LSJ CONSTRUCTION Subcontractor Payout Project: Mechanical Desal October 7, 2010 Trade: Concrete Formwork Requisition #07 Subcontractor Big Bear Construction, Inc. Insurance ex iration: march 1. 2011 Invoice # Phase # Requisition #07 03-120 Original Contract Sum: Change Orders Submitted & Approved: New Change Orders: Total Work Contracted to Date: Total Work Completed to Date: Less Retainage: Total Payments Made to Date: Total Current Payment Due: Balance to Finish including Retainage: Sales Tax Liability: Partial X Final $821,461.00 $4,835.00 $0.00 $826,296.00 65% $541,220.00 a. Subcontractor/Supplier is liable, explaii install only / tax included in contract b. Non-resident Subcontractor/Supplier Bond Applicable: c. Use Tax to be paid by our company: d. Shipping Total Outlays for this contract incl. Sales or Use Tax: JEE approval attached YES NO X Submitted Bill Signed: Date: October 7. 2010 Approved by: Ema signed. fThte $27,061.00 $459,766.75," $54,392.25 dr $312,137.00 None $541.220.00 YES X Invoice Attached NO Approved by: Gary Signed: Date: October 7, 2010 Approved by: Signed: Date: EFTA00722170 LSJ CONSTRUCTION Propel Mechanical Desal hatcontractor full legal name Big BSI COnflruCtiOn, Inc Phases 03.120 Trade Concrete Cannon Ithaca ft Requisition s07 Insurance espiranon 1-Mar.11 Pavan:nil Partial final X Invc•ce/Regq Dale CIO Amounl ftelainace Due Paid Dale Pad Checks Balance COONICI Amount U3,1 1 ,10 621.461.00 CO111 COII2 CO113 CUM COO 07712:10 4.635 00 Requisition el 03/31;10 74 400 00 772000 70 680 00 " 'IL 70.680 00 0.00 RequiStIU)n #2 04/3010 44.475 00 2,223 75 42.25125 ‘/j.. 42.251 25 0.00 Roquisthon #3 05'31110 120.7W 00 6,03500 114.665 00 V Il4,665 4)0 000 Requisition #4 C6/31.10 72.025 00 3.601 25 68.423.75 Vie 68.423 75 000 RequisiemS5 07121/10 57 325 00 2.866 25 54.458 75 r•ore 54 458 75 000 Requismon MS 08/25/10 115,04000 5,75200 109.268110 he I 09 288 CO 000 Raoul:Mon te7 09124110 57255.00 2.862.75 54 392 25 Remo/ben 18 0.00 Recansilon 4/9 000 • Tao 1 541.220.00 1 27.061 00 1 514.15940 459.766.75 54,392 251 Date Revised OCI0Opf 7. 2010 Contract Amount • Phase Contract coo con con COH4 C005 Concrete SW/nye:wig 821,401 00 Trench StapOrt 4,835 00 Downoeun beconaliOn Descnotion Deacnotion Description Contracted To Dale Banc. of Contract w1Relanage 826.296.00 312,137.00 EFTA00722171 APPLICATION AND CERTIFICATION FOR PAYMENT AIA DOCUMENT G702 /ROY :ON/ RA: TOR .I•X Rww ON1S In .14 'Nano VW, OCKO OR Si.. /ewer aC %CV Ef.e•C/19.90P411 9 Rh, 00,41 rqt.14:1 uvneu,Oes &M. ' ,O. ' 04....V_A I .C.N &awe, CVO 1,..,2•1 !tun 20,0 11 9 :0 TO 9'30.221O "4:....4C I a •I310 CONTRACTORS APPECATON FOR OAYMENT KCk.19•S mme ft, Seinen, IS Shao. 002a CO, CCLO' WI. 0.• :C010:t CIMAI39", S'ett O0CV' 4C7h4 S !rag • ORO/1N CONTA.Att REY 2 wtewq.M CAIF9i CA0/1 1 CONTRACT WM /0 OATE Rae I a 21 1 IOTA:. COD/A.11EO. STORED TO DATE :C0'.rG en CVOS s RETANAGE kIVenir•I lityaity tees. no %ire goal N .a.nru wonlele norowcom Dag 9,0NO try r•Ateenon £r4l, nanny...num .r A. Lawnlfi Opactefis MI al nuts '.10.11 Ism ca. ite IVOfi PO anti, pfikyl.C.Wgreafi W 01. MaI nw.uA.. reowti.ce-peof 'roue Dye in' or can wren s`c..., woo. C Nas V.JI.W. CO CONTRACTOR. $4.$35 OC So262Vo '0 6, R9 Near C.0./111ADCA Nt a'C t.1 .4201C 5.444.22020 ! a 5.9)+4 SCanoewo .SrN en WO g/100 $27 6, ‘,111/.../ :Calm C • t ir 0703) 500% /1 cl SON. 4/11rai SO CO taYNO CNON31 -cti; RetnNile Lets 5,a • SO ar TOwr COVrn a 0703, • TOTAE EARNED/ORS RETMNOSE a Fe 4 ENS.Ne1 To1A1 • 6RESPRENICUS CERTIFICATES FOR 9AY1.ENT 4. no ONONtiv Ctlicxel • CURRENT PAYMENT DUE • (*NANCE TO' NSN INCO.ONCI RETO"ACIC 0.%• on Lae E. lv.a soatenan Nn ...conga Ma* ••• ..9‘0, FAN •Ate,i f ' RTINCATE FOR PAYMENT 127 ow co I, ' v •4 'so CO . , $4,0 ys D Ncrenoo rine Cervatt ONE-Am wry re. N. ssANNA. worse.. Nyrry•00.•Nuo. noNnue user "NT* SU-322Th Any ON A0 °Awn. vroC•nacta a Non 0 ANNAN a NamO/A.T<ARIAttO SS le +a rim YS Cane" n9embhin We.. Abp%N. Oi•eNs3 NNANI Aspen a nt Ain 1.1 /2 13700 %%tat/ AMOUNT CERTIFIED CAORGE OROER sip.01./Fo• ail:/';•.S DEDOVIONS %5(0.theconsta0.4.0 0fleNcua 0crAyo• 0000. RN115 OD • 1 1 SO CO 'AM acroa.c .fts mrin I S00O 5101 TOTA..$ I $4 811 00 . 5C u. ‘c I c-Ancis Or :Argo Syr Sa :as CO I 554 3922$ rAr.N. •••411./.01 centre cith, - ay. It Sfififf •14.4.3 I IS N twat rt.. .yams tnewOrictancnYy. ape 0, (token ...parr wet.) COOSINCI By Dals: 0VO.filit VOJ• CW OM ite• tenla pfififito r ire...4 Iv 0•••.4fi Coma or war Ma Gretna 4. D0wvodl Awt.,‘• • Cs &PC T 10% 0.4 vAtUil; hr, WA I .1, r.C.* a.l I NI .9/00CAN Lis thi I bad 114.O% 11) WW .MA .µ Nth venSPIPC., ON IX Moll..92 Viers /030001.00 9.150140141 Nil CV...Wiwi by ntwaTabag a ccrapPlitd DocumoN 0101- CellifiCat.On el 00Cliffltfit'S Ay Ill !fib( YO,IltfiC L•censee. DO. 07 2016 By Sun:, ?• I I EFTA00722172 CONTINUATION SHEET 42400CiAlEPil G103 MA 0:02.444 Ow/003a m talealeon W e Camel CO02 APPUCA1C0 NW WROFICAT1011 PON PAYMENT. 10040 Mothcan 6 lawene0 melrell can nun APPLICA11011140 APPLICATON DATE PERIOD 10 1 060010 0310110 Oros aimeeets re raw ion Goo ion Cornets awe eloODI•Kteespeoe, kse•AniSmaY44% b A a C 0 I E • 0 M , iv NO OISCRO.Veo : CS *Obi i I '0 SOWPA80 Viete W0 an Cams nio suarma.1 SREINIIV nmi. COOKTE0 MO PORIO '00*7! 0.1.6) 1 (G • Cl MAKI -OFKSH C. CI esureKt c i I:Mat WI o AWN KINICUS I P4 MorOCAKto • KOKO • 11 I I SKIM POTitt011ei C OM' X001 SNYAI ROW 100 15003 568 35C CO : SOCA SO 00 566.31000 10.100%1 SC 03 341750 00002 Les Ina tures I SW 93900 $79,50000 SOO) 50 '0) 128 503 00 WOW' WOO '42500 0:1203 Fon. Or w 113 WOW 11150003 SOW 1030 SW 1010) 10)00%, 1000 117500 00004 Iftsumnc• 5850000 53.600 CO 1000 10 00 $O WO CO 10)0LN WOO 42510 00005 fe•oni 6,150003 $15100031 1000 SO 03 115030 0) 24 9211: $4 WO 00 100 00 Soren Miran 55 00) 0) X00000 0144, WOO 5000 91 00001 8000% S1 COM 20100 000% 00007 Vac monis 6/9000 00 Id KO 0) ; Si 500 CC I 13 CO PS SO CO 4100% 53.9%00 3250 MOW Lew Sr Vices SS) 750 03 S12a00 01 1)4.... SOW 00D 112.3C0 00 43 CM SNI 450 OD 61593 00000 Owe Sue icon S16 WO CO 114 POO 03 NCO 1000 in.= CO I0)00%4 50 00 53500 003 .3 Saw SRO ReNCION) SU 80000 S348000) 50 011 SOW MASLOW 1W00191 RICO 170010 0331, Ono Sta. Pow 5595000 1595000 SO 03 1000 169000 10300%1 000 2r JO 00042 Use WoOle Fan SS X0 CO 15600000 1000 50 00 556.13000 10000% 50 00 26'5W 02313 Bate Vous Airbag 1/2 MO 03 53230007 $000 WOO 13220) 00 10300% 50 .00 16350 03014 lias4 Wals Poi 1630000 18 300 CO 1 SO 0) 000 16.130 04 10000% SO OC 3'500 03075 's1 014/04140 SW ram SO See CO 520.97500 171 MO CO 000 132 n5 CO 000% 1419500 115771 COOS '14 0 mad Sao Iberian 537 7W CO SW 625 03 $W 625 03 50 00 1372000 MOM. ION 18624 00012 1s1 04,44165 St Poo UAW CO 54.20003 SOO) WOO $422000 000% 5420000 2100 00)1 1st IN Pont Fan 1»000= in 750 CO otys„ 05003 1000 SS 030 00 4000% 547:0300 12300 00319 'u1, Walls R002420-0 $41 TOO CO 576.68000 WO) SOW SW 083 00 4000% 12502003 BUM MOW 'MR wan. Pc., ISOM CO SO 03 1000 1003 10 00 0004 156[000 0 0) 0)321 Root Soo Fon 0 40000 SO W SOW 000 SO 00 000% 554.4!00: 000 WOZ2 Awl Sob Raker% PO 300 CO SO 0) 1000 1000 w00 COI% 142.00)00 530 W023 Nog Sue Poo $9 KOOS SOW SOW SOW SOW 080% 19.10003 C 01 0;022 Pam% ww Pr Ill 450 CO 000 000 SOW I WOO OW% sl i 45000 cm C0325 Prom wall arnlacte 12 ECO CO SO CO 00O woo we) 000% S2.11000 OW OW26 Prow! WAI Etu. SI 300 CO SOW SOW 1003, WOO 000'4 S390003 000 %COO 10...mese SU 225t0 120.50000 \ a% Se CO:K0 ID 00 : 1.12.90,0) 65 741: III 72100 '125'6 00025 Rao 519268300 $r 5C0 CO 11ka 53.93°C° SOW 36160000 6525% $35(411)0 235000 0:029 COv1 Twos LownY8 CAS 544300) 14435W SO OS SOW 14 WSW 10300%. 000 54175 00330 SOW 5003 10.00 5000 *Own SO 00 000 0,331 WW $1)01 SOW 1000 Kat 10 00 OK OM WM SO 00 9300 SO 03 /1COACt 5000 000 OR01,6000 TOTALS US 2160i $A M 365 CO 05 2 25501 0 000 SS4400 - 6150 % Mid-- S265.01600 t.S/Vri-- $2 , C6 1to vsAte.... 2000 EFTA00722173 Emad Hanna From: Monique Harry Sent: Thursday, October 07, 2010 2:31 PM To: Emad Hanna Subject: Big Bear Construction, Inc Attachments: Big Bear Construction Req 7.pdf I I Emad, Attached for payment via wire Big Bear Construcion, Inc Req 7 in the amount of $54,392.25. Project 1010 Code 03-120. Monique &044) /0//0 EFTA00722174

Document Preview

PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.

Document Details

Filename EFTA00722170.pdf
File Size 839.8 KB
OCR Confidence 85.0%
Has Readable Text Yes
Text Length 8,876 characters
Indexed 2026-02-12T13:51:45.849552
Ask the Files