#2-2019 LSJ Punch List
ORIGINAL ITEM NUMBERS
Including Notes from Conf. Call May 29, 2019
JEFFREY'S PRIORITIES
7
Emergency Room-EKG Machine - Anna provided quote for machine JE wants. Need
14
Sam's Place-Furniture (Anna to Choose)
23
GSJ Cottage
Expert Builders-Hoping for barge on Fri. May 31 to take sand & Irg
Concrete mixer, etc to island. Completion date still hoping for end of July
24
GSJ Helipad
Helipad
30
Engineering
Doors-Quote Received from John Bedminster
34
Flagpole Pool
Shade Structure-John Bedminster to be offered bid this week. Bill
liligAssimicatai
43
GSJ RIO
2nd R/O Intake-
45
GSJ New Dock Water Sport Ramp
47
Maurice Brother?
55-62
Cabana's 1-4 Need Cabinet Handles, Pushtabs, Shutter Pulls
shutters, due to arrive PB/Latches on island Maurice to install
73
Sam's Place
Bedroom
74
Sam's Place
Guest Bath
81
Tunnel Roof-...are we patching holes? Yes. 4 sheets installed Carlos picking up more
today
94,95,96
LSJ Cistern 1,2,3
Cistern Pumps-
then ship to us, should arrive around July
97
GSJ R/O
R/O Container
98
GSJ R/O parts
R/O Parts-Parts received including maintenance items for LSJ desal
102
LSJ Library
Wall Sconces-7 of them, started chipping out-needs to be done by
Brine installed May 28
50 more pulls orders for
-•rd
.5 pump ordered May 24. Will take 6 weeks,
30 or 31ff
103, 104, 105, 106
Cabana 1,2,3,4
Dimmers
107
Flagpole Pool
Dimmers
112
Cabana 1
Rope Light -show JE on June 4
143
Old Heavy Machinery
Removal we need barge back (hoping for barge first week
June)
152
AYH / Big N
Fenders-Daphne to FU w/Carlos re quote, must go via Tropical-too
heavy
153
AYH / Big N
Cleats -Repair needs to be done to dock then cleats will work
158
JE Denali
A/C -
[service performed May 29/AC Hose to arrive June 5,
ins
a ion w
TO DO LIST
1
LSJ/GSJ Seth "Mold"-Working on it...gym is an issue
EFTA00286245
2
Cabana's
Motion detector lights
3
LSJ MC Kitchen Banquet
4
Master Bedroom
JE Pillow-Karyna
8
Theater Room Blackout Curtains-
10-11
Housekeeping Washers/Dryers-Arriving Tues. May 28
12
Gym
Air out-airing out daily
13
Cottage Furniture
15
LSJ/GSJ Solar Lights
16
LSJ/GSJ Sun Umbrellas
17
Welder ? Welder Came today May 29, he brought frames, will bring more tomorrow
May 30. Weather permitting he will also start work tomorrow May 30
18
Five Palms
19
Grotto ?
21
New Road
Road Project-Jeffers to do walk through today, May 24, start Tues
r-'11--
May28
22
LSJ Generator Room
Hurricane Shutters
25
26
27
28
29
31
32
Lis""
GSJ Generator
LS1 Tunnel
Wreckshop
HM Storage
LSJ Fuel Room
LSJ/GSJ ?
Waterfall (Tiki or Juggly Park)
Slab
Exhaust
Skin it-Rich to look at bid (Bill Terry)
40x60 Bld.-Bill Terry to look at (Rich)
00x00 Bld. ?
Vents-
Permits
Reefco to order (Rich following up)
33
Gym
Doors -Gym Doors, window, 12 cement bags at Port! Need PU asap! (Mike
will try to get them on LSJ early next week)-Waiting for Barge!
35
LSJ Tiki Hut
Freezer
36
Flagpole Pool
Freezer
37
Dock (LS1 or GSJ) ?
Permits
38
Christmas Cove Moorings
Moorings
39
Old Generators Old Generators
41
42
44
46
48
49
50
52
53
54
63
doors so Brian doesn't have to make them
Five Palms
Five Palms
GSJ New Dock
Bill Terry is aware you want him to sell old generato
Concrete
Dock Expansion
Cables ?
Cables ?-
Heavy Machinery Trencher
LS1 Facilty Entrance
Service Gates
LS1 MB Bath
Shower Tiles
LS1 Main Compound
Mockup Planter
Tunnel Entrance
Tunnel Gate
LSJ Helipad
Heli Service Gate
LSJ Dock
Water Sport Dock Box-
Emailed Paul Gandy, when can he come? Purchase tix
Brian working on this/ Mike looking for Pre-Fab
"Hi
EFTA00286246
64
Christmas Cover
Container shed
65
GSJ Tiki Terrace Small Dock box
66
GSJ Tiki Terrace Wooden Furniture
67
LSJ/GSJ Tiki sheds
Thatch
69
GSJ New Dock 4 Post
71
Barn ? Barn
75
GSJ New Dock Dock Shed
76
LSJ TikiHut
Coral Stone
78
Grotto Steps
79
Tiki Terrance
Brown stain
80
LSJ Dock
Polyurathane
82
Christmas Cove Structure-
85
Emergency Room
WIFI
86
Emergency Room
Computer
87
Emergency Room
Fax
88
Emergency Room
Phone
89
LSJ Island
Emergency PA System
90
GSJ Island
Emergency PA System
91
Cost-U-Less
IT Equipment
92
Chillax 82" TV
93
New WIFI System
LSJ/GSJ WIFI
99
R/O Water
Water Testing -Anna Sent Email from Ocean Systems Labs Today
100
Flagpole
Landscape lighting
101
Info Center
Landscape lighting
108
MC New Planter
Lighting
109
Tiki Waterfall
Pond Fountain
110
Flagpole Pool
Kitchen
111
GSJ Peters Point
Solar Lights/Other
113
Cottage
114
LSJ MB Bath
Shower Drain
115
Sam's Place
Guest Bath
116
Library Air Handler-
weeks)
117
IT Server Room A/C Unit
118-121
Cabana 1,2,3,4,
A/C Unit-Shipping May 31, Goal to install week of June 3
122
GSJ Office
A/C Unit
123
GSJ Bedroom
A/C Unit
124
GSJ Living Space
A/C Unit
125
LSJ Tiki Hut
Tiki Parking
126
GSJ
Solar lights
127
LSJ Landscaping Irrigation
128
LSJ Main Compound
Stone Wall
129
GSJ Stones
Stones
130-133
GSJ
Solar lights
Material to arrive Tues May 28/Work to Start Tues. May 28
Dave will order May 27, Daphne to follow up (custom machine, 6
EFTA00286247
134
GSJ
Orlianders
135
LSJ / GSJ Landscaping
Chemicals
136
LSJ/GSJ Equipment
Quadski-Repair could be done by June 7. If the clutch needs
137
LSJ/GSJ Equipment
Dump Truck
138
LSJ/GSJ Equipment
Fuel Truck / Flatbed
139
LSJ/GSJ Equipment
Mules
140
LSJ/GSJ Equipment
Electric Carts
141
LSJ/GSJ Equipment
ProGator
142
LSJ/GSJ Equipment
Roller
144
GSJ Engineering Shed
Berm
145
Nautica Boat
A/C— Nautica Boat is in boat yard-Completion date is July 20
146
Nautica Boat
Tubes-Jesus w/Offshore Marine to come Fri. May 31 to remove
tube/ship out. FibergliTs repairs will start right after (Carlos)
147
Nautica Boat
Structure
148
Sportis Boat
A/C
149
GSJ Water Front
Sail Boat
150
Christmas Cove Boat debris
151
New Crew Boat Crew Boat
154
PR / Big N
PR Repairs
155
New Barge
New Barge
ders for Barge ordered. 10 week production time.
Should bellErnhip fr
round Aug. 2
156
GSJ MC Kitchen Kitchen
157
GSJ Office
JE Office
159
LS1 Suburban
Accident
160
TWA Hanger
Tracks
161
TWA Hanger
Fridge
162
TWA Hanger
Hanger Doors
163
TWA Hanger
Fire Safety
NOTE: #83 is deleted as it was a duplicate of #73 `Sam's Place Bedroom'
DONE:
5,6
3 Oxygen Tanks (Master Kitchen, Karyna's Office, Ambulance) DONE
77
Library Johnson Wax-DONE
68
LS1 MC Kitchen Doors-DONE
70
Cabana 3
Shower Tile-DONE
9
Theater Room Carpet DONE
51
LS1 MC Kitchen Kick Plate -
72
GSJ Terrace
Chandelier-DONE (Bulbs just need to be installed)
84
LS1 Dock-Nest Cam-DONE
EFTA00286248
More NOTES from Conference Call May 24. 2019
-When will we have water on GSJ to irrigate? Need pipes/parts... Mike to get with Bill Terry on
irrigation (around the house and around the house and pool) Anna/Daphne -Hire someone to
do this.
-40
Flagpole Pool
Awning- No Awning, Just the shade structure
-Fuel Tank Rooms- Dave reduced initial quote by 4500 and will order today (May 24) hopes
to have by June 15th and will then schedule to install-Rich Followed up
EFTA00286249
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Extracted Information
Dates
Document Details
| Filename | EFTA00286245.pdf |
| File Size | 282.8 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 7,273 characters |
| Indexed | 2026-02-11T13:22:42.152626 |