Maguire Group Inc.
Architects / Engineers / Planners
33 Commercial Street
Foxbor
Ph
•
Fax:
E-Mail:
September 29, 2009
Jeffrey M. McCormick, PE
Project Manager
Mr. Gary Kerney -Representing LSJ LLC (master agreement "owner")
Landmark Land Co.
2817 Crain Hwy
Upper Marlboro MD 20774
Procured through
HBRK Associates Inc.
PO Box 400.
New York, NY 10150
RE:
Engineering /Architectural Services — Work Order No. 17.
Revisions to Mechanical Building
Dear Mr. Kerney:
Maguire Group Inc. (Maguire) is pleased to present this proposal for Work Order No. 17
under our Master Agreement to provide architectural and engineering services for Little St.
James Island. This Work Order is based on the general scope of services, terms, and conditions
described in the Abbreviated Standard Form of Agreement Between Owner ( LSJ., LLC ) and
Architect (Maguire Group) herein known as the Master Agreement, dated February I, 2007.
The following revisions shall apply to the master agreement:
I.
Maguire Group Inc. address shall be revised to 33 Commercial Street, Foxborough MA
02035
2.
Molyneux Studio or any reference to Molyneux shall be replaced by Owner's interior
designer or representative.
3.
Paragraph 1.1.1 "Owners Design Team" spokesperson shall be Gary Kerney in place of
Douglas Schoettle.
In general, the services proposed in Work Order No. 17 includes architectural design and civil,
structural, mechanical, electrical, and plumbing engineering for the Revisions to the Mechanical
Building design scoped with Gary Kerney, September 11, 2009. Services will be provided for
design development and construction documents described in Article 2 - Scope of Architect's
Basic Services of the Master Agreement. A more site specific description of the project scope
and services to be provided is as follows:
Scope
The second phase of the mechanical building construction will include building the
structure as essentially designed between columns 1 through 7, deleting the construction
between columns 7 through 11 and building columns Il through 14 are to become free
standing. The floor plan program between columns 5 through 7 will now be shell
Winner of Two Presidential Awards for Design Excellence
EFTA00722406
Little St. James LLC
Mr. Gary Kerney
Page 2 of 4
construction only, no interior offices/bathrooms etc. Water production to be reduced to
approximately 100,000 gallons per day utilizing reverse osmosis units design of which
including specific mom requirements to be programmed by others, but implemented into
the floor plan design. TSG out of Tampa Dean Bedford contact was providing the water
production previously.
Architecture: Maguire shall remain "Architect of Record" assuming full coordination and
technical responsibilities for implementation of the interior and exterior architectural
design concepts. Maguire will revise the construction documents accordingly. The
program for columns 5 thru 7 to be structural shell only construction.
Site/Civil: Site drawing will be revised to show new building and utility connections as
well as grading to match the new building layout.
Structural: The Structural drawings and details will be revised accordingly to implement
the new program.
Mechanical, Electrical, Plumbing: Existing designs will be revised according to the new
program.
Technical Specification and Submittals: Technical specifications are SI format and
MASTERSPEC® will be revised as necessary for the revisions.
Construction Administration: This will include shop drawing review, request for
information responses, construction sketches and any site investigations or inspections
deemed necessary.
Deliverables
We anticipate one submission for owner review and comment prior to construction sketches.
Coordination meetings will be held by teleconference as needed.
Fee
The scope of services is as anticipated in the Master Agreement and as generally described
above. We propose to engage in the design services on an hourly basis, utilizing the hourly
billing rates attached plus reimbursable expenses. Reimbursable expenses shall consist of mail,
printing, travel, lodging etc.. Invoices will be submitted monthly based upon the hours and
expenses charged directly to the project in the proceeding month. For financial planning
purposes, we suggest the establishment of Work Order No. 17 budgets as follows:
Architecture
$7,000
Structural
$10,000
Mech., Elect, Plumbing
$16,000
Site/Civil
$5,000
Const. Administration
$15,000.00
Reimbursable Expenses
$500.00
Total:
$53,500.00
Winner of Two Presidential Awards for Design Excellence
EFTA00722407
Little St. James LLC
Mr. Gary Kerney
Page 3 of 4
This budget is open ended and is not a "NOT-TO-EXCEED BUDGET" as past history with LSJ
projects dictates multiple scope changes are expected throughout design and construction.
Maguire has and will continue to be diligent and responsive to the clients needs. Your signature
and receipt of a $10,000 retainer will be considered notice to proceed. Please feel free to call me
if you have any questions. We look forward to working with the LSJ, Lafayette and HBRK team
once again.
Very truly yours,
MAGUIRE GROUP, INC.
./104 / 1-4_
Jeffrey M. McCormick, PE
Project Manager — Land Development
Approved and accepted this
day of
2009
Gary Kerney— for Little St. James, LLC
cc: Darren Indyke HBRK, Thomas Hevner -MGI, Eric Douglas- MGI, Files
Winner of Two Presidential Awards for Design Excellence
EFTA00722408
Document Preview
Extracted Information
Locations
Document Details
| Filename | EFTA00722406.pdf |
| File Size | 199.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 5,542 characters |
| Indexed | 2026-02-12T13:51:52.189674 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.