From: Ken-Hao Hsu <1
To: Ga
Kerne
, Doug Schoettle
Cc: Warwick Wicksman
, Tom Sze
, Bryan Oakes
, Jeffrey Epstein
<jeevacation@gmail.com>
Subject: RE: LSJ Update
Date: Fri, 06 Aug 2010 00:25:01 +0000
Attachments: LSJ VIEWS 20100805_LR.pdf
Team,
To follow up Warwick's email, please see attached revised images for your reference.
These images reflect smaller screening room.
Thanks,
Ken-Hao Hsu LEED AP
Associate
Gensler
2500 Broadway
Suite 300
Santa Monica CA 90404
From: Gary Kemey [mallto:
Sent: Thursday, August 05, 2010 4:30 PM
To: Warwick Wicksman; Doug Schoettle
Cc: Tom Sze; Bryan Oakes; Ken-Hao Hsu; Jeffrey Epstein
Subject: RE: LSJ Update
Warwick
These look good,we'll understand all the stairs in the screen complex better when we see the 3D renderings, as well the
scale of the screening room .when the renderings are ready send to all.
Thanks
EFTA00735885
Gary
From: Warwick Wicksman [mailto
Sent: Thu 8/5/2010 6:17 PM
To: Gary Kerney; Doug Schoettle
Cc: Tom Sze; Bryan Oakes; Ken-Hao Hsu
Subject: LS) Update
Gary,
Please review these draft sketches, and let me know if you need me to add any more info before you
present them to Mr. Epstein this weekend! I have not sent them to him yet. Ken-Hao will be sending
you the 3D views later today - as soon as they are ready. I have attached the plan views only.
With these sketches, we have exhausted the re-design services approved Work Authorization 1. These are
intended to be programmatic conceptual drawings. When we move forward with the next phase, we will
refine the layouts, and get into the details of the design.
Please note:
The layouts are based upon previous Option 1, sent 7/28/10.
We have revised the exterior stairs and circulation per our discussions.
We have provided options for the Kitchen windows.
We have revised the road, to reflect the corrected site plan we received yesterday, 8/4/10, with the
relocated service road. Note, this did impact the previous layout a bit.
I added the door at the north end of the east wall of the kitchen addition, per my conversation with Doug
this morning.
The two "partial site plans" attached reflect the two different screening room sizes. One has a 30' screen,
per our original design. The other has a 25' screen, as I discussed with Gary. I recommend someone
mock up the two sizes for Mr. Epstein's review, perhaps in the living room, to confirm the desired screen
size. The screening room area is not completely laid out, as we need to dig into the design of that area in
greater detail, once we set the location and screen size.
If this layout is approved, we can prepare a new proposal to provide complete construction documents,
based on this layout, including all of our consultants. If we need to make minor adjustments, we can
accommodate that as we move forward. If we need to make major adjustments, I can prepare a new
proposal for additional conceptual re-design services.
EFTA00735886
Please call me or email me if you have any questions!
Thanks,
Warwick
Warwick Wicksman, AIA
Principal
Gensler
2500 Broadway
Suite 300
Santa Monica, California 90404
USA
EFTA00735887
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Email Addresses
Document Details
| Filename | EFTA00735885.pdf |
| File Size | 110.2 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 3,172 characters |
| Indexed | 2026-02-12T13:54:36.534527 |