From:
Richard Kahn
Sent:
Thursday, June 30, 2016 5:57 PM
To:
jeffrey E.
Subject:
Fwd: Florida Windows
Attachments:
Screenshot 2016-06-29 15.09.20.png; Untitled attachment 00436.htm; Screenshot
2016-06-29 15.30.04.png; Untitled attachment 00439.htm; Screenshot 2016-06-29
15.09.10.png; Untitled attachment 00442.htm; Screenshot 2016-06-29 15.09.00.png;
Untitled attachment 00445.htm; image003.jpg; Untitled attachment 00448.htm; SAF-
Q16-040 -B Richard Kahn Proposal .pdf; Untitled attachment 00451.htm; SAF-
Q16-040 -B Richard Kahn TakeOff .pdf, Untitled attachment 00454.htm
i know you approved =lready however i wanted to send you all facts that i am aware of so =here are no surprises
1) =indow Functionality
currently you have horizontal rollers =see picture 1 below)
unfortunately =orizontal rollers are no longer made in wood mahogany
Hartman (original bid =rom dan labonte and vendor that supplied LSJ) proposed a wood mahogany =utswing
casement window (see picture 2 below)
bid =as 224,250 before other work, permit fees and gc fees -> projected =ost 298,000
Coastal proposed a wood mahogany tilt and turn window (see =ictures 3 & 4 below)
Proposal was for windows =o tilt and turn in (picture 3) however if you do not like they can tilt =nd turn out
(picture 4)
Scott from Coastal =elieves the tilt and turn in is a better design
negotiated bid is 90,000 before other work and permit fees => projected cost 125,000
2) Next =teps
a) wire requested is 50% of materials and =ermit fees or 32,727.83 along with signed contract
b) shop drawings will be ready in 2 weeks for your =eview
c) file for permit
d) order windows (12-14 weeks)
e) =nstall windows (2-3 weeks)
Projected completion date November 1- 15
3) Other contractor work =equired
Drywall / Stucco repairs
Repaint trim =nd walls around windows
EFTA_R1_01369945
EFTA02369618
Protection
Remove any window treatments and put back when =ompleted
Remove any art and furniture
Alarming of new windows
Removal =nd reinstall of storm shutters
4) Work to be provided by Coastal =indows
Removal of old and installation of new =indows
Bucking / Waterproofing
Rain simulation testing
Scaffolding
Portajon
5) Other Notes
a) Windows will be staged in garage bay =t 358 el brillo
b) Windows (interior and exterior) =ill receive 2 coats of primer and 2 coats of topcoat
c) Hardware for Multipoint lock system (medco or tricoat) =nbsp;- you will choose at time of shop drawings
(satin nickel, oil =ubbed finish)
d) Framing currently is 2.5 inches =hick and new window frames will be 3 inches thick
e)=Currently we do not have screens and they are not proposed in =id
f) Warranty - 1 year on installation and 10 =ears from manufacturer for failure in workmanship
g)=House to be painted after windows are installed (3.4 weeks)
Please advise if ok to proceed
Thank=you
PICTURE =
2
EFTA_R1_01369946
EFTA02369619
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Document Details
| Filename | EFTA02369618.pdf |
| File Size | 137.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,917 characters |
| Indexed | 2026-02-12T15:33:21.089421 |