I cannot convey to you strongly enough how displeased I am about Sikorsky's failure to
meet its second extended completion deadline of December 7, 2009, a deadline which
Sikorsky assured me was absolute.
As you know, the original deadline in our contract was July 2009. That deadline was
extended until September 2009. At our meeting in NY early this past summer, Sikorsky
acknowledged Sikorsky's responsibility for being unable to meet that extended
September deadline and requested another extension, repeatedly assuring my
representatives both at that meeting and in subsequent telephone calls leading up to the
second extension that "there is no way that we are not going to make this deadline." We
reluctantly agreed to your request to extend the deadline until December 7, 2009, based
on Sikorsky's assurances that this was going to be the last extension. Well before that
deadline, on October 13, 2009, I even notified Howard Germon, personally, of certain
completion issues and requested his assistance to resolve them and to make sure that we
met the December 7, 2009 completion deadline.
To my astonishment, that second extended December 7 deadline has come and gone.
Although I was to receive a letter from Chris Shurkus over a month ago explaining the
reasons for Sikorsky's failure to meet this deadline and specifying a new and final
delivery date, which Chris initially promised Larry Visoski would be no later than
January 15, 2010, I have received no such letter. All that we received was a draft
Amendment to Air Ghislaine, Inc.'s purchase agreement which provided for a January
25, 2010 presentation date and a January 29, 2010 delivery date.
1
EFTA00722161
As Lany informed Chris more than three weeks ago, the January 25, 2010 and January
29, 2010 presentation and delivery dates are totally unacceptable. Although Chris has
informed Larry that Chris is "working on it," we have yet to receive a satisfactory
resolution. As we also informed Chris, Air Ghislaine, Inc. expected to have N722JE in
West Palm Beach by no later than January 20, 2010 because it plans to display the
aircraft at La Bella Ferrari and Aircraft Show at Jet Aviation on January 21, 2010. The
plan to display the aircraft at this show was made jointly with Sikorsky's marketing
department. John Sarter informed Larry that Sikorsky Marketing desires to display Air
Ghislaine, Inc.'s S-76 at this show and advised Larry that Sikorsky will pay the $7,000
display fee for that purpose.
Under the circumstances, if Sikorsky fails to deliver N722JE in time for the La Bella
Ferrari and Aircraft Show on January 21, 2010, it is only appropriate that additional
compensation be provided. To that end, if delivery is not made in time for the show (i.e.,
by no later than January 20, 2010), Air Ghislaine will deduct $50,000 from the
outstanding completion balance due at delivery, and will deduct an additional $50,000 for
every two week period thereafter that delivery is not made. We understand the STC
process and the lengthy delays that may arise for WiFi certification and would be willing
to depart Keystone with the WiFi operational, but with circuit breaker pulled, while the
FAA issues proper approved STC certification paper work, if necessary.
I am sure that I need not remind you that when, at the eleventh hour, Sikorsky sought our
assistance because it needed to close on the green aircraft before the end of 2008, my
people rearranged vacation schedules and made it happen to accommodate you. Why is
it that I am unable to receive the same diligence from your organization. Please resolve
this now. I have been more than patient.
2
EFTA00722162
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00722161.pdf |
| File Size | 119.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,923 characters |
| Indexed | 2026-02-12T13:51:45.741468 |