To:
Gary Kemey
Cc:
Jeffrey Epstein[jeevacation©gmail.com]
From:
Shelley
Sent
Mon 6/14/2010 8:08:41 PM
Subject.•
Re: Island - June
like this
On Jun 14, 2010, at 10:10 AM, Gary Kerney wrote:
no attachment Gary
From:
Sent: Sun 6/13/2010 7:37 PM
To:
Cc:
Gary Kerney; Doug Schoettle
Subject: Island - June
Hi all,
Gary did a great job of putting this together. I've added some comments below and the
specific things I'm taking care of in a separate email.
Thank you,
EFTA_R1_01473745
EFTA02412198
PLANS
Pick up latest marked drawings from Robert's °nice on Tuesday 15th. will make copy and send to Doug this week.
DOCK
Sec attached image.
LIBRARY
Status interior
1.interiors complete by construction
Outstanding issues
1.ceilina treatment
Ion to visit week after next to start painting • work duration 2- 3 weeks • estimated
completion date July 8th
2.cabinet finishes
awaiting panel from Paris. delay now due in this week by the 19th
3.floor finishes
Je to decide on next visit to Island. decision made by July 1st.
Status exterior
1.courtyard paving underway complete by the July 31
2.irragation main line underway complete by July 15
3. wall sconces to replace existing, will get info on them from Robert's office
Outstanding issues
1.landscape plans
a.plants Igala to fill in area behind tiki hut with plants we chose awaiting new images from him
b.irragatiion plans
c.lighting will send sample lighting options via email this week
2.Igala has trees tagged ready for delivery as soon as barge is ready
MASTER SUITE
Status interior
1.const under way ,subject to decisions being made should finish by Oct 31
Outstanding issues
1.steam bench
2.out side shower
3.lites over bed
EFTA_R1_01473746
EFTA02412199
4.lighting in bedroom
5.electrical in bath area
6.tub deck and surround
7.selection of wood floor
8.sourcing thassos slabs
9.powderroom vanity plan
10.shop drawings for stone
i.order ru for bathroom
Status exterior
1.wall under way, complete by Aug 31
Outstanding issues
1.landscape plans..liting irr.
KITCHEN
Status
1.assume we get permit by July 1 should be complete by Nov.31
Outstanding issues
1.kitchen design
2.stair and wall design to master
LAUNDRY
1.assume we get permit July 1 should complete by Oct 31
COTTAGES
1.const underway should complete by Sept 30
Outstanding issues
1.shower design
Other guest cottage to be built in same complex: revisit idea on next visit
MAIN HOUSE REMODEL
Status no estimate to compleation til program complete
1.courtyard side plan final,proceeding
2.roofing proceeding
Outstanding issues
1.north side program
MECHINICAL ELECTRICAL Status under way should complete by Sept 30
EFTA_R1_01473747
EFTA02412200
MECHANICAL DESAL Status under way should complete by Nov 30
POOL/THEATER
1.Gensler allow three months for plans
2.two months for permits Nov 30
3.pool by Mar 31
4. theater by Jun 30
EFTA_R1_01473748
EFTA02412201
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Document Details
| Filename | EFTA02412198.pdf |
| File Size | 155.1 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 2,960 characters |
| Indexed | 2026-02-12T16:26:47.819115 |