To:
J Epstein[jeevacation©gmail.com]
From:
Brice Gordon
Sent:
Wed 9/30/2009 9:49:33 AM
Subject: Re: Zorro Fountain Install
Title: Re: Zorro Fountain Install Winter, last frost ZR mid to end may, start June 2010 would meaning
completion by end of July to Mid August. concrete slab needs 28days to cure
Only access to area is through front doors, which would mean building a ramp over floor etc, sealing hall
area off.
Just thought you would like to have this done before your return to Zorro
Maybe Gary K needs to visit Ranch, to review, stucco, water, etc?
On 9/29/09 10:57 AM, "J Epstein" <jeevacation@gmail.com> wrote:
i seee no reason to break it up
On Tue, Sep 29, 2009 at 8:37 AM, Brice Gordon <IMM
I
wrote:
To JEE
Resubmitting estimate for the fountain installation at Zorro Ranch. Would
recommend that we remove existing fountain and form base this year, Then in
the Spring erect new fountain.
For your consideration
Brice
EFTA_R1_01510433
EFTA02437580
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA02437580.pdf |
| File Size | 52.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 983 characters |
| Indexed | 2026-02-12T16:57:44.832516 |