JE Punch List —July 27. 2012 Directive Updates
1. Clean Up - make as many barge runs as necessary
- Top of Desal plant
- Engineering
- Cleaning the shops — ongoing
2. Equipment and Vehicles
- Sell equipment
- Bikes should be ready to be sold — no sales without JE approval — bike sale list forwarded to Brice 7/24 - will
be forwarded for JE approval
- No machinery off the island unless approved
- Buy new Kawasaki bikes and mules — (5) 2012 Kawasaki 750 EPS and (2) 2012 Kawasaki Mule 4010 purchased
— wire sent 7/26
- Kawasaki parts order submitted twice — awaiting direction
- Remove all concrete trucks and cement hopper no later than 7/27
- Cement hopper scheduled to be transported to the Heavy Materials - St. John yard for storage -
storage is free — crane/tractor/low boy rental $4,300 — pending Boyson reschedule and JE approval —
Boyson unable to provide rescheduling information until after 7/30
- Concrete trucks — transported to Heavy Materials STT 7/24 — storage free — transport $300 —
per Brice approved by JE - COMPLETE
3. Computers
- Buy new computers — 2 Macs Desktops & 1 Laptop — Captains' Office - ordered
4. Five Palms
Internet/Phone Switch installed — broken fiber discovered 7/24 — Danny repaired 1 of 2 — replacement
termination tips arrived 7/27 — Danny has them in his possession
- Phone set up left of desk — switch installed 7/20 - COMPLETE
- Wireless inside only — as of date 7/10 via JE — installed 7/24 - COMPLETE
- Computer — as of date 7/10 not required via JE
- Exterior Door Shutters — estimate forwarded to JE 7/12 - $2,865.00 - awaiting direction
- Painting - outside to be completed via JE direction
- Inside to be completed via JE direction — Ion
- Tapestry Molding for Ceiling — Ion
- Furniture — outside furniture ordered — sailing 7/27 - EDA to STT 7/31
- Piano Bench — mounted 7/18 - COMPLETE
- Piano — schedule to re-tune week of 8/15
- Picture Frame — measurements forwarded to Sarah - 86 x 70
- Mirrored siding — liquid nails — will cover entire panel with glue when the next one falls off
- Transformer Protection Wall — should be built - work to start 7/30
- Floor Gold Lamps - electrical wiring needs to be replaced - COMPLETE
- Fire pit — fix — a new propane tank was installed but it is now empty - Danny and Brian suspect there is a leak -
they will replace the piping
5. Grotto
- Furniture — put back in grotto
- Curtains — more curtains ordered — cream for the bed at the base of the grotto — expected to arrive to Zorro
to take to LSJ 7/31
- Genset wiring — COMPLETE - Danny reviewing auto start from Kite House — need to purchase part from
Electronics Unlimited — out of stock — Danny to contact vendor for status on restock
6. Berm/Top of Hill
- Stone threshold needs total re-do — must be level and straight — commenced 7/27
- Boulders — Jules to finish boulder work — once stone threshold completed
- Electrical — Low voltage transformer in place - placement & connection of lights - COMPLETE
EFTA00584522
- Main transformer on site — installed 7/19 - COMPLETE
7. Engineering/Maintenance Yard
- Steel Shed concrete pad — COMPLETE
- Metal Sheets - on old building replaced — COMPLETE
- Power sanding/rust removal complete - painting in progress
- Engineering Storage & Shelving — concrete wall repaired 7/27
- Landscaping — quote for Sea grapes forwarded to JE 7/12 - awaiting direction
- Landscaper(s) to travel to Josephine's nursery (Coral Bay) — trip cancelled
- Engineering water boundary — Jules - COMPLETE
8. Triangle -
- Peter transplanted 3 palms from engineering per JE directive 7/26 - COMPLETE
9. Flagpole Pool Cabana -
- Furniture — investigate new desk, new furniture more like Pool Cabana PBI
- relocate orange sofa to Media Room
- Check water pressure in shower — Danny discovered the pressure equalizer tank was not pressurized — he
pressurized and adjusted — COMPLETE
10. Floating Dock
- Jet ski bumpers -ordered - presently on backorder - Overton will email Carlos when they are shipped out
- Table/Dock Box
- Dock box handles - COMPLETE
- Dock box top to be resurfaced
- Dock floors — staining needs completion — COMPLETE
- Swim Ladder — direction from JE on placement required
- Dive Platform — require construction details
- Wooden Bumpers — to cover concrete stripping — COMPLETE
- Painting — Railing, Cross Brackets & Robe Hooks - COMPLETE
11. Entry Tree Lights
— Lights on site, electrical installation - COMPLETE
12. Solutions for Generators
— Soundproofing Installation — back wall and door — COMPLETE —JE is concerned may not be adequate for
deep sound penetration
13. Tiki
— Shields left Papua 7/24 — EDA in FL 7/29 — Lund & Pullara will clear and transport to Tropical
14. Kite House
— relocation of outside furniture from 5 Palms once new 5 Palms furniture on site
15. Chillax Room
— requires furniture piece for electrical/media equipment — Sarah
16. Chillax Bathroom
- require blue rugs for bathroom & vanity area — Sarah
17. Mechanical Building
- Replacement Transformer — estimated date to be shipped from factory (Illinois) 8/21
18. Boats
- Lady G — sell — in hurricane storage 7/18
- Lady K — sell — survey forwarded to Darren & Rich, suggested price $225,000
- Big N — repair — will go to Subbase Drydock after 8/7
19. Timers
- Review installing timers on air conditioners, irrigation water systems, and lights
- Set all air conditioning to 85 degrees (no need to keep anything cooler)
- No irrigation week of 7/23
20. Beach lighting
— per JE, replace existing transformers for the beach lighting of palms around the salt pond and beach
EFTA00584523
21. Transient Surge Protection — will review and forward estimate ASAP - Danny
22. Ice Maker — on LSJ 7/25
23. Landscaping
- Soil material on site - soil removed from beds 7/16 — area replanted - COMPLETE
- Finish sundial corner (trees, stones, hydro-seed) — more trees transplanted, per JE - COMPLETE
- Clean up areas marked in paint - COMPLETE
- Prepared banana area for pineapples 7/24 -100 pineapples picked up and planted 7/26 - COMPLETE
- Plantings - removed the plantings that are anywhere near the bottle palms, per JE - COMPLETE
24. Solar lights — ordered - place every 30 feet — EDA on STT 7/28
25. Roads — grade - Jules work continues
26. Library
- Lights on bookshelves need attention — Danny to repair
- Temperature — STABLE
- Repair hanging wooden louver — COMPLETE
27. Main hill
— Asphalt path — pour asphalt ends in concrete — top and bottom have been formed, concrete poured at top
and bottom — stones placed at bottom and top 7/25 - COMPLETE
28. New Employee Bathrooms
29. Gym
- New punching bag — arrived at 7P, — will come down on the next plane trip
- Wiring — balance cables on site - final tidy up 7/20 — COMPLETE
- Audio cables purchased — installed 7/20 — COMPLETE
- Yoga room air does not work — Danny replaced the batteries - COMPLETE
30. Benches
31. Danny Vicars — boat driving lessons in progress
32. Beach Office
- complete electrical overall required
- waterproofing/sealing/painting/replace rotten wood required
33. LSJ Mooring — Darren will forward to Army Corp for final approval — 7/12
34. AYH Dock — re-sanding/staining of Nanna dock - COMPLETE
35. Main Compound Cistern — Demo work complete - confirmed multi leaks - repair work required
36 Hangar
- Jermaine to redo internet at hangar — forward quote for rack enclosure 7/24 — awaiting approval
- Fuel Containment Pad — draft approved with drainage incorporated, waiting for updated plan
37. Woodshop Tunnel — floor needs to epoxy — clearing area
38. Master bedroom area — add many lights in master bedroom planter — Danny 7/26 — COMPLETE
39. Little C — new engine has a blown head — Fred (Offshore Marine) came out 7/27 — two holes in the new
engine block — one is above the oil filter and the other is above the shift assembly — Fred to contact Brice
EFTA00584524
Document Preview
Document Details
| Filename | EFTA00584522.pdf |
| File Size | 212.7 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 7,938 characters |
| Indexed | 2026-02-11T22:50:27.048837 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.