From: Richard Kahn
To: Ann Rodriquez
Cc: Jeffrey Epstein
Subject: Re: Staff Cottage: revised work schedule on cottage from Dave
Date: Thu, 27 Apr 2017 11:04:13 +0000
i believe we have paid 2/3 of work (20k of 30k) yet job not 2/3 complete
now he says he wants 3k draw and will use our labor - not fair nor our initial deal
are we going to bill him back for our labor costs?
not sure i understand his downtown due to noise?
please advise
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York, NY 10022
tel 212-971-1306
fax 646-350-0954
cell 917-414-7584
On Apr 27, 2017, at 6:56 AM, Ann Rodriquez <
> wrote:
David Starofsky
6501 Red Hook PlazaSuite 201
St Thomas VI
309-912-2114
Revised Schedule for LSJ Cottage Rmodeling
Apri 29th Start painting inside kitchen, Laundry and office areas
Cannot finish painting rest of area due to electrical panel needs installed and air conditioners need
replacing.
May 1-5th install kitchen cabinets, exhaust hood for stove, appliances and interior doors. Also
Hughes electric will install all plugs and lights for new addition. He was contracted for 4,000.00 with
permision from Brice because Danny Vicers did not have time to complete it. He was not contacted
to install new electric panel if this needs to be done it will be an additional cost. All electric originally
was to be done by in house empoyees.
This is based on hardware for doors to be bought
May 8-12th Finish drywall rest of area bedroom and living area if AC and Electric panel is installed,
work on finishing outside tile and outside deck if plumbing is finished for downspouts from roof. This
is in house work.
EFTA00679033
May 15-19th Finish lose ends until windows, doors and skylights come in. I placed an order for these
March 16th and were to be here already. When I called about delivery he had not ordered them at all
so when he ordered them delivery is Nay 19th
May 22-May 31 install windows, doors and skylights. Then complete tile work inside and out need
doors installed to finish tile. Roof and install gutters.
Outside new area ready for exterior painting also have advised that it can be completed two weeks
ago
Up to this date I have had 76 hours of downtime due to noise which resulted in 280 man hours This
is almost two weeks of time loss.
I am sure that with Anna"s help to get electric panel resolved , plumbing work done, ac completed
and painting to be done by in house we can complete this by above date.
I have drawn 20,800.00 so far and balance of 9,200.00 is left. I will hold back 6,200.00 till job
completed and draw 3,000.00 to pay employees til job finished.
Ann R.
Begin forwarded message:
From: david starofsky
Date: April 27, 2017 at 6:05:57 AM AST
To: Ann Rodriquez <
Subject: revised work schedule on cottage
Reply-To: david starofsky
Anna
I have attached a revised schedule for your review. I know that with your help on electric panel, plumbing and completing
new AC units we stick to this schedule
Also I noted the amount of down time due to noise and Mr Epsteins requests.
Thank you for your time and consideration on this
Dave
<revised Isj cottage schedulestf>
EFTA00679034
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Phone Numbers
Document Details
| Filename | EFTA00679033.pdf |
| File Size | 116.2 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,212 characters |
| Indexed | 2026-02-12T13:40:15.149070 |