To:
JEE[jeevacation@gmail.comj
From:
curtis
Sent:
Thur 4/30/2009 7:45:39 PM
Subject: Revised Mechanical budget
04-17-09-LSJ- MechBldaUpdate FINAL.pdf
Title: Revised Mechanical budget Jeffrey,
Please find attached Revised Mechanical Building Budget for you approval
The Original Budget was 2,330,543.72 in Green font
Adjustments total
-$317,858.67 n oink font
The revised budget is
2,012,685.05 in Blue font
Paid to date
$940,413.62 in red font
This is the original approved budget updated to show latest cost revisions based on adjustments both up
and down in individual line items showing present cost down by $317,858.67.
NOTES:
1. Newman & Moll will complete their contracted work in less than a month.
2. The contract was bought out for $689,000, leaving $20,500 remaining in the budget. (see line 3120)
3. We recommend using this money towards the 1,000 gallon DPNR required Gasoline tank
containment vessel.
4. This will serve two purposes
A. Satisfy the DPNR for this requirement.
B. Keep Newman & Moll on site a couple more weeks, as we review Final Mechanical Build Out
Options, thus avoiding re-mobilization costs, if we Newman & Moll for future work.
Or
We can reconcile the concrete by deducting $20,500 off this budget now and let them finish.
Curtis
EFTA_R1_01516848
EFTA02442071
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA02442071.pdf |
| File Size | 71.1 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 1,325 characters |
| Indexed | 2026-02-12T17:08:49.196562 |