Jeffrey,
The following proposal is based on Gensler schematic drawings dated 2/26/09.
A revised Budget will be issued after the Design Development Plans are submitted by the
Architects and again after the Construction Documents are submitted,
The attached schedule shows the critical path of information & construction in red. A new
Schedule will be submitted with each new Budget.
General Conditions
$135,400.00
Sitework
$599,900.00
Concrete
$3,026,120.00
Masonry
$590,000.00
Metals
$392,410.00
Wood
$770,000.00
Moisture / Thermal
$523,930.00
Doors and Windows
$615,320.00
Finishes
$882,000.00
Specialties
$44,500.00
Special Equipment
$754,000.00
Furnishings
$0.00
Special Construction
$350,000.00
Mechanical
$1,100,000.00
Electrical
$725,000.00
$10,508,580.00
EFTA00731173
Document Preview
Extracted Information
Dates
Document Details
| Filename | EFTA00731173.pdf |
| File Size | 35.6 KB |
| OCR Confidence | 85.0% |
| Has Readable Text | Yes |
| Text Length | 811 characters |
| Indexed | 2026-02-12T13:53:27.200131 |
Related Documents
Documents connected by shared names, same document type, or nearby in the archive.