LAFAYETTE CONTRACTORS, LLC
WEEKLY REPORT No. 130
07.31.09
I.
OFFICE AND ADMINISTRATIVE MATTERS
•
Site Management: Tom Melnick continues to manage construction on the island and Bill Rowles continues to oversee.
Gary Kerney is now head of all construction and design.
II.
Communications and Coordination: Systems in and out, being corrected. Still not 100%. No fax capabilities. Tom needs a new
computer for the field trailer. A lease has been signed for the old Lafayette space at AYH. Construction operations will be out of
the Gym on LSJ the week of August 10th.
III.
CONSTRUCTION AND SITE SUPPORT
•
Site and Production Support: Crushing Operation — In operation as time and resources allow.
•
Schedule Update: Manpower diverted to island projects
•
Office Pavilion: Contractual Issues: Construction Progress:
■ Archive Area plaster, punch list completed. Ready for paint. Proposal received from Bluestone to provide
installation labor for casework and trim. Proposal under review.
■ Native stone veneer pointing work nearly completed.
■ Terrace ceiling finish boards 100% complete. Installation of the crown moulding is underway.
■ Electrical rough in Main Office 108 on hold until J.P. Molynewc's visit next week. Expected 6/20/09. DAS to
specify. Awaiting direction.
■ Mechanical work punch list 90% complete. Need selection of lay and kitchenette sinks and faucets. Awaiting
direction.
■ Type B window frame received on LSJ 7/21, installed 7/22, stonework completed 7/31. Negotiations underway for
the glass and hurricane protection.
■ Metal roofing topcoat paint - Contract out to Bluestone Services. Work is 50% completed.
■ Millwork installation completed with the crew they have. Mr. Fancelli arrived to inspect the work. Meeting on site
Saturday 6/20/09 with Fancelli, Molyneux and Doug Schoettle. Awaiting direction.
IV.
Fit up, Finish and Envelop work:
■
EIFS scope being revised- plans and specifications for revised work required for new proposals. Package
leaving NYC on 3/20, expected on STT 3/23. Received, and issued for pricing. Awaiting pricing. Scope
reviewed, tweaked, pricing continues for stock shapes. Awaiting dimensioned sketch on cornice shape. EIFS
package undergoing revisions. Two options presented to JEE. Awaiting decision to proceed. Reviewed on
site. DAS to provide cornice detail by 6/19/09. Awaiting direction. Received direction on sizing of foam
block, enough for pricing. Pricing underway. Pricing received and approved to complete blocking, lath and
plaster on the terrace beams. Work to begin week of 8/3.
EFTA00724425
■
Coral tile cleared and on island. Installation pricing received. Award pending. Approval received. Dennis
Boone on site this week fabricating door and window sills.
■
Approval received for A&I Development to proceed with the Archive Area millwork. Shop drawings
underway. Ismail on LSJ 7/31 to complete final field dimensions.
•
RO/Nlechanical Building:
• Concrete work proceeding according to schedule
■
Newman & Moll touching up seams and tie holes. 95% on punch list completion.
■ Utilities
■
Duct bank installed up to the vault location outside of the service entry.
■
Backfilling continues.
■
Vault slab to begin 8/3.
• Fit up, Finish and Envelop Work
■
Pricing underway to budget the addition of the fuel tanks, two generators, ATC, Controllers, electric, fuel
piping, fire suppression, ventilation, to the Phase 1 structure. Pricing completed pending client review and
approval. Currently compiling an alternative budget. Alternative D completed, under review. Still awaiting
client response. Gary to present to JEE 8/3.
■
CMU walls for the electrical room completed. FP room and stairwell underway.
■
Electrical switchgear room doors and frames ordered.
•
Master Suite Bath
■
Demolition completed at bath area
■
Excavation completed
■
Footing reinforcing to commence 8/3.
V.
DESIGN RELATED ACTIVITIES
•
Archive Area sconce lighting and under counter lighting resolved, sketch issued. Awaiting selection. DAS to provide
sconces, Glidden to provide kitchenette strip.
•
Archive area trim and casework detailed and out for pricing. Trim pricing completed, product ordered. Product received.
Labor pricing received and under review.
•
Outstanding design issues discussed and scheduled with DAS this week.
EFTA00724426
VI.
OBJECTIVES FOR THE NEXT WEEK AND TRACKING OF PROGRESS THIS WEEK
Task
Goal for week of 07.27.09
Status at end of week
of 07.27.09
Goal for week of
08.03.09
Construction
Item - Office
1.
Office Stonework
Completed Type B
window, pointing 90%
complete.
Complete stonework.
2.
Archive Area interior — Casework
and trim package
Pricing received, shops
underway
Begin running trim,
complete shops for
review.
3.
Office roofing work - Rain Guard
roofing complete until EIFS is
installed.
Painting 50% complete
Progress awaiting
instructions. Complete
aintin .
4.
Office: Open Issues Fit up work
progress the procurement and
design issues
Discussed and
scheduled.
Progress pricing and
procurement
5.
Exterior EIFS - Revised EIFS
package out for review
Beam package received
and approved.
Complete pricing.
Begin beam work.
6.
Fancelli casework Installation
Installation completed
Progress awaiting
instructions
7.
Electrical Work (Glidden)
Resolved issues with
Molyneux on 6/20/09
Progress awaiting
instructions
Const. Item —
Mech. Bldg.
1.
Newman & Moll - Complete
punchlist
Punchlist 95% complete. Complete punch list and
final demobilization
2.
Backfill and compaction
Backfill underway
Continue backfill
3.
Waterproofing
Awaiting material
delivery
Awaiting material
delivery
4.
CMU walls
Continue interior CMU
walls
Continue interior CMU
walls
EFTA00724427
Const. Item —
Master Suite
I.
Demolition
Bath area completed
Awaiting further
instruction on columns
and dropped beams
2.
Excavation
Complete
Complete
3.
Footing Rebar
Begin rebar
EFTA00724428