From: Warwick Wicksman <
To: Gary Kerney
CC: Tom Sze <
>, "
Subject: RE: flagpole pool
Date: Wed, 23 Feb 2011 19:40:59 +0000
Ok. Will call you tomorrow around 10am LA time.
Warwick
Warwick Wicksman, AIA
Principal
Gensler
From: Gary Kerney [mailto:
Sent: Wednesday, February 23, 2011 11:36 AM
To: Warwick Wicksman
Cc: Gary Kerney; Tom Sze;
Subject: Re: flagpole pool
I was in physical therapy when you called ,any time tomorrow ok
Sent from my iPhone
On Feb 23, 2011, at 3:10 PM, "Warwick Wicksman"
Gary,
> wrote:
Please let me know when we can speak about this more. I am concerned about just drawing
something up, and having it built, with no real "design". I do not recommend building the pool
house with no relationship to the design of the adjacent cabana structures. This will be pretty
visible from above when Jeffrey flies in, and from the sea, and it needs to look right.
I am available today until 12 LA time, or 2-4. Also tomorrow after 10am LA time.
Thanks,
Warwick
Warwick Wicksman, AIA
Principal
Gensler
EFTA00683793
From: Warwick Wicksman
Sent: Wednesda Februa
23 2011 7:22 AM
To:
• Tom Sze
Cc: leevacat
noi@gmail.com1;
;
Subject: Re: flagpole pool
I'll get you a proposal for plans sections and elevations today.
Thanks,
Warwick Wicksman
Principal
Sent from my BlackBerry Device.
From: Gary Kerney <
To: Warwick Widcsman; Tom Sze
Cc: leffre E stein <*eevacation gmail.com>; William Rowles <
<
>
Sent: Wed Feb 23 07:20:27 2011
Subject: RE: flagpole pool
Warwick
>;
It is a very simple building,and I gave you the design outline,' will do structuals here and we are using trusses.' would
think you can get me a set of drawings in a couple days.
Please call me
Gary
From: Warwick Wicksman [malt°
Sent: Tue 2/22/2011 8:13 PM
To: Gary Kerney; Tom Sze
Cc: Jeffrey Epstein; William Rowles;
Subject: RE: flagpole pool
Gary,
I got the sketches you sent, and attached is an updated plan sketch based on the new comments. But I am confused about
what you are asking us to provide. Our proposal was for conceptual design. It sounds like you are jumping from that to
permit drawings in one week. Is that what you now need? And who is engineering the building, including the slab and
foundations?
Thanks,
Warwick
Warwick Wicksman, AIA
Princi al
Gensler
EFTA00683794
From: Gary Kerney [mailto
Sent: Saturday, February 19, 2011 7:09 AM
To: Wanvick Wicicsman; Tom Sze
Cc: Jeffrey Epstein; William Rowles;
Subject: flagpole pool
Wawick
Specifications for construction development drawings.I need a quick turn around ,can form slab next week.
Revised bath and kitchen programs attached
Revised site plan attached
BUILDING
block structure
10' ceiling
plaster finish in and out
truss roof
insulated and cornmeal roofing same as main compound
crown molding and copper gutter same as main compound
roll down hurricane shutters on 8' sliding glass doors(jeffrey mirrored?)
mechinacial awnning over sliding door
all other doors slabs
INTERIOR
floors stained concrete floors
manufactured kitchen cabinets
30" refrigerator
30"range
Ice maker
dbl. sink
bath to be ceramic tile floor and shower(small 1"+-)
wood vanity top,with vessel sink
erotic shower fixtures all other American Standerd or eq.
corner sconces in livingroom
recess can liting
all liting on dimmers
all base wall outlets to be I/2 switched
POOL
current thinking to reflect on next generation of image review
10x30 shade structure one each side
2x2 plaster col's 9' high
10" thick solid top ( 2' overhang?)
ceiling cans,col. sconces,ceiling fans
EFTA00683795
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00683793.pdf |
| File Size | 131.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,625 characters |
| Indexed | 2026-02-12T13:41:30.537662 |