To:
Richard Kahn
Cc:
Stephanie Remingto
•
n
nquez
From:
michael glidden
Sent
Wed 5/22/2019 1:48:47 PM
Subject Re: Punchlist #21
Yes, the road from Mr Wind to the flagpole pool will be first and has already been partially
graded.
Sent from my iPhone
On May 22, 2019, at 9:01 AM, Richard Kahn
wrote:
jee said yesterday that mr windy road is to begin first
is that what you are referring to below?
please update punchlist with dates..
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York, NY 10022
On May 20, 2019, at 1:58 PM, Stephanie Remington
aMISIMMF
wrote:
Perfect. Thank you, Mr. Jeffers.
Stephanie Remington
LSJE, LLC
On Mon, 20 May 2019 at 13:01, Eason Jeffers
<MniiMi
a
wrote:
Good Day Stephanie,
EFTA_R1_01113293
EFTA02286850
I will get in touch with Mike to take some measurements and verify
quantities this week.
Kindest Regards,
Eason Jeffers
President
uantum Vision Construction LLC
On Mon, May 20 2019 10-40 AM
h nie Remington
wrote:
Good day, Mr. Jeffers,
We have plenty of material here for you to begin on the Flagpole
Pool Road. This is the owner's first priority. We look forward to
you beginning this project on Tuesday, May 28.
The owner's second priority is the road going toward the gym all the way up to the
Sun Dial.
His third priority is a small road going from the beach up to the Flagpole.
The owner would like for you to work in this order of priority.
Do you need to return to the island this week to take further measurements or
organize material in preparation for next week's start date?
Please confirm the total amount of all materials needed so that we can preemptively
procure them for future weeks' projects.
Please be in touch with any questions.
Thank you,
Stephanie Remington
LSJE, LLC
On Sun, 19 May 2019 at 19:16, Eason Jeffers
wrote:
Good Day,
Mr Epstein chose a color sample labeled #3 for the flag road. That
sample will use about 21 pounds of color per cubic yard of
concrete with gray cement. Mr. Epstein also mentioned doing two
EFTA_R1_01113294
EFTA02286851
roads in that area, one being the "Beach Road". I need assistance
and confirmation in identifying that road. I also need verification as
to whether this is an added amount to the sample roads or if we
will do this one in lieu of the Sundial Road. Or if the "Beach Road"
is the same as the Sundial Road. I will then be able to send the total
quantities of materials needed along with any changes or
additions/subtractions.
Kindest Regards,
Eason Jeffers
President
uantum Vision Construction LLC
EFTA_R1_01113295
EFTA02286852
Document Preview
Extracted Information
Document Details
| Filename | EFTA02286850.pdf |
| File Size | 167.7 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,643 characters |
| Indexed | 2026-02-12T14:02:25.469690 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.