Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:10484
Month Code: 10
Institution: NYM
Project #:
Title: 2D3S Remove Asbestos
Approval: 7/18/2019
Expiration: 7/18/2022
Funding
Fiscal Year Funded: 2019
Allotted:
$100,000.00
Percent Obligated: 0%
Obligated:
$0.00
Unobligated:
$100,000.00
Construction Status
Completion Percentage: 01%
Progress Status: On Schedule
Est. Completion: 7/18/2022
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 2.00
S&E ManHours this Month: 2.00
Total S&E and B&F ManHours: 2.00
Estimated Hours: 600
Detail Check List
K A&E Services required.
O New construction will result in capitalization of a building or other structure.
O Renovation will result in capitalization of an improvement to an existing building or other structure.
El Asbestos Abatement is required or has been completed.
O ESPC or UESC funded
O FITARA process is required.
Funding
Fiscal Year Funded: 2019
Allotted:
$120,320.00
Percent Obligated: 0%
Obligated:
$0.00
Unobligated:
$120,320.00
Construction Status
Completion Percentage: 01%
Progress Status: On Schedule
Est. Completion: 7/25/2022
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 1.00
S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 1.00
Estimated Hours:
Detail Check List
K A&E Services required.
O New construction will result in capitalization of a building or other structure.
O Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
O FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D3U Replace PBX - Project Approval Received 7/25/19. Procurement Documents Initiated.
Facility Manager:
AW:
Page 1 of 9
EFTA00142424
Region: NER
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:6633
Month Code: 10
Institution: NYM
Project #: 2C4G
Title: 2C4G Replace Doors Phase 2
Approval: 6/7/2017
Expiration: 6/7/2020
Funding
Fiscal Year Funded: 2017
Allotted:
$116,746.48
Percent Obligated: 96.3219%
Obligated:
$112,452.48
Unobligated:
$4,294.00
Construction Status
Completion Percentage: 61%
Progress Status: On Schedule
Est. Completion: 6/7/2020
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 254.00
S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 254.00
Estimated Hours: 3,705
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
Ri Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C4G Replace Doors Housing Unit Phase II -
Number of Doors Installed This Month - 0
The Doors Were Installed On Unit -
Staff Hours Used This Month - 0
Cost of Materials Used This Month - $0
Number of Doors Left to Install On This Project - 14
Facility Manager:
AW:
Page 2 of 9
EFTA00142425
Region: NER
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:6926
Month Code: 10
Institution: NYM
Project #: 2C4T
Title: 2C4T Repair Food Service Coolers
Approval: 7/29/2017
Expiration: 7/29/2020
Funding
Fiscal Year Funded: 2017
Allotted:
$15,200.00
Percent Obligated: 72.772%
Obligated:
$11,061.35
Unobligated:
$4,138.65
Construction Status
Completion Percentage: 17%
Progress Status: On Schedule
Est. Completion: 7/29/2020
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 17.00
S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 17.00
Estimated Hours: 180
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
K Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C4T Repair Food Service Coolers -
Staff Hours Used This Month: 0
Tasks Completed This Month: Revised plan for placement of future condensate unit and how the lines will be run
Tasks Left to Complete: Install Units, Run Lines
Plan Going Forward: Staff will mount units, then we will determine necessity for contractors
Facility Manager:
AW:
Page 3 of 9
EFTA00142426
Region: NER
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:7247
Month Code: 10
Institution: NYM
Project #: 2C5N
Title: 2C5N Replace Food Service Trough
Approval: 10/23/2017
Expiration: 10/23/2020
Funding
Fiscal Year Funded: 2018
Allotted:
$12,000.00
Percent Obligated: 40.233%
Obligated:
$4,827.97
Unobligated:
$7,172.03
Construction Status
Completion Percentage: 99%
Progress Status: On Schedule
Est. Completion: 10/23/2020
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 43.00
S&E ManHours this Month: 0.50
Total S&E and B&F ManHours: 43.00
Estimated Hours: 112
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
K Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C5N Replace Food Service Trough - All financial obligations have been met. Financial closure submitted.
Awaiting NERO business office.
Facility Manager:
AW:
Page 4 of 9
EFTA00142427
Region: NER
Project #: 2C6Z
Approval: 5/16/2018
Funding
Fiscal Year Funded: 2018
Percent Obligated: 99.844%
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
Month Code: 10
Institution: NYM
WO #:8437
Title: 2C6Z MTA-Lead/Asbestos Removal MTA
Expiration: 5/16/2021
Allotted:
Obligated:
Unobligated:
$2,460,000.00
$2,456,164.60
$3,835.40
Construction Status
Completion Percentage: 75%
Progress Status: On Schedule
Est. Completion: 5/16/2021
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 60.00
S&E ManHours this Month: 8.00
Total S&E and B&F ManHours: 60.00
Estimated Hours: 2,400
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
Ei Renovation will result in capitalization of an improvement to an existing building or other structure
El Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C6Z MTA-Lead/Asbestos Removal MTA-
Type of Work Conducted This Month - Demolition: Removed 4 turbines, 1 tank, 1 switch
Staff Hours Used This Month - 8
Cost of Materials Used This Month - 0
Anticipated Time Left On This Project - 2 months
Next Anticipated Work Type - Demolition: Remove Remaining Switches and Demo Turbines
Facility Manager:
AW:
•
Page 5 of 9
EFTA00142428
Region: NER
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:8282
Month Code: 10
Institution: NYM
Project #: 2C8L
Title: 2C8L Replace Basement Elevator Saddle
Approval: 5/17/2018
Expiration: 5/17/2021
Funding
Fiscal Year Funded: 2018
Allotted:
$45,000.00
Percent Obligated: 97.6091%
Obligated:
$43,924.10
Unobligated:
$1,075.90
Construction Status
Completion Percentage: 99%
Progress Status: On Schedule
Est. Completion: 5/17/2021
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 25.00
S&E ManHours this Month: 0.50
Total S&E and B&F ManHours: 25.00
Estimated Hours: 40
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
K Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C8L Replace Basement Elevator Saddle-
Preparing documents for financial closure.
Facility Manager:
AW:
Page 6 of 9
EFTA00142429
Region: NER
Project #: 2C8V
Approval: 6/14/2018
Funding
Fiscal Year Funded: 2018
Percent Obligated: 92.413%
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
Month Code: 10
Institution: NYM
Title: 2C8V Repair Roof
Expiration: 6/14/2021
Allotted:
Obligated:
Unobligated:
WO #:8438
$76,000.00
$70,233.91
$5,766.09
Construction Status
Completion Percentage: 99%
Progress Status: On Schedule
Est. Completion: 6/14/2021
Completed: 8/13/2019
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 17.00
S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 17.00
Estimated Hours: 425
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
K Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C8V Repair Roof- Project work completed, awaiting Financial Closure. Financial Closure submitted to Financial
Management on 4/23/2019.
Facility Manager:
AW:
Page 7 of 9
EFTA00142430
Region: NER
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:9580
Month Code: 10
Institution: NYM
Project #: 2D2P
Title: 2D2P Emergency Replace Heating Coils
Approval: 2/8/2019
Expiration: 2/8/2022
Funding
Fiscal Year Funded: 2019
Allotted:
$99,500.00
Percent Obligated: 24.1778%
Obligated:
$24,057.00
Unobligated:
$75,443.00
Construction Status
Completion Percentage: 66%
Progress Status: On Schedule
Est. Completion: 2/8/2022
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 102.00
S&E ManHours this Month: 2.00
Total S&E and B&F ManHours: 102.00
Estimated Hours: 800
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
K Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D2P Emergency Replace Heating Coils
Equipment Replaced This Month -
The Equipment Services -
Staff Hours Used This Month - 2
Cost of Materials Used This Month - $0
Equipment Left to Replace On This Project - Condensate Pumps, AHU Motors, In-Duct Coils
Next Anticipated Equipment Replacement Site Is - Condensate Pumps
Facility Manager:
AW:
Page 8 of 9
EFTA00142431
Region: NER
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:10473
Month Code: 10
Institution: NYM
Project #: 2D3N
Title: 2D3N Construct Gun Locker
Approval: 7/17/2019
Expiration: 7/17/2022
Funding
Fiscal Year Funded: 2019
Allotted:
$200,000.00
Percent Obligated: 0%
Obligated:
$0.00
Unobligated:
$200,000.00
Construction Status
Completion Percentage: 05%
Progress Status: On Schedule
Est. Completion: 7/17/2022
Completed:
Staff Man Hours
Total B&F ManHours:
B&F ManHours this Month:
Total S&E ManHours: 8.00
S&E ManHours this Month: 8.00
Total S&E and B&F ManHours: 8.00
Estimated Hours: 1,920
Detail Check List
K A&E Services required.
K New construction will result in capitalization of a building or other structure.
K Renovation will result in capitalization of an improvement to an existing building or other structure.
K Asbestos Abatement is required or has been completed.
K ESPC or UESC funded
K FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D3N Construct Gun Lockers - Project Approval Received 7/17/19. RCA Packet prepared and sent for approval
7/26/19.
Facility Manager:
AW:
Page 9 of 9
EFTA00142432
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Document Details
| Filename | EFTA00142424.pdf |
| File Size | 523.3 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 12,840 characters |
| Indexed | 2026-02-11T10:49:12.445170 |