6th floor & Room
■
Movie room — Sony projector not operational need theater /audio company to
check to see if it can be repaired. New proposal 5/24 sent to Rich Kahn
for. JE to approve.
■
Movie room — middle black out shade not getting proper signal from crestron
system needs to be checked. New proposal 5/24/12.
■
JE desk computer speaker wires are they acceptable? Glass table for printer
is this good or do we need to order proper printer table. JE decision.
■
Purchase new patio furniture for terrace? JE decision.
■
Skylight all glass old and discolored needs to be replaced caulking needs to
be changed. RB will provide proposal to get cost for glass change out 5/4
pressure washed looks better. Contractor scheduled to come in to see
sky light for proposal 5/31
5th Floor —
• Hallway needs to be repainted wood trim and doors patched and painted, clean
paint off hardware. RB to provide proposal for JE approval by 6/8.
■
Purchase window shades for rear bedrooms bathrooms and Sarah's, bathroom .JE
approved girls need to purchase, SK or SH.
4th Floor —
• Yoga room— new speakers, Cardio equipment make room more useable for JE
and guests .JE decision how to proceed with room.
■
Yoga room — purchase lighting or change lighting to over head lighting. JE
decision how to proceed.
■
Plaid room bedroom area — needs new leather furniture, or old set needs to be
refinished. Upgrade Flat screen TV to HD and HD cable box and new TV stand
JE decision. If decision to proceed we will provide proposals.
■
Elephant room — replace white carpeting, carpeting is worn and discolored around
all base board areas. Upgrade Flat screen TV to HD and cable box order new TV
stands. JE decision, IF decision to proceed we will provide proposals.
3rd Floor —
• Repair all scratched and damaged woodwork in entrance corridor and
bedroom stair well. RB will get proposal by 6/8 for JE approval.
■
Flat screen TV for bathroom area? JE decision.
EFTA00287140
■
Purchase new window shades in dressing room areas due to discoloration and
damage to existing shades. SK or SH to purchase.
■
Re paint over Master bathroom ceiling mural? JE decision
2nd Floor —
• Kitchen area — replace old blue carpet on floor with proper kitchen flooring. JE
decision.
■
Hidden office behind library - is this room becoming a t.v. area as J.E. discussed
or breakfast room. I removed all office computer & fax equipment. JE decision.
1" Floor —
• Replace entrance spotlights with proper fixtures for silk/screen oriental paintings
JE decision & approval and design? RB repaired light fixtures several times
fixture on left side beyond repair.
■
Replace cocoa mat Front door? JE decision
■
Lounge area Sue's office purchase new furniture. SH to purchase.
■
Main Grand Stair case have Ion touch up Venetian plaster walls door entrance to
elevator corners damaged. Ion working new paint concept.
■
Entrance stairs — install new carpet runner on stairs? , have stone stairs front door
landing cleaned again. Change lighting scheme in entrance. JE decision for
runner & lighting .RB to provide company to clean stone Port Morris
scheduled to see floor for proposal 10:30 am 5/31
■
Pantry corridor and kitchen area — replace vinyl wood floor. JE decision.
■
Re finish front entrance wood doors .RB proposal for JEE approval. Proposal
for$10.000.00 same people who did Lutnick front door. Sent proposal to JE
5/30 for approval. JE rejected proposal Merwin to wax 6/8
■
Repaint kitchen and pantry corridor. JE decision.
■
Dining room — Repaint change carpet? JE decision.
Cellar Area —
• Laundry room — Re paint touch up walls, doors, and trim. RB to do 6/5
■
Lynn and Jojo's apartment — repaint entire apartment, kitchen area install all new
appliances on order, and kitchen exhaust system purchase all new furniture and
carpet. RB & SK work in progress.
■
Catering kitchen — repaint entire room, and cellar hallway walls RB to have
Michael to give proposal for paint.
Mechanical —
• Replace Stand pipe sprinkler alarm panel defective beyond repair. RB to get
proposal this system is original to house ,and is not supported by ADT.Their
is only one technician in ADT that is familiar with this control panel he had a
used control board by luck on his repair truck and fixed the panel, it worked
for a few months . If I plug in it will alarm randomly and send alarms to all
house key pads and disturb everyone in the middle of the night. In Progress
electrical design engineer to review system week of 3/20 .ADT sent email with
EFTA00287141
projected costs .I will look into other alarm companies. Called Sawyers
sending zone lists. Sawyers to do walk through with electrical engineer week
of 4/16 Sawyers will have a proposal by 5/15 called sawyers will have
complete proposal by 6/4
■
Drain and clean cooling tower sump order suction baffles and filter screens for
sump from BAC. RB seasonal maintenance RB to provide proposal to order
parts needed to be done due to age of cooling tower sump. It will need total
replacement in the near future. JE approved parts arrived 04/09/12
Installation 6/8.
■
Replace siemens steam pre heat valves on AC-2, AC-4.RB found during steam
pre heat operation valves not holding set points. RB will provide proposal for
replacement of valves needs to be done before next heating system this
system operates and is valved on when outside temperatures fall below 32
deg .F tested valves ok need Siemens to come in to do programming. Siemens
Scheduled for 6/7 or 6/8
■
Perform NYCFD .standpipe sprinkler 5 yr test with licensed fire suppression
plumber RB received proposal for$1800.00 scheduled for August 24th 7:30am
■
Paint front of house all black steel bars on tree pits, terrace guards, 2nd fl., 3rd fl.,
rear of house set back railings. RB sent proposal to JE rejected .JE requested
JoJo and Merwin will paint.
■
Test emergency generator ATS switches EPP and emergency life safety
system. RB to provide proposal for JEE approval for electrical engineering
Test Company to assist in testing. We should run in emergency mode at least
once per year. Scheduled for June, will give cost for project.
■
Replace fan motor for bedroom stair case ac-unit AC-6, replace fan motor for unit
heater for court yard heater, RB removed motor having problem finding
replacement motor manufacturer discontinued line searching for
replacement I will forward price when I find proper motor unit failed due to
age. RB to remove blower 6/4 and bring to Castellano motor for proper
sizing.
■
Server room ac unit needs to be re piped and tied into cooling tower condenser
water system and taken off domestic water.RB reviewing nearest condenser
water piping for tie in I will give cost to resolve problem.this is not legal in
NYC. Work in progress.
■
Main House Chiller #1 old Carrier needs to be up graded to high efficiency chiller
to meet the new load demands of the building. Called AD Winston to start the
engineering of chiller #1 re lacement. JE will call AD Winston Mauro
Palladino at
for details of project.
EFTA00287142
■
Otis Elevator exhaust fan for main passenger car needs to be changed to a quiet
slow speed fan. Called Otis service rep to come to see elevator on 6/5
EFTA00287143
Document Preview
PDF source document
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
This document was extracted from a PDF. No image preview is available. The OCR text is shown on the left.
Document Details
| Filename | EFTA00287140.pdf |
| File Size | 264.4 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 7,357 characters |
| Indexed | 2026-02-11T13:22:49.663121 |