JEEljeevacat"
Cc:
Brice Gordon
From:
curtis R
Sent:
Tue 4/21/2009 11:01:36 AM
Subject: Re: Mechanical budget revised
04-17-09-LSJ-2 MechBldoUpdate(1) xls
Title: Re: Mechanical budget revised 46.72% paid to date
Please find attached revised Original approved budget — same as I sent you last Friday — with Paid to
date as per yesterday and including Newman & Moll which you approved and will be posted today.
Note : we are still carrying $709,500 in their Budget line item rather than their buy out number of
689,000.00 because there will be extra work needed to terminate the existing building if we do not
proceed with the next phase, whichwe will present to you later this week, as I mentioned below.
Please review this existing budget presented for your approval
Curtis
Original approved budget: $2,330,543.72
Revised budget:
$2,012,685.05
PAID to DATE:
$940,413.62
On 4/17/09 4:33 PM, "JEE" <jeevacation@email.com> wrote
what has been paid to date?
On Fri, Apr 17, 2009 at 3:42 PM, curtis
wrote:
We are currently working on scope and budget for the steel alternate
building as per your request. We have the Engineer coming on Tuesday to
review the condition of the hill.
We will have a new budget for the generator and RO build out next week which should
satisfy future demand and leave room for integration of steel or other
options.
Jeffrey,
Please approve the revised previously approved budget on the
Mechanical building.
This is the existing budget reworked to more accurately represent the
work done and completion of scope -Same as we did for
the Office Pavilion.
Original approved budget: $2,330,543.72
Revised budget:
$2,012,685.05
EFTA_R1_01516635
EFTA02441900
PAID to DATE:
I will report to you for approvals on Trade line items — ONLY if
they
go over Budget.
Emad will monitor Budget as firewall against budget breach.
I DO NOT anticipate any changes except downward in price.
Curtis-
EFTA_R1_01516636
EFTA02441901
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Email Addresses
Document Details
| Filename | EFTA02441900.pdf |
| File Size | 123.3 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 1,985 characters |
| Indexed | 2026-02-12T17:07:38.936742 |