) Front door scanner waiting on proposals from Tyco
Security, Sawyers, and Stanley Security , Stanley is scheduled to come back to look at project again due to Andy
Mc Caffery being let go before he could provide a proposal .4 )Front door restoration we have provided one
proposal Simply Elegant, Marco Restoration looked at the front door yesterday and will provide a proposal also
Artistic Finishing looked at the front door yesterday. 5) Living Room French wax job, Marcos restoration is also
bidding this work and also Artistic finishing, Simply Elegant sent his wood specialist to see the project and Tony
the owner of Simply Elegant will come by tomorrow to see the project due to a very high quote from his wood
specialist because or the removal of the old wax and the height and size of the room and the liability involved.
From:
Subject:
Date: Wed, 9 Oct 2013 15:15:44 -0400
CC:
To:
can you please update me on fire alarm project
is there any other vendor work being performed at house
other bids on scanner for front door, etc
thanks
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor,
New York, New York 10022
EFTA00663257
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Email Addresses
Document Details
| Filename | EFTA00663256.pdf |
| File Size | 101.3 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,538 characters |
| Indexed | 2026-02-11T23:23:10.897332 |