EFTA00722163.pdf
PDF Source (No Download)
Extracted Text (OCR)
Maguire Group Inc.
Architects / Engineers / Planners
GROUP
110 Corporate Drive, Suite 6
Portsm
Phone:
Fax:
E-Ma :
March 14, 2007
Mr. Darren Indyke
Little St. James LLC
St. Thomas, USVI
do NY Strategy Group
The Villard House
457 Madison Ave., 4th Fl.
New York, NY 10022
RE:
Engineering /Architectural Services — Work Order No. 1.
Redesign of Office Pavilion
Dear Mr. Indyke:
Barry W. Kimball, PE
Senior Vice President
Maguire Group Inc. (Maguire) is pleased to present this proposal for Work Order No. 1 under
our Master Agreement to provide engineering and architectural services for the revised Office
Pavilion on Little St. James Island. This work order is based on the general scope of services,
terms, and conditions described in the Abbreviated Standard Form of Agreement Between Owner
and Architect herein known as the Master Agreement, dated February 8, 2007. In general, the
services proposed in Work Order No. 1 include architecture and civil, structural, mechanical,
electrical, and plumbing engineering to design the Office Pavilion building as shown on the
concept plans prepared by Molyneux Studios dated February 2007.
Services will be provided for all phases of design and construction as described in Article 2 -
Scope of Architect's Basic Services in the Master Agreement. A more detailed description of the
services to be provided is as follows:
Office Pavilion
The Office Pavilion in its new configuration will be approximately 3,000 square feet in area and
located on the island's northwest bluff. The building's foundation will be constructed of full
height reinforced concrete walls engineered to appropriate thickness and reinforcement, pending
the findings of a wave / impact study presently underway. A full height mechanical room will be
located within the Southeast corner. The building's super structure will be constructed of
structural steel and reinforced concrete masonry unit (CMU) walls and a steel roof truss system.
The major revisions to the building design, as previously developed to building permit status, will
be as follows;
Architecture — Maguire will become the "Architect of Record" assuming full coordination and
technical responsibilities for implementation of the interior and exterior architectural design
concepts prepared by Molyneux Studio. Maguire's part of the project does not include any work
associated with design, purchase or installation of construction materials provided by Molyneux
Studio. Preliminary code, product, and systems research will be undertaken along with review of
the casework/panel shop drawings for coordination into the design. Maguire will prepare
construction documents including architectural plans, elevations, sections, details, and schedules
along with project specifications. Individual bid packages will be prepared for bid solicitation by
Winner of Two Presidential Awards for Design Excellence
EFTA00722163
Little St. James LLC
Mr. Darren Indyke
Page 2 of 3
the Construction Manager using AIA 2001 contract documents.
Site/Civil- Site design will include an ocean wave analysis to determine the potential for wave
during a major storm event to reach Office Building. Structural design loads will be developed if
the initial analysis shows the potential for wave action on the building. Detailed layout, grading
and drainage plans will be prepared based upon the conceptual site plan prepared by Molyneux
Studio. Utility design will consist of a new water service supplied from the adjacent master
bedroom and an ejector sewerage pumping system for discharge into the existing septic system.
Structural —The full height basement area will be limited to an HVAC mechanical/electric room.
The roof diaphragm will be redesigned to accommodate the new roof plan and interior dead loads.
Provisions for future plumbing, water and waste piping to be provided. The foundation and walls
will be designed to resist wave action loads as required by the wave analysis.
Mechanical — The chiller will be remote from the building and the air handler units will be located
in a basement mechanical-electrical room with air handler. Intake louvers will be situated on the
southwest wall. The ductwork will be designed to accommodate the building floor plan. Duct
material, insulation and duct locations will be coordinated with a sound attenuation consultant
hired by the Owner.
Electrical — A transformer will be located in a remote location coordinated with the sound
attenuation consultant for transformer noise reduction. Lighting and power system layouts will
match the new basement and first floor plans. Lighting control switches will be minimized.
Electrical loads will be recalculated and diagrams modified to reflect the new floor plan. The
design will be coordinated with Molyneux's lighting fixture selection and the casework/panel
shop drawings to ensure coordination with electrical work within the casework.
Plumbing —A new plumbing layout will be developed to match new office floor plan, including
downspouts, vents, waste and water piping and to plumbing service under slab piping for future
use as guest quarters.
Technical Specification — Technical specifications using CSI format and Master Spec. will be
prepared for the parts of the project that Maguire has design responsibility. The work does not
include any specifications associated with the purchase, fabrication or installation of materials
being supplied by Molineux Studio
We anticipate three design submissions; 30% schematic design for Owner review and approval,
80% Building Permit package for owner review and comment, and a 100% Construction plans &
specifications. Biweekly design coordination meetings will be by teleconference and we
anticipate one design review meeting to be held in our Foxborough, Massachusetts office. No site
visits are included in the proposal.
FEE
The scope of services is as anticipated in the master agreement. Revisions will be made to fee to
match any significant revisions to the proposed building. We propose the engage in the above
design services on an hourly basis plus reimbursable expenses utilizing the hourly billing rates
established in the Master Agreement. Invoices will be submitted monthly based upon the hours
and expenses charged directly to the project in the proceeding months. For planning purposes we
suggest the establishment of Work Order No. 1 budgets as follows:
Design Phase Services
$197,447
EFTA00722164
Little St. James LLC
Mr. Darren Indyke
Page 3 of 3
Construction Phase Services
$34,736
Reimbursable Expenses
$10,000
Oceanographic Consultants
$17,000
Total
$259,183
Please feel to call me directly if you have any questions. We look forward to undertaking this
important and interesting project.
Very truly yours,
MAGUIRE GROUP, INC.
PA)
Barry W. Kimball, PE
Senior Vice President — Civil Works/Land Development
attachments
Approved and accepted this
day of March, 2007
Darren Indyke — for L.S.I., LLC
EFTA00722165
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00722163.pdf |
| File Size | 204.0 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 7,055 characters |
| Indexed | 2026-02-12T13:51:45.766464 |