Punch List —April 28. 2012
1. Flagpole Pool Cabana -
- Fabric - on site, orange piping & pillow for sofa/chairs - via JE's direction to be completed in May
- Furniture - review another piece of furniture - Sarah
- Palm lighting —JE finalized design 4/24
2. Main compound -
- Landscaping — plant goat's foot vine on hillside
- repairing of coral stone deck areas
- Coral stone thresholds in guest rooms need to be cut
3. Five Palms-
- Interior Wall requires finishing — will be completed once doors are installed - awaiting door installation date
- Electrical — generator from Kite to be relocated with remote starter
- Floor - material on site 4/25
- Exterior Door Shutters - require design and finish
-Interior Doors — due on site 5/21
- Painting —final outside coat to be completed once all work is finished
- Outside coral stone seat — JE has given direction to Tom
- Fire Pit —requires construction with Mexican tile on floor
- Ramp and Road Transition — complete
- Molyneux Canvas —to be placed on stretcher/backed and installed to ceiling, boarded with cornice molding
(approx 6 to 8 inches wide) & painted white — subcontractor required for installation
- Furniture — sofa for Five Palms, rug
X 2 cannonball lamps, bronze lamp
- Mirrors due on site 4/30
- Photos - for Five Palms
- Built in Cabinets/shelves — to be completed by Bill — Hinges due NYC 4/27
- Landscaping— level dirt - continuing
— Relocate grasses —JE has selected location
- Concrete benches — need to be repositioned
- Lights— outside light boxes on back and front walls to be covered over
- Light parrots and building — from roof line (rectangular 24 X10)
- Lighting to be installed in ceiling — complete
- Desk —to be sent from NYC — due to be picked up 4/26 to be shipped to Tropical
- Mirrored siding — due on site 5/3
4. Grotto -
- Concrete pour — completion expected 4/27
- Road to Pavilion — road to mimic Starfish Market - 4/27
- Road - to be extended via JE direction
- Lighting pavilion — JE to advise on lighting in pavilion and landscape lighting
- Pavilion — painting to begin 4/30
- Landscaping — more dirt required on left hand side as you look down, then hydroseed
- Shutters/generator doors/storage doors — to be completed by John
S. Hangar —
- Concrete Floor - grinding ongoing
- Painting — interior paint selected —waiting on JE direction on Blue color
painting floor — completion 5/3 — delayed due to power issues
- Silver Polaris - from al relocated to hanger, purchase new vehicle for LSJ
6. Steel Shed — ABC Concepts proposal forwarded to JE 4/24
7. Triangle — needs to be reconfigured, with more dirt on top and less around base
Tree from lower road and engineering to be relocated - complete
EFTA00583506
8. Entry Tree Lights— lights on site
9. Solutions for Generators— Sound proofing solution forwarded to JE
10. To of hill — CLEAN UP — remove rocks - ongoing, and hydroseed
11. Tiki - Shields — ETA mid May
12. Sunken Garden Berm — crusher runs - place inside berm area
- 50 planter boxes require construction — size to be determined by JE
- relocate tie downs to engineering — complete
- berm boxes' plantings
13. Engineering—Clean Up —area needs to be leveled and metal shed to be laid out
- Landscaping — planting Sea grape
14. New vehicles — two more Polaris bikes (800's) — Larry/Brice
15. Dock —
- Entry — redo entry — Brice to source dock wood locally
- Decking - discuss pressure treated timber/carpeting
- Extension - design required
- Floating Dock— design required
- Jet ski Docking - review
- Table— final size/design to be determined — coral stone top — Bill
- Old floating dock — move to high road
16. Mooring Permit — estimate to place anchors forwarded to JE 4/10 - awaiting direction
17. Telephone system — remove/add speed dial — awaiting programming disc — due 4/27
18. Gates - to hide engineering both at top and bottom of hill
- Columns —JE changed design — work continues
- Construction — Gates ready to be hung
19. Guest House at Beach 3 — sited, needs to be roughed out — start 4/21
20. Kite House — review of wooden outside furniture - Sarah
21. Chillax Room — requires furniture piece for electrical/media equipment — Sarah
22. Chilax Bathroom - requires blue rugs for bathroom & vanity area - Sarah
23. Mechanical Building
- Replacement Transformer — approved to purchase, forward to Rich K, as of date no response
24. Boats
- Midnight Express — 4/2 approved to purchase Yamaha 300 motors —bids will be forwarded 4/27
- ship existing motors to FL, LV to sell — crated, expected to ship 5/4
- PRD — sell
- Lady G — sell
- Big N - sell
- Calypso — refurbish
25. Sundial —
26. Hydro seeding— as much as possible especially when it rains
27. Mr. Wind statue — stone veneer work — completion expected 5/2
28. Gym Road - road material & holes in stone wall need to be added for water drainage
29. Master Suite -
- landscaping— bananas by bedroom
- maintenance —bedroom door to outside to be adjusted and lock added
30. Entry basket - bougainvillea bought for basket and dirt put in the front of the basket
31. Floating dock - redesigned
32. Mirror arrival — expected to arrive at Tropical FL Monday 4/30, sailing 5/2 or 5/4 to STT
33. Additional road by Triangle
34. Move beach trees
35. Place bench concrete
EFTA00583507
Document Preview
Document Details
| Filename | EFTA00583506.pdf |
| File Size | 154.9 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 5,340 characters |
| Indexed | 2026-02-11T22:50:14.013207 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.