MEMORANDUM
TO:
Mr. Marc Poland, Vice President
Mr. Howard Germon, Regional Sales Manager
Mr. Chris Shurkus, S-76 Program Manager
cc:
Mr. Geor e Reenstra
FROM:
Jeffrey Epstein
RE:
S-76C++
76TD6167A
DATE:
January 27, 2010
By memorandum dated January 4, 2010, I made it abundantly clear to you
that a delivery after January 20, 2010 was completely unacceptable.
I worked with Sikorsky to close on Green Delivery at the eleventh hour in
December 2008, so that you could reflect that on your books for 2008. When
Sikorsky could not meet the original July 2009 delivery deadline under our contract,
I agreed to extend it until September 2009. When Sikorsky again could not meet the
extended deadline, I reluctantly accepted an extension of that deadline until
December 7, 2009 on assurances from Sikorsky that December 7 was the absolute
and final extension. Once again, Sikorsky failed to meet its obligations.
Chris Shurkus again requested a delivery extension which he verbally
advised Larry Visoski would be no later than January 15, 2010. I explained to you in
my January 4, 2010 memorandum the need for the aircraft to be ready and in Palm
Beach by no later than January 20, 2010 so that it could be displayed at the La Bella
Ferrari and Aircraft Show at Jet Aviation on January 21, 2010, which was planned jointly
by us and Sikorsky's marketing department. In my January 4, 2010 memorandum, I
advised Sikorsky that if the aircraft were not delivered by January 20, 2010, I would
deduct $50,000 from the balance due at delivery and would continue to deduct $50,000
for every two-week period thereafter that delivery was delayed.
I received no response to my January 4, 2010 memorandum and no January 20,
2010 delivery. Instead, Sikorsky attempted to impose on me yet another amendment to
our contract, which provided for a further delay of presentation until January 27, 2010, of
final delivery until January 30, 2010 (note that, among other defects, the draft amendment
1
EFTA00722159
mistakenly indicates the dates as January 27, 2009 and January 30, 2009, respectively)
and feebly attempted to make amends with an additional $50,000 parts credit and an
extension of time within which to use New York area charter hours which are of minimal
benefit to me.
Sikorsky's repeated delays putting off delivery now more than 6 months after the
original contractual delivery date are outrageous. I have no obligation to accept delivery
at this late juncture and reject your proposed amendment, which I note Sikorsky was
unable to comply with in any event as it is January 27, 2010 and the aircraft is still not
available for presentation today. If we are to move ahead, in addition to the $50,000
spares credit now owing to Air Ghislaine as a result of Sikorsky's failure to comply with
the December 7, 2009 delivery deadline, I require confirmation of Sikorsky's agreement
to a $50,000 deduction in the balance due at delivery and a further deduction of $50,000
for every two-week period after January 20, 2010 that delivery continues to be delayed.
My patience is at an end. Your prompt reply is expected.
2
EFTA00722160
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00722159.pdf |
| File Size | 102.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,169 characters |
| Indexed | 2026-02-12T13:51:45.716810 |