DARREN K. INDYKE
DARREN K. INDYKE, PLLC
301 East 66'h Street
New York, New York 10065
(212) 517-2052
November
2009
Jay Goldberg, Esq.
250 Park Avenue
Suite 2020
New York, NY 10177
Re:
Design Services Agreement dated May 15, 2009
by and among Juan Pablo Molyneux, J.P. Molyneux
Studio, Ltd., L.S.J., LLC and Jeffrey Epstein
Dear Jay:
I write to inform you about two important and time-sensitive issues which have
arisen in connection with the performance of the Agreement for Design Services between
our clients.
First, by email dated November 18, 2009, Doug Schoettle advised Laurin Goff of
JP Molyneux Studio that the short timeline provided by your clients for the delivery to
Little St. James of the woodworking materials and tools required for Fancelli to complete
its installation was very unrealistic. Mr. Schoettle also advised that Fancelli should
schedule its installation on Little St. James for early January, rather than late December.
In response, by email dated November 19, 2009, Allison Brantley of JP Molyneux Studio
advised that she required a formal extension of the January 1, 2010 completion deadline.
Second, by email dated November 20, 2009, Bryn Schuyler of JP Molyneux
Studio forwarded to my client a photograph of one of the globes which your clients
propose to deliver in satisfaction of their obligations under the Agreement for Design
Services. By email dated November 24, 2009, Mr. Epstein advised Mr. Molyneux that
the globe in the photograph was completely unacceptable.
Mr. Molyneux and Mr.
Epstein agreed that the globes to be delivered, which are reproductions from a John Ford
movie, were to be as depicted in a design which Mr. Molynewc previously gave to Mr.
Epstein. The globe presented in the photograph does not conform to that design. In
addition, the globes are to be waxed and the globe in the photograph is not. Put simply,
EFTA00722286
the pictured globe is a very poor reproduction and not what Mr. Epstein and Mr.
Molyneux agreed to.
In light of the foregoing issues, and in an effort to ensure that office pavilion may
be completed smoothly without additional issues, I have been authorized to extend the
January 1, 2010 completion deadline in the Design Services Agreement to February I,
2010, provided that your clients (1) provide a complete and realistic schedule for the
shipment and delivery to Little St. James of the woodworking materials and tools
necessary for Fancelli to complete its installation and a definitive commencement date in
early January for Fancelli to complete that installation, and (2) provide Mr. Epstein with
confirmation that they will deliver to Mr. Epstein by the proposed February 1, 2010
completion deadline globes, acceptable to Mr. Epstein, which conform to the design
agreed to between Mr. Epstein and Mr. Molyneux.
Please review this with your clients and get back to me promptly.
Sincerely,
/s/ Darren K. Indyke
Darren K. Indyke
EFTA00722287
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Phone Numbers
Document Details
| Filename | EFTA00722286.pdf |
| File Size | 97.3 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,982 characters |
| Indexed | 2026-02-12T13:51:51.039065 |