JE Punch List — October 2 2012
1. Clean Up - make as many barge runs as necessary
2. Equipment and Vehicles
- Sell equipment
- No machinery off the island unless approved
- New seats for gators, progators, beach cleaner - on STT 10/2
- Red Polaris Bike - Power Steering Module for ordered due NM — incorrect part arrived — LV sourcing in FL
- Beach cleaner —de-rust it, clean it — 90% complete
- Lull — non-operational, sourcing a mechanic to complete repair
3. Computers/Phones
- Beach office — no Internet, phone, Time Clock — Jermaine will work at trying to resolve
4. Five Palms
- Furniture — outside furniture in place —
to tie down cushions to resolve wind issues, completed by 10/5
- Picture frame — measurements forwarded to
- 86 x 70
- Mirrored siding — will continue to reglue — possible mural work
- Fiber work/Phone — COMPLETE —Jermaine to provide estimates for "fiber secure box" inside 5 Palms
5. Grotto
- Mattress cover —JE approved buying fabric — fabric ordered — due on site 10/5
6. Berm/Top of Hill
- Hydroseed outside — in progress
7. Triangle
- Must design triangle — awaiting JE direction
- Need to review new palm installation — heli approach with Larry
8. Flagpole Pool Cabana
- Furniture — desk from Paris —JE to select a fabric for seats on site — Sue
- Review bottle palm lights — COMPLETE
- Clock — unit rusted — have order 2 new units - 1 for backup
- Yellow exercise pole —Carlos has completed 1 will work on other this week
- Auto-closer on toilet door —will add to carpentry list
- Hanging of paintings from PB - 10/3
9. Floating Dock
- Jet ski bumpers — complete — reviewing whether this type resolves the issues with the jet skis
- Table/Dock Box - Dock box top investigate possible "rubber material" other possible solution
- Dock boxes — struts should all be replaced — they are all backward — will add to carpentry list
- "walk the plank" option — review material on this & floating dock — "rubberized material"
10. Chillax Room
— Requires furniture piece for electrical/media equipment, reviewing pieces that are stored in PBI, which do not work,
to review other options
11. Chillax Bathroom
- require blue rugs for bathroom & vanity area --
12. Mechanical Building Transformer — on site — to be removed off pallet 10/4, then review installation options
13. Boats
- Lady G — sell — in hurricane storage — offer $60K via JE, Rich to negotiate pricing
- Lady K — sell — survey forwarded to Darren & Rich, suggested price $225,000
- Big N — repair — at AYH dock — have Subbase & Bob Kassner quote — reviewing — Putting together an estimate for
hydraulic hoses and fittings to be completed "in house" — all to be forwarded by 10/8
- Inside cleaning 3 days/2 pers $720.00 supervised by Carlos, after final completion of work — approved JE
- doors/windows in progress — Complete
- cylinders/boxes in PR — EDA on STT 10/5
EFTA_R1_01214945
EFTA02316357
14. AC - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees
15. Transient Surge Protection — due at Tropical 10/9
16. Landscaping — Peter's List
- High road trees
- High road waterfall — details required
- Line all roads with stones
- Pop's Garden — need deer protection — Danny suggested install a motion detector with a strobe light - the deer will
activate the light/sound — JE approved 9/24 — Danny will forward 10/5
- Shade cloth — on L.51 — Peter installed one for JE review
- Clean mess, cut grass; trim all vines, acacia — owner's drive, blue beach, gym — work in progress
- Peter to clean the sides of the road — work in progress
- Black Heli Under Pads — install at top of bike path at MC — not enough on site to complete project. Have located
dealer, require amount to order will review 10/3
- Review growth of sea grape - engineering area
- Hydroseed all pull box areas & engineering
- Take out the single tree in engineering - Peter might want to cut it, so not to damage lines
- PR Coconut Palms — planted at main entrance, blue beach (5), berm, Five Palms, MBR — completed 9/27
17. Roads
- General re-grading of roads — ongoing — Peter
- Betteroads quotes from triangle to crest of road above gym — Asphalt - $71,5000, Concrete - $103,600. Brice to review
details with Better Roads — week of 10/1
18. Library
- AC quote forwarded to Rich Barnett, who had design concerns, awaiting reply from vendor
19. New Employee Bathrooms
20. Gym
- New punching bag — installation of the speed bag on hold 9/22 - per JE until visit
• New front & back doors installation — will complete after visit
21. Beach Office
- complete electrical overall required
- waterproofing/sealing/painting/replace rotten wood required
22. LSJ Mooring — Darren forwarded to Army Corp for final approval — awaiting response
23. Hangar
- Fuel Containment Pad — draft approved, drainage incorporated — survey forwarded to the architect 9/18 - he will
complete the plan by 10/5, submit to DPNR for permitting (Cecile's update as of 9/21)
24. Steel shed — Buck Steel —JE approved mock-up 9/26, changes 9/27— Buck Steel working on the final specs/quote
25. Equipment to be Purchased
- (1) light generator, (2) arms with lights to be hard wired - quote due 10/5
- (1) skid steer on site — require forks, ordered 10/3
- (1) John Deere box and blade — Brice has recommended JD 5101E AWD — loader, scraper, digger, 100hp, enclosed cab
- (1) man-lift
- (2) golf cars — 2 seater
• (1) dump truck — JE approved purchase — 2012 Ford F450 - $15,000 deposit sent 9/25, shipment booked at Tropical
-(1) mini excavator
- (1) Jet ski trailer
26. LSJ Mats — for all locations — ordered 9/22
27. Engineering — start emptying/relocating items in remaining 20 foot containers 10/15
28. Stone Walls — Repair work to replace missing loose stones — Gerry & TJ — Danny to schedule them
29. Part Time Employees —M forwarded information of 2 potential part-time housekeepers to
9/25 —
to schedule meeting with them on 10/3
30. Heli Pad - reinstall windsock to north side of helipad - JE & Larry to review lights and windsock location when next
on site
EFTA_R1_01214946
EFTA02316358
31. Cisterns — need to be cleaned and sealed work to begin 11/1
32. Solar - lights installation COMPLETE - JE does not like the "white light", likes a "soft white" light —JE to review when
on site
• Solar quote reviewed with Rich, submitted to JE 9/17 — now researching line loss on cable, awaiting update
33. Master Bedroom — door sliders require waxing and alignment — to be completed after vist
EFTA_R1_01214947
EFTA02316359
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Document Details
| Filename | EFTA02316357.pdf |
| File Size | 311.4 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 6,616 characters |
| Indexed | 2026-02-12T14:33:10.716543 |